RESURFACE (ASPHALT ) SH-51B: FROM 8TH STREET IN THE TOWN OF PORTER , EXTEND EAST THEN SOUTH. PROJECT LENGTH = 0.79 MILES
- Let date
- Thursday, March 17, 2011
- Contract
- 110208
- J/P numbers
- 28081(04)
- District
- Division 1
- County
- Wagoner
- Highway
- Limits
- RESURFACE (ASPHALT ) SH-51B: FROM 8TH STREET IN THE TOWN OF PORTER , EXTEND EAST THEN SOUTH. PROJECT LENGTH = 0.79 MILES
- Project number
- STPY-173C(173)
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $111,672 | ||
| 1 | APAC-CENTRAL, INC. Low bidder | $123,694 | +10.8% | |
| 2 | Paragon Contractors, LLC | $125,521 | +12.4% | +1.5% |
| 3 | MCGUIRE BROTHERS CONSTRUCTION, INC. | $132,478 | +18.6% | +7.1% |
| 4 | GLOVER & ASSOCIATES, INC. | $134,145 | +20.1% | +8.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 APAC-CENTRAL, I… | #2 Paragon Contrac… | #3 MCGUIRE BROTHER… | #4 GLOVER & ASSOCI… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 407(B) 0250 | TACK COAT | 1,300 | GAL | $2.40 | $2.49 | $3.00 | $3.00 | $2.63 |
| 2 | 411(E) 5990 | SUPERPAVE, TYPE S6(PG 64-22 OK) | 900 | TON | $75.00 | $92.70 | $88.25 | $88.50 | $110.00 |
| 3 | 412 5267 | COLD MILLING PAVEMENT | 6,010 | SY | $2.25 | $2.33 | $3.50 | $5.00 | $1.34 |
| 4 | 855(A) 8812 | TRAFFIC STRIPE(PLASTIC)(4" WIDE) | 18,200 | LF | $0.4000 | $0.6800 | $0.5100 | $0.7000 | $0.5200 |
| 5 | 855(A) 8825 | TRAFFIC STRIPE(PLASTIC)(24" WIDE) | 430 | LF | $0.5800 | $6.49 | $3.20 | $6.60 | $4.20 |
| 6 | 855(B) 8824 | TRAFFIC STRIPE(PLASTIC)(SYMBOLS) | 10 | EA | $500.00 | $162.31 | $198.00 | $165.00 | $740.25 |
| 7 | 880(J) 8905 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $15,000.00 | $6,233.64 | $8,523.00 | $1,650.00 | $5,000.00 |