BRIDGE REPAIR SH-58: OVER AN UNNAMED CREEK 1.1 MILES SOUTH OF THE SH-45 JCT.
- Let date
- Thursday, September 20, 2012
- Contract
- 120316
- J/P numbers
- 28705(05)
- District
- Division 6
- County
- Alfalfa
- Highway
- Limits
- BRIDGE REPAIR SH-58: OVER AN UNNAMED CREEK 1.1 MILES SOUTH OF THE SH-45 JCT.
- Project number
- BRFY-202C(006)3B
Bidders 7
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $109,900 | ||
| 1 | B & B CONSTRUCTION SERVICE J.T., INC. Low bidder | $124,779 | +13.5% | |
| 2 | Bridges, Inc. DBA Scudder Bridge Co. | $142,560 | +29.7% | +14.2% |
| 3 | GIBSON & ASSOCIATES, INC. | $154,494 | +40.6% | +23.8% |
| 4 | SCR CONSTRUCTION CO., INC. | $170,384 | +55.0% | +36.5% |
| 5 | B & B BRIDGE COMPANY, LLC | $171,789 | +56.3% | +37.7% |
| 6 | TOPCOR SERVICES, LLC AND SUBSIDIARIES | $187,214 | +70.3% | +50.0% |
| 7 | PBX Corporation | $248,787 | +126.4% | +99.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 B & B CONSTRUCT… | #2 Bridges, Inc. D… | #3 GIBSON & ASSOCI… | #4 SCR CONSTRUCTIO… | #5 B & B BRIDGE CO… | #6 TOPCOR SERVICES… | #7 PBX Corporation |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 501(G) 6309 | CLSM BACKFILL | 20 | CY | $300.00 | $150.00 | $150.00 | $200.00 | $145.00 | $250.00 | $150.00 | $388.00 |
| 2 | 504(A) 1304 | APPROACH SLAB | 128.8 | SY | $250.00 | $255.00 | $350.00 | $375.00 | $380.00 | $380.00 | $330.00 | $628.00 |
| 3 | 510(C) 6139 | SLOPE WALL (6") | 248 | SY | $125.00 | $145.00 | $160.00 | $218.00 | $180.00 | $250.00 | $395.00 | $353.00 |
| 4 | 513(B) 6019 | CLASS B BRIDGE DECK REPAIR | 60 | SY | $350.00 | $425.00 | $300.00 | $205.00 | $550.00 | $385.00 | $400.00 | $229.00 |
| 5 | 823 8480 | (SP)PORTABLE TRAFFIC SIGNAL SYSTEM | 1 | LSUM | $3,750.00 | $9,100.00 | $12,500.00 | $9,000.00 | $10,000.00 | $8,195.00 | $8,000.00 | $18,557.00 |
| 6 | 876(A) 8482 | (PL)TRUCK MOUNTED ATTENUATOR | 15 | SD | $20.00 | $15.00 | $10.00 | $11.00 | $30.00 | $10.00 | $100.00 | $10.00 |
| 7 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $3,500.00 | $8,000.00 | $8,000.00 | $8,000.00 | $13,000.00 | $7,250.00 | $3,000.00 | $15,000.00 |
| 8 | 882(A) 8306 | PORT.CHANGEABLE MESSAGE SIGN | 15 | SD | $10.00 | $10.00 | $10.00 | $11.00 | $30.00 | $10.00 | $150.00 | $10.00 |
| 9 | 641 1399 | MOBILIZATION | 1 | LSUM | $12,000.00 | $10,000.00 | $16,000.00 | $18,500.00 | $17,000.00 | $17,000.00 | $5,000.00 | $25,000.00 |