(101)RS-7
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Samron Midwest Contracting, Inc. Low bidder | $1,048,828 | ||
| 2 | E. T. Simonds Construction Company | $1,191,952 | +13.6% | |
| 3 | Southern Illinois Asphalt Co., Inc. | $1,359,531 | +29.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Samron Midwest … | #2 E. T. Simonds C… | #3 Southern Illino… |
|---|---|---|---|---|---|---|---|---|
| 1 | X1700066 | POTHOLING | 12 | EACH | $1,000.00 | $1,379.13 | $1,211.38 | |
| 2 | X7340100 | CONC FOUNDATION GR MT | 1 | CU YD | $5,000.00 | $5,815.23 | $5,967.02 | |
| 3 | X8570215 | FAC IN EXIST CAB | 1 | EACH | $3,300.00 | $9,384.79 | $9,629.76 | |
| 4 | X8760200 | ACCESSIBLE PED SIGNAL | 8 | EACH | $2,630.00 | $2,019.05 | $2,071.76 | |
| 5 | Z0034105 | MATL TRANSFER DEVICE | 2,379 | TON | $2.00 | $5.46 | $8.83 | |
| 6 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $5,000.00 | $4,500.00 | $2,850.00 | |
| 7 | 40600290 | BIT MATLS TACK CT | 9,556 | POUND | $0.0100 | $0.0100 | $0.8900 | |
| 8 | 40600990 | TEMPORARY RAMP | 1,981 | SQ YD | $5.00 | $0.0100 | $0.0100 | |
| 9 | 40604164 | P HMA SC IL-9.5 D N90 | 2,379 | TON | $125.00 | $135.13 | $186.63 | |
| 10 | 42001300 | PROTECTIVE COAT | 66 | SQ YD | $1.00 | $25.00 | $0.0100 | |
| 11 | 42400100 | PC CONC SIDEWALK 4 | 2,430 | SQ FT | $20.00 | $16.16 | $13.98 | |
| 12 | 42400800 | DETECTABLE WARNINGS | 160 | SQ FT | $20.00 | $18.70 | $19.38 | |
| 13 | 44000157 | HMA SURF REM 2 | 21,236 | SQ YD | $3.60 | $7.35 | $6.93 | |
| 14 | 44000500 | COMB CURB GUTTER REM | 298 | FOOT | $10.00 | $17.78 | $18.42 | |
| 15 | 44000600 | SIDEWALK REM | 2,200 | SQ FT | $8.00 | $8.18 | $8.48 | |
| 16 | 44201403 | CL C PATCH T2 14 | 224 | SQ YD | $250.00 | $198.00 | $250.80 | |
| 17 | 44201407 | CL C PATCH T3 14 | 152 | SQ YD | $210.00 | $182.00 | $250.80 | |
| 18 | 44201409 | CL C PATCH T4 14 | 1,167 | SQ YD | $185.00 | $180.00 | $222.30 | |
| 19 | 60603800 | COMB CC&G TB6.12 | 298 | FOOT | $40.00 | $63.23 | $65.53 | |
| 20 | 67000400 | ENGR FIELD OFFICE A | 3 | CAL MO | $1,250.00 | $2,000.00 | $2,280.00 | |
| 21 | 67100100 | MOBILIZATION | 1 | L SUM | $60,000.00 | $61,000.00 | $48,652.46 | |
| 22 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $5,000.00 | $30,659.82 | $0.0100 | |
| 23 | 70102622 | TR CONT & PROT 701502 | 1 | L SUM | $15,000.00 | $13,924.67 | $46,638.44 | |
| 24 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $0.0100 | $3,308.13 | $478.80 | |
| 25 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1,000.00 | $2,925.33 | $0.0100 | |
| 26 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $100.00 | $75.00 | $85.50 | |
| 27 | 70300100 | SHORT TERM PAVT MKING | 321 | FOOT | $0.0100 | $57.49 | $9.50 | |
| 28 | 70300150 | SHRT TRM PAVT MK REM | 107 | SQ FT | $0.0100 | $0.0100 | $0.0100 | |
| 29 | 70300211 | TEMP PVT MK LTR & SYM PAINT | 776 | SQ FT | $0.0100 | $0.0100 | $0.0100 | |
| 30 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 13,376 | FOOT | $0.0100 | $0.0100 | $0.0100 | |
| 31 | 70300241 | TEMP PVT MK LINE 6 - PAINT | 288 | FOOT | $0.0100 | $0.0100 | $0.0100 | |
| 32 | 70300261 | TEMP PVT MK LINE 12 - PAINT | 558 | FOOT | $0.0100 | $0.0100 | $0.0100 | |
| 33 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 120 | FOOT | $0.0100 | $0.0100 | $0.0100 | |
| 34 | 78000100 | THPL PVT MK LTR & SYM | 776 | SQ FT | $7.00 | $7.43 | $7.70 | |
| 35 | 78000200 | THPL PVT MK LINE 4 | 13,376 | FOOT | $1.25 | $1.24 | $1.29 | |
| 36 | 78000400 | THPL PVT MK LINE 6 | 288 | FOOT | $1.80 | $1.87 | $1.94 | |
| 37 | 78000600 | THPL PVT MK LINE 12 | 558 | FOOT | $3.60 | $3.74 | $3.88 | |
| 38 | 78000650 | THPL PVT MK LINE 24 | 120 | FOOT | $7.25 | $7.59 | $7.87 | |
| 39 | 78100100 | RAISED REFL PAVT MKR | 261 | EACH | $39.00 | $40.70 | $42.18 | |
| 40 | 78300200 | RAISED REF PVT MK REM | 261 | EACH | $10.00 | $10.22 | $11.34 | |
| 41 | 78300201 | PAVMT MRKG REM GRIND | 6,176 | SQ FT | $0.0100 | $0.0100 | $0.0100 | |
| 42 | 80500010 | SERV INSTALL GRND MT | 1 | EACH | $14,000.00 | $14,635.13 | $15,017.14 | |
| 43 | 81028350 | UNDRGRD C PVC 2 | 164 | FOOT | $26.25 | $60.75 | $62.34 | |
| 44 | 81028390 | UNDRGRD C PVC 4 | 251 | FOOT | $60.00 | $66.54 | $68.27 | |
| 45 | 87301225 | ELCBL C SIGNAL 14 3C | 945 | FOOT | $3.00 | $3.17 | $3.25 | |
| 46 | 87301245 | ELCBL C SIGNAL 14 5C | 143 | FOOT | $8.00 | $8.83 | $9.06 | |
| 47 | 87301815 | ELCBL C SERV 6 3C | 62 | FOOT | $37.00 | $38.79 | $39.80 | |
| 48 | 87301900 | ELCBL C EGRDC 6 1C | 400 | FOOT | $4.00 | $4.14 | $4.25 | |
| 49 | 87500600 | TS POST 10 | 1 | EACH | $2,300.00 | $2,456.73 | $2,520.86 | |
| 50 | 87600100 | PED PUSH-BUT POST T1 | 6 | EACH | $1,740.00 | $1,837.64 | $1,885.61 | |
| 51 | 87800100 | CONC FDN TY A | 3 | FOOT | $1,260.00 | $1,336.45 | $1,371.33 | |
| 52 | 87900100 | DRILL EX FOUNDATION | 2 | EACH | $1,000.00 | $1,064.96 | $1,092.76 | |
| 53 | 87900200 | DRILL EX HANDHOLE | 14 | EACH | $450.00 | $456.41 | $468.32 | |
| 54 | 88102717 | PED SH LED 1F BM CDT | 8 | EACH | $1,345.00 | $1,442.65 | $1,480.31 | |
| 55 | 88600100 | DET LOOP T1 | 540 | FOOT | $20.00 | $21.42 | $21.97 | |
| 56 | 89502375 | REMOV EX TS EQUIP | 1 | EACH | $12,000.00 | $4,259.83 | $4,371.02 |