SAFETY IMPROVEMENTS (FIBER OPTIC CABLE) US-270/US-271: FROM THE CITY OF WILBURTON TO THE CITY OF POTEAU. PROJECT LENGTH = 41.790 MILES PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED , HOWEVER, BIDDERS WILL BE REQUIRED TO PROVIDE VERIFICATION OF EXPERIE

Let date
Thursday, January 19, 2012
Contract
120066
J/P numbers
28128(47)
District
County
Latimer, Leflore
Highway
Limits
SAFETY IMPROVEMENTS (FIBER OPTIC CABLE) US-270/US-271: FROM THE CITY OF WILBURTON TO THE CITY OF POTEAU. PROJECT LENGTH = 41.790 MILES PREQUALIFICATION FOR THIS PROJECT HAS BEEN WAIVED , HOWEVER, BIDDERS WILL BE REQUIRED TO PROVIDE VERIFICATION OF EXPERIE
Project number
BTOP-239B(001)

Bidders 8

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$2,784,935
1 AMERICAN DIRECTIONAL BORING,INC. Low bidder $1,906,450 -31.5%
2 B & H CONSTRUCTION, LLC. $2,703,652 -2.9% +41.8%
3 ROHL NETWORKS, LP $2,789,528 +0.2% +46.3%
4 TRANS-TEL CENTRAL, LLC $3,263,910 +17.2% +71.2%
5 WILDCAT CONSTRUCTION CO., INC. & SUBSIDIARIES $3,268,238 +17.4% +71.4%
6 THE FISHEL COMPANY $4,603,512 +65.3% +141.5%
7 MASTEC NORTH AMERICA, INC. $5,020,785 +80.3% +163.4%
8 MICHELS CORPORATION $10,016,685 +259.7% +425.4%

Bid tab: unit prices 25 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 AMERICAN DIRECT…#2 B & H CONSTRUCT…#3 ROHL NETWORKS, …#4 TRANS-TEL CENTR…#5 WILDCAT CONSTRU…#6 THE FISHEL COMP…#7 MASTEC NORTH AM…#8 MICHELS CORPORA…
1201(A) 0102 CLEARING AND GRUBBING1LSUM $30,000.00 $1,000.00 $10,000.00 $4,275.00 $56,458.32 $50,000.00 $35,480.31 $45,000.00 $50,000.00
2221(C) 2801 TEMPORARY SILT FENCE2,000LF $2.50 $8.70 $5.00 $3.90 $4.64 $5.00 $6.64 $5.00 $15.00
3230(A) 2806 SOLID SLAB SODDING2,000SY $2.50 $7.08 $5.00 $3.60 $4.28 $3.50 $6.13 $25.00 $15.00
4509(B) 0321 CLASS A CONCRETE15.36CY $650.00 $1,041.57 $500.00 $250.00 $148.56 $1,200.00 $2,656.37 $950.00 $1,200.00
5802(A) 8316 3" GALV. STEEL ELECTRICAL CONDUIT EXPOSED1,350LF $20.00 $61.00 $50.00 $54.30 $64.25 $45.00 $91.95 $100.00 $100.00
6802(A) 8318 3" GALV. STEEL ELECTRICAL CONDUIT PUSHED OR BORED100LF $25.00 $46.90 $50.00 $62.50 $142.90 $60.00 $57.68 $115.00 $300.00
7802(C) 8551 1 1/2" HIGH DENSITY PE PIPE - BORED14,840LF $15.00 $14.68 $30.00 $50.80 $18.29 $14.00 $28.05 $48.00 $120.00
8802(C) 8556 1 1/2" HIGH DENSITY PE PIPE - TRENCHED67,285LF $3.50 $8.68 $7.76 $14.95 $12.53 $14.00 $27.52 $23.00 $52.00
9802(C) 8565 1 1/2" HIGH DENSITY PE PIPE - PLOWED144,828LF $2.00 $3.13 $4.00 $3.55 $6.71 $9.10 $6.71 $11.50 $25.00
10803(B) 8135 GROUND BOX (R3248)54EA $2,500.00 $1,166.93 $1,000.00 $880.30 $1,054.85 $1,800.00 $3,271.35 $1,800.00 $1,500.00
11803(B) 8150 GROUND BOX (B2-48)24EA $3,000.00 $1,670.70 $1,500.00 $1,276.06 $1,723.51 $2,000.00 $5,314.71 $1,500.00 $2,000.00
12804(B) 2916 REINFORCING STEEL288LB $2.25 $14.00 $1,736.00 $3.60 $1.74 $1.10 $6.13 $35.00 $30.00
13818(A) 8730 (SP)FIBER OPTIC CABLE, 96 SMF238,862LF $6.33 $0.8500 $0.4200 $0.8800 $0.9300 $0.8000 $1.54 $1.25 $0.8500
14818(A) 8739 (SP) FIBER OPTIC CABLE, 48 INDOOR/OUTDOOR PLENUM1,200LF $8.66 $1.00 $8.33 $0.8800 $8.42 $0.4500 $31.00 $22.00 $20.00
15818(B) 8755 (SP)FIBER OPTIC PATCH PANEL, 96 PORT4EA $1,600.00 $1,282.00 $7,500.00 $1,653.80 $1,597.23 $10,000.00 $2,945.32 $2,500.00 $20,000.00
16818(D) 8740 (SP)FIBER OPTIC CABLE TERMINATION192EA $100.00 $42.90 $208.33 $36.05 $48.51 $100.00 $46.94 $39.00 $80.00
17818(F) 8370 (SP) SHIELD ISOLATION PEDESTAL5EA $325.00 $672.50 $2,000.00 $101.40 $77.98 $250.00 $366.61 $1,300.00 $750.00
18818(F) 8375 (SP) SHIELD ISOLATION PEDESTAL (MINI)13EA $150.00 $429.00 $769.23 $55.60 $126.53 $250.00 $366.61 $350.00 $750.00
19818(G) 5570 (SP)FIBER OPTIC ROUTE SIGN & INSTALLATION250EA $150.00 $204.00 $50.00 $70.33 $69.79 $60.00 $188.61 $100.00 $100.00
20876(A) 8482 (PL)TRUCK MOUNTED ATTENUATOR170SD $16.00 $200.00 $88.24 $172.50 $108.36 $85.00 $846.67 $150.00 $110.00
21880(I) 8902 FLAGGER45SD $100.00 $175.00 $333.33 $63.25 $328.74 $300.00 $1,481.08 $900.00 $3,600.00
22880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $10,000.00 $17,000.00 $74,041.46 $13,800.00 $97,520.29 $6,875.00 $27,776.90 $11,000.00 $15,000.00
23882(A) 8306 PORT.CHANGEABLE MESSAGE SIGN170SD $16.00 $130.00 $88.24 $86.25 $57.36 $85.00 $102.17 $150.00 $110.00
24220 2800 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $7,500.00 $15,000.00 $50,000.00 $4,500.00 $10,965.10 $750.00 $15,692.99 $125,000.00 $10,000.00
25641 1552 MOBILIZATION1LSUM $133,546.35 $35,000.00 $75,000.00 $25,000.00 $482,292.63 $182,500.00 $75,062.69 $80,000.00 $100,000.00