14-00026-02-PV
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Keller Construction, Inc. Low bidder | $551,712 | ||
| 2 | The Kilian Corporation | $619,282 | +12.2% | |
| 3 | Hank's Excavating & Landscaping, Inc. | $641,726 | +16.3% | |
| 4 | Stutz Excavating, Inc. | $648,939 | +17.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Keller Construc… | #2 The Kilian Corp… | #3 Hank's Excavati… | #4 Stutz Excavatin… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0326899 | SOLAR-POWER FB AS CMP | 2 | EACH | $6,625.00 | $7,150.00 | $7,325.00 | $7,700.00 | |
| 2 | X0350810 | BOLLARD REMOVAL | 16 | EACH | $47.93 | $50.00 | $13.00 | $22.00 | |
| 3 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $10,582.00 | $9,500.00 | $30,000.00 | $9,212.00 | |
| 4 | X7030005 | TEMP PAVT MKING REMOV | 1,335 | SQ FT | $1.79 | $0.00 | $1.85 | $0.0100 | |
| 5 | Z0056648 | SS 1 WAT MN 12 | 227 | FOOT | $56.20 | $53.00 | $52.00 | $78.00 | |
| 6 | Z0056650 | SS 1 WAT MN 15 | 29 | FOOT | $80.37 | $85.00 | $95.00 | $114.00 | |
| 7 | 20200100 | EARTH EXCAVATION | 2,540 | CU YD | $15.98 | $22.00 | $26.00 | $21.25 | |
| 8 | 20800150 | TRENCH BACKFILL | 71 | CU YD | $34.00 | $23.00 | $25.00 | $23.00 | |
| 9 | 25000100 | SEEDING CL 1 | 1.5 | ACRE | $1,326.00 | $1,325.00 | $1,400.00 | $3,025.00 | |
| 10 | 25000400 | NITROGEN FERT NUTR | 135 | POUND | $1.22 | $1.26 | $4.25 | $1.25 | |
| 11 | 25000500 | PHOSPHORUS FERT NUTR | 135 | POUND | $1.22 | $1.26 | $4.25 | $1.25 | |
| 12 | 25000600 | POTASSIUM FERT NUTR | 135 | POUND | $1.22 | $1.26 | $4.25 | $1.25 | |
| 13 | 25100115 | MULCH METHOD 2 | 1.5 | ACRE | $1,326.00 | $1,325.00 | $2,000.00 | $1,900.00 | |
| 14 | 28000400 | PERIMETER EROS BAR | 530 | FOOT | $4.34 | $4.35 | $2.50 | $3.50 | |
| 15 | 28000500 | INLET & PIPE PROTECT | 34 | EACH | $102.60 | $115.00 | $225.00 | $10.00 | |
| 16 | 35200420 | PROC SOIL-CEM BC 12 | 6,345 | SQ YD | $2.74 | $4.15 | $5.00 | $4.30 | |
| 17 | 35200500 | CEMENT | 4,283 | 100 WT | $6.67 | $8.75 | $9.50 | $8.25 | |
| 18 | 40600290 | BIT MATLS TACK CT | 1,179 | POUND | $0.9700 | $0.9700 | $1.00 | $1.00 | |
| 19 | 40701841 | HMA PAVT FD 8 | 5,463 | SQ YD | $34.64 | $34.25 | $35.00 | $37.00 | |
| 20 | 42400100 | PC CONC SIDEWALK 4 | 4,040 | SQ FT | $6.18 | $7.55 | $6.00 | $7.00 | |
| 21 | 42400800 | DETECTABLE WARNINGS | 87 | SQ FT | $27.00 | $36.00 | $45.00 | $35.00 | |
| 22 | 44000100 | PAVEMENT REM | 380 | SQ YD | $13.44 | $8.25 | $14.00 | $20.00 | |
| 23 | 44000200 | DRIVE PAVEMENT REM | 592 | SQ YD | $7.71 | $5.50 | $13.00 | $18.00 | |
| 24 | 44000500 | COMB CURB GUTTER REM | 89 | FOOT | $2.17 | $5.25 | $7.00 | $9.50 | |
| 25 | 44000600 | SIDEWALK REM | 501 | SQ FT | $0.8600 | $0.9000 | $1.00 | $2.50 | |
| 26 | 48101600 | AGGREGATE SHLDS B 8 | 116 | SQ YD | $26.73 | $28.00 | $12.00 | $24.00 | |
| 27 | 48203029 | HMA SHOULDERS 8 | 594 | SQ YD | $35.83 | $36.00 | $36.00 | $38.00 | |
| 28 | 50105220 | PIPE CULVERT REMOV | 585 | FOOT | $4.78 | $7.25 | $4.00 | $10.30 | |
| 29 | 54213657 | PRC FLAR END SEC 12 | 1 | EACH | $783.00 | $615.00 | $550.00 | $800.00 | |
| 30 | 54214509 | PRC FL END S EQ RS 24 | 1 | EACH | $1,090.00 | $1,225.00 | $1,100.00 | $1,400.00 | |
| 31 | 550A0050 | STORM SEW CL A 1 12 | 143 | FOOT | $47.54 | $57.00 | $33.00 | $70.00 | |
| 32 | 550A0070 | STORM SEW CL A 1 15 | 49 | FOOT | $52.09 | $61.50 | $38.00 | $62.00 | |
| 33 | 550A4100 | SS CL A 1 EQRS 24 | 89 | FOOT | $107.07 | $120.00 | $80.00 | $105.00 | |
| 34 | 60218400 | MAN TA 4 DIA T1F CL | 1 | EACH | $2,319.00 | $1,725.00 | $2,400.00 | $1,400.00 | |
| 35 | 60218500 | MAN TA 4 DIA T3F&G | 2 | EACH | $2,413.00 | $2,175.00 | $2,100.00 | $841.00 | |
| 36 | 60219000 | MAN TA 4 DIA T8G | 1 | EACH | $2,920.00 | $2,655.00 | $2,100.00 | $1,500.00 | |
| 37 | 60219540 | MAN TA 4 DIA T24F&G | 6 | EACH | $2,482.00 | $2,795.00 | $2,450.00 | $1,700.00 | |
| 38 | 60236200 | INLETS TA T8G | 3 | EACH | $1,452.00 | $1,100.00 | $900.00 | $1,100.00 | |
| 39 | 60237470 | INLETS TA T24F&G | 10 | EACH | $1,591.00 | $1,425.00 | $1,000.00 | $1,245.00 | |
| 40 | 60240220 | INLETS TB T3F&G | 2 | EACH | $1,788.00 | $1,970.00 | $1,500.00 | $1,442.00 | |
| 41 | 60255500 | MAN ADJUST | 8 | EACH | $453.00 | $485.00 | $900.00 | $330.00 | |
| 42 | 60403800 | LIDS T1 CL | 1 | EACH | $257.00 | $250.00 | $375.00 | $545.00 | |
| 43 | 60406100 | FR & LIDS T1 CL | 1 | EACH | $364.00 | $875.00 | $1,300.00 | $545.00 | |
| 44 | 60605000 | COMB CC&G TB6.24 | 3,018 | FOOT | $15.64 | $25.25 | $23.00 | $27.15 | |
| 45 | 67100100 | MOBILIZATION | 1 | L SUM | $22,054.00 | $26,075.00 | $10,000.00 | $26,000.00 | |
| 46 | 70300220 | TEMP PVT MK LINE 4 | 3,635 | FOOT | $0.00 | $0.00 | $0.5500 | $0.0100 | |
| 47 | 70300260 | TEMP PVT MK LINE 12 | 62 | FOOT | $0.00 | $0.00 | $12.60 | $0.0100 | |
| 48 | 70300280 | TEMP PVT MK LINE 24 | 31 | FOOT | $0.00 | $0.00 | $18.00 | $0.0100 | |
| 49 | 72000100 | SIGN PANEL T1 | 102.8 | SQ FT | $22.19 | $21.25 | $23.00 | $23.50 | |
| 50 | 72900200 | METAL POST TY B | 254 | FOOT | $11.73 | $11.75 | $12.00 | $12.50 | |
| 51 | 78000100 | THPL PVT MK LTR & SYM | 110 | SQ FT | $7.51 | $7.50 | $29.00 | $30.00 | |
| 52 | 78000200 | THPL PVT MK LINE 4 | 3,635 | FOOT | $1.32 | $1.33 | $1.45 | $1.50 | |
| 53 | 78000400 | THPL PVT MK LINE 6 | 272 | FOOT | $1.49 | $1.50 | $6.80 | $7.00 | |
| 54 | 78000600 | THPL PVT MK LINE 12 | 167 | FOOT | $4.01 | $4.00 | $10.75 | $11.00 | |
| 55 | 78000650 | THPL PVT MK LINE 24 | 31 | FOOT | $7.51 | $7.50 | $13.65 | $15.00 |