RESURFACE (ASPHALT ) SH-5: FROM 8.1 MILES EAST OF SH -54, EXTEND EAST. PROJECT LENGTH = 3.05 MILES
- Let date
- Thursday, February 16, 2012
- Contract
- 120122
- J/P numbers
- 29156(04)
- District
- Division 5
- County
- Tillman
- Highway
- Limits
- RESURFACE (ASPHALT ) SH-5: FROM 8.1 MILES EAST OF SH -54, EXTEND EAST. PROJECT LENGTH = 3.05 MILES
- Project number
- STPY-271B(001)3P
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $782,507 | ||
| 1 | T & G CONSTRUCTION, INC. Low bidder | $743,551 | -5.0% | |
| 2 | DOBSON BROTHERS CONSTRUCTION CO. | $796,102 | +1.7% | +7.1% |
| 3 | APAC-CENTRAL, INC. | $811,364 | +3.7% | +9.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 T & G CONSTRUCT… | #2 DOBSON BROTHERS… | #3 APAC-CENTRAL, I… |
|---|---|---|---|---|---|---|---|---|
| 1 | 411(C) 5950 | SUPERPAVE, TYPE S4(PG 76-28 OK) | 9,254 | TON | $70.00 | $72.30 | $80.85 | $80.03 |
| 2 | 412 5267 | COLD MILLING PAVEMENT | 16,329 | SY | $6.00 | $3.10 | $1.69 | $1.33 |
| 3 | 856(A) 8530 | TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 49,620 | LF | $0.6500 | $0.3500 | $0.3700 | $0.3500 |
| 4 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $4,500.00 | $6,500.00 | $1,960.21 | $31,681.38 |