RESURFACE (ASPHALT ) US-64: FROM 5.0 MILES EAST OF US -83, EXTEND EAST. PROJECT LENGTH = 7.00 MILES
- Let date
- Thursday, February 16, 2012
- Contract
- 120080
- J/P numbers
- 27576(04)
- District
- Division 6
- County
- Beaver
- Highway
- Limits
- RESURFACE (ASPHALT ) US-64: FROM 5.0 MILES EAST OF US -83, EXTEND EAST. PROJECT LENGTH = 7.00 MILES
- Project number
- STPY-104B(073)3P
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $1,280,125 | ||
| 1 | J & R SAND COMPANY, INC. Low bidder | $1,363,941 | +6.5% | |
| 2 | DOBSON BROTHERS CONSTRUCTION CO. | $1,455,656 | +13.7% | +6.7% |
| 3 | HIGHWAY CONTRACTORS, INC. | $1,457,377 | +13.8% | +6.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 J & R SAND COMP… | #2 DOBSON BROTHERS… | #3 HIGHWAY CONTRAC… |
|---|---|---|---|---|---|---|---|---|
| 1 | 202(D) 0184 | UNCLASSIFIED BORROW | 1,200 | CY | $5.00 | $6.00 | $7.80 | $8.00 |
| 2 | 202(H) 0185 | EARTHWORK | 1 | LSUM | $20,000.00 | $20,000.00 | $15,291.71 | $25,000.00 |
| 3 | 230(A) 2806 | SOLID SLAB SODDING | 28,750 | SY | $2.25 | $2.00 | $2.37 | $2.00 |
| 4 | 407(B) 0250 | TACK COAT | 7,060 | GAL | $2.25 | $2.00 | $3.00 | $3.65 |
| 5 | 411(C) 5960 | SUPERPAVE, TYPE S4(PG 64-22 OK) | 13,200 | TON | $75.00 | $86.00 | $89.50 | $89.79 |
| 6 | 411(I) 6310 | SUPERPAVE, TYPE S4(PATCH)(PG64-22OK) | 500 | TON | $100.00 | $115.00 | $100.00 | $120.00 |
| 7 | 856(A) 8530 | TRAFFIC STRIPE(MULTI-POLYMER)(4" WIDE) | 129,360 | LF | $0.7000 | $0.2800 | $0.5800 | $0.3400 |
| 8 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $8,000.00 | $9,000.00 | $15,258.12 | $6,500.00 |
| 9 | 641 1552 | MOBILIZATION | 1 | LSUM | $35,000.00 | $27,200.00 | $20,000.00 | $43,797.65 |