| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Kankakee Valley Construction Company, Inc. Low bidder | $813,406 | ||
| 2 | Gallagher Asphalt Corporation | $905,253 | +11.3% | |
| 3 | Ruben E. Smith Const. dba R & R, Inc. | $938,818 | +15.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Kankakee Valley… | #2 Gallagher Aspha… | #3 Ruben E. Smith … |
|---|---|---|---|---|---|---|---|---|
| 1 | C2C072G3 | S-ROSA FLWR CR CG 3G | 145 | EACH | $75.00 | $100.00 | $100.00 | |
| 2 | K0012990 | P PL ORNAMENT T GAL P | 4.93 | UNIT | $2,500.00 | $3,750.00 | $3,750.00 | |
| 3 | K0013020 | P PL PRAIRIE TY GAL P | 0.95 | UNIT | $2,500.00 | $3,350.00 | $3,300.00 | |
| 4 | K0013080 | P PL SEDG MDW T GAL P | 4.45 | UNIT | $2,500.00 | $3,200.00 | $3,150.00 | |
| 5 | K1003679 | MULCH | 36 | CU YD | $36.00 | $53.00 | $52.00 | |
| 6 | XX005967 | TOPSOIL PLANT MIXTURE | 259 | CU YD | $85.00 | $125.00 | $122.00 | |
| 7 | X0324894 | WM MANHOLES ADJ | 1 | EACH | $800.00 | $550.00 | $500.00 | |
| 8 | X5510100 | STORM SEWER REMOVAL | 106 | FOOT | $14.00 | $22.50 | $20.00 | |
| 9 | X6026050 | SANITARY MANHOLE ADJ | 1 | EACH | $1,130.00 | $900.00 | $800.00 | |
| 10 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $19,400.00 | $21,500.00 | $25,000.00 | |
| 11 | X8440110 | REL EX LP W/LUMINAIRE | 1 | EACH | $2,800.00 | $3,000.00 | $2,900.00 | |
| 12 | X8950305 | REMOV EX SIG HEAD | 5 | EACH | $300.00 | $315.00 | $315.00 | |
| 13 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $5,000.00 | $12,000.00 | $25,000.00 | |
| 14 | 20200100 | EARTH EXCAVATION | 202 | CU YD | $0.0100 | $80.00 | $50.00 | |
| 15 | 20800150 | TRENCH BACKFILL | 14 | CU YD | $55.00 | $33.00 | $30.00 | |
| 16 | 21001000 | GEOTECH FAB F/GR STAB | 138 | SQ YD | $1.25 | $4.00 | $3.05 | |
| 17 | 28000500 | INLET & PIPE PROTECT | 16 | EACH | $95.00 | $200.00 | $95.00 | |
| 18 | 35101600 | AGG BASE CSE B 4 | 811 | SQ YD | $12.00 | $10.00 | $13.00 | |
| 19 | 35102200 | AGG BASE CSE B 10 | 138 | SQ YD | $22.00 | $25.00 | $19.00 | |
| 20 | 35300100 | PCC BSE CSE 6 | 441 | SQ YD | $35.00 | $68.00 | $40.00 | |
| 21 | 40600290 | BIT MATLS TACK CT | 5,255 | POUND | $0.0100 | $1.00 | $0.6200 | |
| 22 | 40602985 | HMA BC IL-9.5 N70 | 33 | TON | $150.00 | $250.00 | $155.00 | |
| 23 | 40604162 | P HMA SC IL-9.5 D N70 | 1,366 | TON | $110.00 | $125.00 | $150.00 | |
| 24 | 42000400 | PCC PVT 9 | 17 | SQ YD | $108.00 | $125.00 | $125.00 | |
| 25 | 42400200 | PC CONC SIDEWALK 5 | 4,818 | SQ FT | $10.00 | $10.00 | $7.65 | |
| 26 | 42400800 | DETECTABLE WARNINGS | 360 | SQ FT | $20.00 | $50.00 | $26.00 | |
| 27 | 44000100 | PAVEMENT REM | 735 | SQ YD | $15.00 | $30.00 | $45.00 | |
| 28 | 44000157 | HMA SURF REM 2 | 11,577 | SQ YD | $4.00 | $3.25 | $3.20 | |
| 29 | 44000500 | COMB CURB GUTTER REM | 828 | FOOT | $15.00 | $12.00 | $14.00 | |
| 30 | 44000600 | SIDEWALK REM | 4,611 | SQ FT | $2.50 | $3.00 | $2.50 | |
| 31 | 550A0050 | STORM SEW CL A 1 12 | 62 | FOOT | $55.00 | $95.00 | $85.00 | |
| 32 | 550B0050 | STORM SEW CL B 1 12 | 129 | FOOT | $105.00 | $100.00 | $90.00 | |
| 33 | 56109210 | WATER VALVES ADJUST | 8 | EACH | $85.00 | $280.00 | $250.00 | |
| 34 | 60218400 | MAN TA 4 DIA T1F CL | 4 | EACH | $2,400.00 | $2,800.00 | $2,500.00 | |
| 35 | 60236800 | INLETS TA T11F&G | 4 | EACH | $1,150.00 | $1,650.00 | $1,500.00 | |
| 36 | 60240310 | INLETS TB T11F&G | 3 | EACH | $1,650.00 | $2,250.00 | $2,000.00 | |
| 37 | 60255500 | MAN ADJUST | 10 | EACH | $850.00 | $550.00 | $500.00 | |
| 38 | 60260100 | INLETS ADJUST | 7 | EACH | $170.00 | $550.00 | $500.00 | |
| 39 | 60500040 | REMOV MANHOLES | 1 | EACH | $600.00 | $450.00 | $400.00 | |
| 40 | 60500060 | REMOV INLETS | 4 | EACH | $300.00 | $450.00 | $400.00 | |
| 41 | 60603800 | COMB CC&G TB6.12 | 973 | FOOT | $46.00 | $48.00 | $50.00 | |
| 42 | 61139900 | STORM SEWER SPEC 6 | 5 | FOOT | $90.00 | $160.00 | $150.00 | |
| 43 | 66900200 | NON SPL WASTE DISPOSL | 68 | CU YD | $100.00 | $100.00 | $17.50 | |
| 44 | 66900530 | SOIL DISPOSAL ANALY | 3 | EACH | $1,850.00 | $1,500.00 | $1,850.00 | |
| 45 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,950.00 | $3,000.00 | $2,500.00 | |
| 46 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $900.00 | $1,300.00 | $2,500.00 | |
| 47 | 66901006 | REG SUB MON | 5 | CAL DA | $760.00 | $850.00 | $1,600.00 | |
| 48 | 67100100 | MOBILIZATION | 1 | L SUM | $38,750.00 | $33,000.00 | $25,000.00 | |
| 49 | 72000100 | SIGN PANEL T1 | 119 | SQ FT | $26.25 | $28.00 | $40.00 | |
| 50 | 72800100 | TELES STL SIN SUPPORT | 30 | FOOT | $15.75 | $16.00 | $23.00 | |
| 51 | 72900100 | METAL POST TY A | 125 | FOOT | $13.13 | $15.00 | $20.00 | |
| 52 | 73100100 | BASE TEL STL SIN SUPP | 3 | EACH | $210.00 | $225.00 | $250.00 | |
| 53 | 78000100 | THPL PVT MK LTR & SYM | 333 | SQ FT | $5.50 | $5.75 | $5.75 | |
| 54 | 78000200 | THPL PVT MK LINE 4 | 5,215 | FOOT | $0.7800 | $0.8000 | $0.8200 | |
| 55 | 78000400 | THPL PVT MK LINE 6 | 5,014 | FOOT | $1.39 | $1.50 | $1.45 | |
| 56 | 78000500 | THPL PVT MK LINE 8 | 149 | FOOT | $1.85 | $2.00 | $1.95 | |
| 57 | 78000600 | THPL PVT MK LINE 12 | 1,617 | FOOT | $2.77 | $3.00 | $2.85 | |
| 58 | 78000650 | THPL PVT MK LINE 24 | 89 | FOOT | $5.50 | $5.75 | $5.75 | |
| 59 | 78003131 | PREF PL PM TB STAN L6 | 1,204 | FOOT | $4.30 | $11.00 | $4.50 | |
| 60 | 78003181 | PREF PL PM TB STAN L24 | 178 | FOOT | $18.40 | $31.00 | $19.00 | |
| 61 | 78006100 | PREF THPL PM LTR-SYM | 7,322 | SQ FT | $23.60 | $18.75 | $24.00 | |
| 62 | 78008200 | POLYUREA PM T1 LTR-SY | 167 | SQ FT | $1.00 | $1.00 | $1.05 | |
| 63 | 78008210 | POLYUREA PM T1 LN 4 | 2,900 | FOOT | $1.10 | $1.20 | $1.15 | |
| 64 | 78008230 | POLYUREA PM T1 LN 6 | 1,029 | FOOT | $1.93 | $2.00 | $2.00 | |
| 65 | 78008240 | POLYUREA PM T1 LN 8 | 622 | FOOT | $2.57 | $2.75 | $2.70 | |
| 66 | 78008250 | POLYUREA PM T1 LN 12 | 29 | FOOT | $3.86 | $4.00 | $4.00 | |
| 67 | 78011025 | GRV RCSD PVT MRKG 5 | 2,659 | FOOT | $1.00 | $1.00 | $1.05 | |
| 68 | 78011035 | GRV RCSD PVT MRKG 7 | 3,812 | FOOT | $1.50 | $1.50 | $1.55 | |
| 69 | 78011045 | GRV RCSD PVT MRKG 9 | 609 | FOOT | $2.00 | $2.00 | $2.10 | |
| 70 | 78011065 | GRV RCSD PVT MRKG 13 | 41 | FOOT | $4.00 | $4.00 | $4.15 | |
| 71 | 78011125 | GRV RCSD PVT MRKG 25 | 178 | FOOT | $6.15 | $6.50 | $6.50 | |
| 72 | 78100100 | RAISED REFL PAVT MKR | 140 | EACH | $39.50 | $40.00 | $42.00 | |
| 73 | 78300200 | RAISED REF PVT MK REM | 108 | EACH | $17.00 | $20.00 | $20.00 | |
| 74 | 78300202 | PAVMT MRKG REM WTR BL | 1,172 | SQ FT | $3.00 | $3.50 | $3.20 | |
| 75 | 83600200 | LIGHT POLE FDN 24D | 5 | FOOT | $525.00 | $550.00 | $550.00 | |
| 76 | 88030020 | SH LED 1F 3S MAM | 4 | EACH | $950.00 | $1,000.00 | $1,000.00 | |
| 77 | 88030050 | SH LED 1F 3S BM | 2 | EACH | $900.00 | $950.00 | $950.00 | |
| 78 | 88200310 | TS BACKPLATE LOU PLAS | 6 | EACH | $275.00 | $300.00 | $285.00 | |
| 79 | 89502200 | MOD EX CONTR | 1 | EACH | $725.00 | $750.00 | $750.00 |