| Let date | Contract / J/P | County / Division | Highway | Description | Estimate | Status | Low bidder | |
|---|---|---|---|---|---|---|---|---|
| Jan 16, 2025 | 240056 WR-MC-140 | MayesRogersDivision 8 | WILL ROGERS TURNPIKE | Pavement Rehabilitation (Asphalt) WILL ROGERS TURNPIKE: FROM MILE 260 TO MILE 265.1. | — | Let | APAC-CENTRAL, INC. $4,975,000 · | |
| Aug 14, 2025 | 250198 NHPP-013N(231)FP | MayesWagonerDivision 8 | Grade | — | Let | C3 Construction, Inc. $27,406,576 · | ||
| Sep 11, 2025 | 250244 SSP-272F(425)PM | CraigMayesNowataOsage+3 moreDivision 8 | SH-10SH-125SH-18SH-28+2 more | Bridge Water Proof Seal SH-10/ SH-18/ SH-28/ SH-82/ SH-125/ US-60: OVER BIG CABIN CREEK, SALINE CREEK, VERDIGRIS RIVER, SALT CREEK, HORSE CREEK, HOGSHOOTER CREEK, UNNAMED CREEK AND I-44 IN DISTRICT VIII. | $170,922 | Let | LOGOS CONSTRUCTION CO., LLC $133,307 · -22.0% | |
| Sep 18, 2025 | 250145 STP-249C(068)PM | CherokeeMayesDivision 1 | SH-82 | Grade, Drain, And Surface SH-82: FROM THE CHEROKEE COUNTY LINE, EXTEND NORTH NEAR LOCUST GROVE. | — | Let | ||
| Oct 16, 2025 | 250302 BRO-249F(093)CB / BRO-249F(094)CB | CherokeeDelawareMayesDivision 1 | COUNTY ROADS | Bridge Repair COUNTY ROADS: AT MULTIPLE LOCATIONS IN DISTRICT I AND DISTRICT VIII. | $1,081,465 | Let | Built Right Construction, LLC $587,370 · -45.7% | |
| Nov 20, 2025 | 250352 STP-249C(068)PM | CherokeeMayesDivision 1 | SH-82 | Grade, Drain, And Surface SH-82: FROM THE CHEROKEE COUNTY LINE, EXTEND NORTH NEAR LOCUST GROVE. | $18,976,851 | Let | Robinson Construction, LLC $15,440,915 · -18.6% | |
| Feb 12, 2026 | 260035 SSR-249C(096)SR | MayesDivision 8 | US-412A | Resurface (Asphalt) US-412A: FROM 6.22 MILES WEST OF THE SH-82 JUNCTION, EXTEND EAST NEAR LOCUST GROVE. | — | Let | BECCO CONTRACTORS, INC. $1,278,000 · | |
| Feb 12, 2026 | 260036 SSR-019N(182)SR | MayesDivision 8 | US-412 | Pavement Rehabilitation (Concrete) US-412: FROM 4.22 MILES EAST OF THE US-69 INTERCHANGE, EXTEND EAST NEAR LOCUST GROVE. | $1,595,745 | Let | IOWA CIVIL CONTRACTING, INC. $1,151,251 · -27.9% | |
| Feb 12, 2026 | 260037 SSR-019N(182)SR / SSR-249C(096)SR | MayesDivision 8 | US-412 | Resurface (Asphalt) And Pavement Rehabilitation (Concrete) US-412: FROM 4.22 MILES EAST OF THE US-69 INTERCHANGE, EXTEND EAST NEAR LOCUST GROVE. | — | Let | ||
| Jul 9, 2026 | 260181 NHPP-013N(250)PM | MayesDivision 8 | US-69 | Pavement Rehabilitation US-69: FROM THE SH-20 JUNCTION, EXTEND NORTH NEAR THE CITY OF PRYOR. | $45,177,238 | Let | C3 Construction, Inc. $37,446,427 · -17.1% | |
| Sep 17, 2026 | 260240 HSIPG-299S(495)TR | AtokaBryanComancheCraig+8 moreDivision 2 | I-35SH-7SH-74SH-9+4 more | Traffic Signal Safety Improvement I-35/US-62/US-69/US-70/US-271/SH-7/SH-9/SH-74: AT MULTIPLE LOCATIONS IN DISTRICTS I, II, III, VII, AND VIII. | $748,986 | Let | Lighthouse Transportation Group, LLC $808,785 · +8.0% | |
| Oct 15, 2026 | 260249 HSIPG-221F(071)TR | CraigDelawareMayesOsage+3 moreDivision 8 | SH-10SH-125SH-127SH-18+6 more | Safety Improvement (Guardrail) SH-2/SH-28/SH-85A/SH-20/SH-127/SH-18/SH-125/SH-82/SH-10/US-64: AT MULTIPLE LOCATIONS IN DISTRICT VIII. | $2,593,860 | Let | ACTION SAFETY SUPPLY CO., LLC $2,899,445 · +11.8% | |
| Jan 14, 2027 | 270015 HSIPG-249B(097)TR | MayesDivision 8 | SH-20 | Intersection Modification SH-20: AT THE INTERSECTION OF COUNTY ROAD (NS-435), 3.6 MILES EAST OF THE US-69 JUNCTION NEAR PRYOR. | —23 items | Advertised | ||
| Jan 21, 2027 | 260253 TAP-249E(098)TP | MayesDivision 8 | —77 items | Advertised | ||||
| Sep 1, 2027 estimated | 33821(04) STP-249C(088)PM | MayesDivision 8 | SH-412B | Pavement Rehabilitation SH-412B: FROM SH-69A TO US-412 | $17,600,000 | Planned | ||
| Sep 1, 2027 estimated | 35353(04) SSP-249C(066)PM | MayesDivision 8 | SH-412B | Intersect Modif SH-412B: AT PATROL RD | $4,200,000 | Planned | ||
| Mar 1, 2028 estimated | 35507(04) J3-5507(004)PM | MayesDivision 8 | SH-20 | Safety Improvement SH-20: AT CARBIDE RD 3.5 MILES EAST OF PRYOR | $3,600,000 | Planned | ||
| FY 2030 | 35050(04) STP-249C(089)PM | MayesDivision 8 | SH-412B | Interchange SH-412B: AT US-412 JUNCTION | $26,800,000 | Planned | ||
| FY 2031 | 32693(04) J3-2693(004)FP | MayesDivision 8 | US-69 | Grade,Drain,Bridge & Surface US-69: SB FROM 8.0 MILES N OF SH-20, EXTEND N 5.35 MILES | $29,000,000 | Planned | ||
| FY 2031 | 32693(08) J3-2693(008)PM | CraigMayesDivision 8 | US-69 | Grade,Drain,Bridge & Surface US-69: SB FROM 13.35 MILES N OF SH-20, EXTEND 3.18 MILES | $17,300,0002 items | Planned | ||
| FY 2031 | 33861(04) J3-3861(004) | MayesDivision 8 | US-69 | Pavement Rehabilitation US-69: BEGIN AT THE WAGONER C/L AND EXTEND NORTH 6 MILES | $18,000,000 | Planned | ||
| FY 2032 | 24382(04) SSP-149C(107)SS | MayesDivision 8 | SH-28 | Grade,Drain,Bridge & Surface SH-28: BEGIN US-69/SH-28 JCT. AND EXTEND EAST 7.0 MILES | $39,200,0002 items | Planned | ||
| FY 2033 | 28891(04) J2-8891(004)PM | MayesDivision 8 | SH-28 | Widen & Resurface SH-28: FROM EAST END OF THE I-44 INTERCHANGE, EXTEND EAST APROX. 5.45 MILES | $17,600,0005 items | Planned | ||
| FY 2033 | 33823(04) J3-3823(004)PM | MayesDivision 8 | SH-82 | Grade, Drain & Surface SH-82: FROM 2.82 MILES NORTH OF SH-20 EXTENDING NORTH TO SH-28 AND SH-28 FROM SH-82 N TO SH-82 S | $18,300,000 | Planned | ||
| FY 2033 | 35051(04) J3-5051(004)PM | MayesDivision 8 | US-69 | Intersect Modif US-69: AIRPORT RD & MAIN ST | $500,000 | Planned | ||
| FY 2033 | 35508(04) STP-249B(090)PM | MayesDivision 8 | SH-20 | Safety Improvement SH-20: FROM THE ROGERS C/L EAST 3.3 MILES | $1,100,000 | Planned | ||
| FY 2035 | 23270(04) J2-3270(004)PM | MayesDivision 8 | SH-28 | Grade, Drain & Surface SH-28: BEG. APPROX. 8.1 MILES EAST OF JCT SH-28/US-69 & EXTEND EAST 4.75 MILES | $32,000,000 | Planned | ||
| FY 2035 | 36275(04) J3-6275(004)PM | MayesDivision 8 | SH-28 | Widen & Resurface SH-28: FROM THE ROGERS C/L EXTEND EAST APPROX. 3 MILES TO I-44. | $9,000,000 | Planned |
1–28 of 28
Lettings: ODOT Contracts and Proposals (letting spreadsheets and item lists). Planned projects: ODOT 8-Year Construction Work Plan (roads and bridges layers on the ODOT open data hub). Years are federal fiscal years; let months are shown only where ODOT lists one. Right of way and utility pieces are left out. "Added" is the first date Bid Potato saw the job. Always confirm against the official proposal before bidding.