D9 PATCH 2021-5
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $117,195 | ||
| 2 | Samron Midwest Contracting, Inc. | $128,707 | +9.8% | |
| 3 | Kinney Contractors, Inc. | $131,466 | +12.2% | |
| 4 | G. M. Sipes Construction, Inc. | $182,224 | +55.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Samron Midwest … | #3 Kinney Contract… | #4 G. M. Sipes Con… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X4420716 | CL C PATCH T1 9 SPL | 22 | SQ YD | $150.00 | $145.00 | $180.00 | $290.00 | |
| 2 | X4420718 | CL C PATCH T2 9 SPL | 37 | SQ YD | $120.00 | $140.00 | $147.00 | $215.00 | |
| 3 | X4420720 | CL C PATCH T3 9 SPL | 77 | SQ YD | $115.00 | $135.00 | $144.00 | $215.00 | |
| 4 | X4420722 | CL C PATCH T4 9 SPL | 410 | SQ YD | $110.00 | $130.00 | $140.00 | $190.00 | |
| 5 | 44200050 | WELDED WIRE REINF | 597 | SQ YD | $14.73 | $10.00 | $12.00 | $15.00 | |
| 6 | 44201371 | CL C PATCH T4 11 | 110 | SQ YD | $133.32 | $165.00 | $155.00 | $195.00 | |
| 7 | 44213200 | SAW CUTS | 1,927 | FOOT | $3.08 | $4.00 | $0.0100 | $4.95 | |
| 8 | 44213204 | TIE BARS 3/4 | 614 | EACH | $16.72 | $1.00 | $14.00 | $10.00 | |
| 9 | 67100100 | MOBILIZATION | 1 | L SUM | $5,875.94 | $7,500.00 | $10,000.00 | $9,000.00 | |
| 10 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $9,363.29 | $15,300.00 | $9,000.00 | $18,000.00 | |
| 11 | 70107025 | CHANGEABLE MESSAGE SN | 14 | CAL DA | $42.86 | $100.00 | $125.00 | $25.00 |