22-00201-04-RS
- Let date
- Friday, April 24, 2026
- Contract
- 87900 · job page
- District
- District 3
- County
- Livingston
- Highway
- Limits
- Resurfacing Kangley Road from the LaSalle County line to IL 17.
- Classification
- ·
- Project number
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Kankakee Valley Construction Company, Inc. Low bidder | $805,843 | ||
| 2 | H. J. Eppel & Co. | $884,329 | +9.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Kankakee Valley… | #2 H. J. Eppel & C… |
|---|---|---|---|---|---|---|---|
| 1 | X4401198 | HMA SURF REM VAR DP | 878 | SQ YD | $7.00 | $8.95 | |
| 2 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $4,150.00 | $34,500.00 | |
| 3 | Z0055300 | RUMBLE STRIP | 4 | EACH | $1,200.00 | $1,400.00 | |
| 4 | 40600290 | BIT MATLS TACK CT | 37,098 | POUND | $0.0100 | $1.00 | |
| 5 | 40602965 | HMA BC IL-9.5FG N50 | 2,759 | TON | $106.00 | $109.00 | |
| 6 | 40604000 | HMA SC IL-9.5FG C N50 | 2,907 | TON | $106.00 | $112.00 | |
| 7 | 40800050 | INCIDENTAL HMA SURF | 87 | TON | $275.00 | $255.00 | |
| 8 | 44000154 | HMA SURF REM 1 1/4 | 1,801 | SQ YD | $7.00 | $4.75 | |
| 9 | 48102100 | AGG WEDGE SHLD TYPE B | 3,379 | TON | $31.00 | $33.68 | |
| 10 | 67100100 | MOBILIZATION | 1 | L SUM | $42,000.00 | $13,946.63 | |
| 11 | 70300100 | SHORT TERM PAVT MKING | 6,720 | FOOT | $0.0100 | $0.9500 | |
| 12 | 70300150 | SHRT TRM PAVT MK REM | 563 | SQ FT | $0.0100 | $1.60 | |
| 13 | 78001110 | PAINT PVT MK LINE 4 | 37,800 | FOOT | $0.1700 | $0.1900 |