Bid tab 110229

Let Mar 17, 2011 · Division 8 · Tulsa Sign up free

‹ Mar 2011 results

BRIDGE REPAIR US -75/SH-51: US-75 OVER APACHE AVE . AND UNDER 36TH ST., AND SH-51 UNDER 161ST STREET .

Let date
Thursday, March 17, 2011
Contract
110229
J/P numbers
28477(04)
District
Division 8
County
Tulsa
Highway
Limits
BRIDGE REPAIR US -75/SH-51: US-75 OVER APACHE AVE . AND UNDER 36TH ST., AND SH-51 UNDER 161ST STREET .
Project number
MC-172N(529)

Bidders 5

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$247,079
1 PBX Corporation Low bidder $159,393 -35.5%
2 SCR CONSTRUCTION CO., INC. $222,724 -9.9% +39.7%
4 PCI ROADS, LLC $254,325 +2.9% +59.6%
5 Keystone Services, Inc. $267,022 +8.1% +67.5%
6 MERIDIAN CONTRACTING, INC. $302,001 +22.2% +89.5%

Bid tab: unit prices 23 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 PBX Corporation#2 SCR CONSTRUCTIO…#4 PCI ROADS, LLC#5 Keystone Servic…#6 MERIDIAN CONTRA…
1521(A) 6210 PNEUMATICALLY PLACED MORTAR18SY $600.00 $475.00 $850.00 $825.00 $725.00 $400.00
2524(A) 6610 (SP)CARBON FIBER-REINFORCED POLYMER225.8SF $125.00 $55.00 $65.00 $110.00 $85.00 $80.00
3521(A) 6210 PNEUMATICALLY PLACED MORTAR18SY $600.00 $475.00 $850.00 $825.00 $725.00 $400.00
4524(A) 6610 (SP)CARBON FIBER-REINFORCED POLYMER225.8SF $125.00 $55.00 $65.00 $110.00 $85.00 $80.00
5501(G) 6309 CLSM BACKFILL3CY $400.00 $300.00 $500.00 $350.00 $1,000.00 $1,000.00
6504(G) 6390 RAPID CURE JOINT SEALANT112LF $35.00 $30.00 $55.00 $48.00 $31.00 $52.00
7509 6386 SILICONE CONSTRUCTION JOINT264LF $25.00 $10.00 $35.00 $36.00 $5.00 $35.00
8521(A) 6210 PNEUMATICALLY PLACED MORTAR8SY $600.00 $475.00 $850.00 $825.00 $700.00 $400.00
9524(A) 6610 (SP)CARBON FIBER-REINFORCED POLYMER131.9SF $125.00 $55.00 $65.00 $110.00 $75.00 $80.00
10504(G) 6390 RAPID CURE JOINT SEALANT112LF $35.00 $30.00 $35.00 $48.00 $31.00 $52.00
11509 6386 SILICONE CONSTRUCTION JOINT264LF $25.00 $10.00 $35.00 $36.00 $5.00 $35.00
12513(B) 6019 CLASS B BRIDGE DECK REPAIR2SY $500.00 $300.00 $3,000.00 $700.00 $500.00 $1,500.00
13521(A) 6210 PNEUMATICALLY PLACED MORTAR20SY $600.00 $475.00 $850.00 $825.00 $700.00 $400.00
14524(A) 6610 (SP)CARBON FIBER-REINFORCED POLYMER447.1SF $125.00 $55.00 $65.00 $96.88 $107.00 $80.00
15524(A) 6610 (SP)CARBON FIBER-REINFORCED POLYMER15SF $160.00 $180.00 $65.00 $110.00 $1,000.00 $80.00
16871(B) 8705 (SP)CONST.ZONE IMPACT ATTEN.25SD $7.50 $8.00 $9.00 $8.00 $5.00 $226.00
17876(A) 8482 (PL)TRUCK MOUNTED ATTENUATOR90SD $43.41 $6.00 $7.00 $6.00 $35.00 $7.00
18877(B) 8484 DELIVER PORTABLE LONGITUDINAL BARRIER275LF $3.75 $20.00 $65.00 $28.00 $27.00 $51.00
19880(A) 8812 ARROW DISPLAY(TYPE C)90SD $6.58 $3.00 $4.00 $3.00 $15.00 $4.00
20880(J) 8905 CONSTRUCTION TRAFFIC CONTROL1LSUM $7,000.00 $19,280.00 $10,000.00 $14,535.00 $25,000.00 $99,000.00
21880(L) 8911 TRAFFIC SURVEILLANCE, POLICE360HOUR $55.75 $60.00 $65.00 $45.00 $62.00 $58.00
22882(A) 8306 PORT.CHANGEABLE MESSAGE SIGN90SD $15.85 $8.00 $9.00 $8.00 $25.00 $12.00
23641 1399 MOBILIZATION1LSUM $20,000.00 $8,000.00 $11,000.00 $20,000.00 $35,000.00 $15,000.00