| 1 | 202(C) 0184 |
UNCLASSIFIED BORROW | 4,000 | CY |
$5.50 |
$1.00 |
$5.60 |
| 2 | 202(G) 0185 |
EARTHWORK | 1 | LSUM |
$40,000.00 |
$40,000.00 |
$31,000.00 |
| 3 | 230(A) 2806 |
SOLID SLAB SODDING | 32,775 | SY |
$2.00 |
$1.60 |
$1.64 |
| 4 | 407 0250 |
TACK COAT | 16,415 | GAL |
$3.00 |
$2.00 |
$2.67 |
| 5 | 411(S4) 5960 |
(SP)ASPHALT CONCRETE TYPE S4(PG 64-22 OK) | 22,610 | TON |
$63.00 |
$65.00 |
$77.75 |
| 6 | 413(A) 4861 |
RUMBLE STRIP-METHOD AC-CON | 73,300 | LF |
$0.1000 |
$0.1200 |
$0.0800 |
| 7 | 417 4267 |
COLD MILLING BITUMINOUS PAVEMENT | 4,300 | SY |
$4.00 |
$4.50 |
$2.15 |
| 8 | 619(B) 4780 |
REMOVAL OF GUARD RAIL | 1,250 | LF |
$4.50 |
$2.50 |
$2.05 |
| 9 | 623 8572 |
(PL)CURVED APPROACH GUARD RAIL | 7 | EA |
$1,500.00 |
$450.00 |
$460.00 |
| 10 | 623(A) 0932 |
BEAM GUARD RAIL-W-BEAM-SINGLE | 644 | LF |
$25.00 |
$24.00 |
$24.55 |
| 11 | 623(F) 4447 |
GUARD RAIL ANCHOR UNIT (TYPE B) | 2 | EA |
$1,500.00 |
$600.00 |
$613.50 |
| 12 | 623(F) 5686 |
GUARD RAIL ANCHOR UNIT (TYPE D-BF) | 8 | EA |
$1,800.00 |
$1,600.00 |
$1,636.00 |
| 13 | 623(H) 8571 |
(SP)G.E.T. GUARD RAIL END SECTION | 10 | EA |
$2,400.00 |
$2,350.00 |
$2,402.00 |
| 14 | 854(A) 8800 |
TRAFFIC STRIPE(PAINT)(4" WIDE) | 128,436 | LF |
$0.2000 |
$0.0600 |
$0.1000 |
| 15 | 876(C) 8482 |
(PL)TRUCK MOUNTED ATTENUATOR | 26 | SD |
$40.00 |
$40.00 |
$128.00 |
| 16 | 880(J) 8905 |
CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM |
$5,000.00 |
$50,000.00 |
$8,200.00 |
| 17 | 641 1552 |
MOBILIZATION | 1 | LSUM |
$40,000.00 |
$113,000.00 |
$33,850.00 |