22-00218-00-RS
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $1,599,584 | ||
| 2 | Samron Midwest Contracting, Inc. | $1,809,463 | +13.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Samron Midwest … |
|---|---|---|---|---|---|---|---|
| 1 | XX005569 | MAILBX REM & REINSTL | 10 | EACH | $645.63 | $300.00 | |
| 2 | X6330725 | SPBGR (SHORT RADIUS) | 37.5 | FOOT | $51.50 | $51.00 | |
| 3 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $54,604.37 | $74,500.00 | |
| 4 | 20800150 | TRENCH BACKFILL | 29 | CU YD | $135.45 | $40.00 | |
| 5 | 28100807 | STONE DUMP RIP CL A4 | 50 | TON | $116.93 | $175.00 | |
| 6 | 40200800 | AGG SURF COURSE TY B | 134 | TON | $54.33 | $17.50 | |
| 7 | 40600275 | BIT MATLS PR CT | 3,250 | POUND | $0.0100 | $0.0100 | |
| 8 | 40600290 | BIT MATLS TACK CT | 44,835 | POUND | $0.0100 | $0.0100 | |
| 9 | 40600370 | LONG JOINT SEALANT | 29,131 | FOOT | $2.56 | $2.60 | |
| 10 | 40600982 | HMA SURF REM BUTT JT | 226 | SQ YD | $46.94 | $15.00 | |
| 11 | 40600990 | TEMPORARY RAMP | 45 | SQ YD | $79.90 | $0.0100 | |
| 12 | 40602970 | HMA BC IL-9.5FG N70 | 9,620 | TON | $72.32 | $90.00 | |
| 13 | 40604052 | HMA SC IL-9.5 C N70 | 4,730 | TON | $76.85 | $92.00 | |
| 14 | 44200065 | PAVT PATCH T2 6 | 20 | SQ YD | $511.64 | $550.00 | |
| 15 | 48102100 | AGG WEDGE SHLD TYPE B | 5,794 | TON | $25.62 | $17.50 | |
| 16 | 542C0235 | P CUL CL C 1 30 | 52 | FOOT | $203.46 | $200.00 | |
| 17 | 542C5503 | P CUL CL C 1 EQRS 48 | 52 | FOOT | $247.22 | $250.00 | |
| 18 | 54262730 | METAL FL END SEC 30" | 2 | EACH | $1,660.80 | $1,250.00 | |
| 19 | 54262848 | METAL FL ES EQ RS 48" | 2 | EACH | $2,914.01 | $2,250.00 | |
| 20 | 60300305 | FR & LIDS ADJUST | 2 | EACH | $283.63 | $300.00 | |
| 21 | 63000003 | SPBGR TY A 9FT POSTS | 837.5 | FOOT | $41.20 | $41.00 | |
| 22 | 63100167 | TR BAR TRM T1 SPL TAN | 1 | EACH | $4,017.00 | $3,950.00 | |
| 23 | 63200400 | CABLE ROAD GD REM | 822 | FOOT | $3.09 | $3.05 | |
| 24 | 67100100 | MOBILIZATION | 1 | L SUM | $93,999.17 | $107,750.00 | |
| 25 | 72000100 | SIGN PANEL T1 | 244 | SQ FT | $35.19 | $30.00 | |
| 26 | 72400100 | REMOV SIN PAN ASSY TA | 8 | EACH | $22.81 | $150.00 | |
| 27 | 72400310 | REMOV SIGN PANEL T1 | 1 | SQ FT | $182.46 | $50.00 | |
| 28 | 72800100 | TELES STL SIN SUPPORT | 526 | FOOT | $13.27 | $15.00 | |
| 29 | 78001110 | PAINT PVT MK LINE 4 | 104,020 | FOOT | $0.1200 | $0.1300 | |
| 30 | 78100100 | RAISED REFL PAVT MKR | 413 | EACH | $38.15 | $37.05 |