$108.74Avg low bid / LF
$105.32Avg of all bids
$157.82Avg engineer's estimate
6Jobs · 1,397 LF
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2020 | 5 | 961 | $64.98 | $93.62 |
| 2019 | 1 | 436 | $205.17 | $144.97 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Nov 19, 2020 | 200357 | SequoyahDivision 1 | 512 LF | $37.80 | APAC-CENTRAL, INC. |
| Mar 19, 2020 | 200133 | HaskellDivision 1 | 160 LF | $62.12 | C3 Construction, Inc. |
| Feb 20, 2020 | 200050 | BeckhamDivision 5 | 90 LF | $75.60 | Frontier Bridge, Inc. |
| Jan 16, 2020 | 200043 | HaskellDivision 1 | 40 LF | $269.24 | KOSS CONSTRUCTION COMPANY & SUBSIDIARY |
| Jan 16, 2020 | 190214 | LoveDivision 7 | 159 LF | $98.00 | Silver Star Construction Company, Inc. |
| Nov 14, 2019 | 190383 | CimarronDivision 6 | 311 LF | $215.47 | IHC Scott, INC. |
| Nov 14, 2019 | 190383 | CimarronDivision 6 | 125 LF | $179.55 | IHC Scott, INC. |