127RS-6
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Samron Midwest Contracting, Inc. Low bidder | $1,230,184 | ||
| 2 | E. T. Simonds Construction Company | $1,427,189 | +16.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Samron Midwest … | #2 E. T. Simonds C… |
|---|---|---|---|---|---|---|---|
| 1 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $7,500.00 | $7,150.00 | |
| 2 | 40600290 | BIT MATLS TACK CT | 17,418 | POUND | $0.0100 | $0.0100 | |
| 3 | 40600370 | LONG JOINT SEALANT | 9,534 | FOOT | $2.75 | $3.37 | |
| 4 | 40600405 | MATL TRANSFER DEVICE | 4,272 | TON | $2.00 | $3.41 | |
| 5 | 40600982 | HMA SURF REM BUTT JT | 245 | SQ YD | $20.00 | $34.21 | |
| 6 | 40600990 | TEMPORARY RAMP | 129 | SQ YD | $30.00 | $41.24 | |
| 7 | 40602970 | HMA BC IL-9.5FG N70 | 2,136 | TON | $98.00 | $101.63 | |
| 8 | 40604062 | HMA SC IL-9.5 D N70 | 2,136 | TON | $104.00 | $113.74 | |
| 9 | 40800050 | INCIDENTAL HMA SURF | 21 | TON | $700.00 | $731.46 | |
| 10 | 42001300 | PROTECTIVE COAT | 43 | SQ YD | $0.0100 | $0.0100 | |
| 11 | 42400200 | PC CONC SIDEWALK 5 | 395 | SQ FT | $105.00 | $60.28 | |
| 12 | 42400800 | DETECTABLE WARNINGS | 139 | SQ FT | $35.00 | $32.86 | |
| 13 | 44000153 | HMA SURF REM 1 | 11,496 | SQ YD | $2.25 | $1.58 | |
| 14 | 44000161 | HMA SURF REM 3 | 14,251 | SQ YD | $2.50 | $3.28 | |
| 15 | 44000500 | COMB CURB GUTTER REM | 179 | FOOT | $10.00 | $52.98 | |
| 16 | 44000600 | SIDEWALK REM | 388 | SQ FT | $20.00 | $48.88 | |
| 17 | 44201423 | CL C PATCH T1 16 | 19 | SQ YD | $200.00 | $235.00 | |
| 18 | 44201427 | CL C PATCH T2 16 | 453 | SQ YD | $195.00 | $230.00 | |
| 19 | 44201431 | CL C PATCH T3 16 | 66 | SQ YD | $190.00 | $227.00 | |
| 20 | 44201433 | CL C PATCH T4 16 | 1,875.56 | SQ YD | $185.00 | $220.00 | |
| 21 | 48102100 | AGG WEDGE SHLD TYPE B | 239 | TON | $60.00 | $61.20 | |
| 22 | 48203100 | HMA SHOULDERS | 55 | TON | $85.00 | $130.06 | |
| 23 | 60603800 | COMB CC&G TB6.12 | 182 | FOOT | $60.00 | $71.87 | |
| 24 | 67100100 | MOBILIZATION | 1 | L SUM | $74,000.00 | $90,472.94 | |
| 25 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $14,000.00 | $23,862.47 | |
| 26 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $0.0100 | $32,044.87 | |
| 27 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $8,000.00 | $10,140.85 | |
| 28 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $3,000.00 | $0.0100 | |
| 29 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $90.00 | $41.25 | |
| 30 | 70300100 | SHORT TERM PAVT MKING | 2,898 | FOOT | $2.20 | $1.67 | |
| 31 | 70300150 | SHRT TRM PAVT MK REM | 966 | SQ FT | $0.0100 | $0.0100 | |
| 32 | 70300211 | TEMP PVT MK LTR & SYM PAINT | 123 | SQ FT | $0.0100 | $0.0100 | |
| 33 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 12,477 | FOOT | $0.0100 | $0.0100 | |
| 34 | 70300241 | TEMP PVT MK LINE 6 - PAINT | 302 | FOOT | $0.0100 | $0.0100 | |
| 35 | 70300261 | TEMP PVT MK LINE 12 - PAINT | 282 | FOOT | $0.0100 | $0.0100 | |
| 36 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 121 | FOOT | $0.0100 | $0.0100 | |
| 37 | 78000400 | THPL PVT MK LINE 6 | 302 | FOOT | $5.85 | $6.44 | |
| 38 | 78000600 | THPL PVT MK LINE 12 | 282 | FOOT | $12.10 | $13.20 | |
| 39 | 78000650 | THPL PVT MK LINE 24 | 121 | FOOT | $24.00 | $26.40 | |
| 40 | 78001100 | PT PVT MK LTRS & SYMB | 123 | SQ FT | $4.00 | $4.40 | |
| 41 | 78001110 | PAINT PVT MK LINE 4 | 12,477 | FOOT | $0.6100 | $0.6600 | |
| 42 | 78100100 | RAISED REFL PAVT MKR | 121 | EACH | $66.00 | $71.50 | |
| 43 | 78300200 | RAISED REF PVT MK REM | 121 | EACH | $13.00 | $18.37 | |
| 44 | 78300201 | PVT MKG REM GRINDING | 4,957 | SQ FT | $0.0100 | $0.0100 |