(44-5,44-6)RS-2;BRIDGE REPAIR 2022-1
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $17,924,407 | ||
| 2 | Southern Illinois Asphalt Co., Inc. | $19,733,457 | +10.1% | |
| 3 | Samron Midwest Contracting, Inc. | $19,968,158 | +11.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Southern Illino… | #3 Samron Midwest … |
|---|---|---|---|---|---|---|---|---|
| 1 | X0100002 | GRADING & SHAPING SPL | 2 | SQ YD | $68.28 | $261.25 | $325.00 | |
| 2 | X0322278 | RODENT SHIELDS | 406 | EACH | $119.77 | $108.88 | $200.00 | |
| 3 | X0323818 | CLN & PT EXP RE-BAR | 140 | SQ FT | $81.17 | $250.00 | $85.00 | |
| 4 | X0325748 | ACRYLIC COATING | 54.6 | SQ YD | $130.90 | $62.00 | $55.00 | |
| 5 | X0325749 | FIBER WRAP | 503.6 | SQ FT | $97.52 | $125.00 | $500.00 | |
| 6 | X0900092 | REPAIR BRIDGE RAIL | 30 | FOOT | $151.80 | $261.53 | $175.00 | |
| 7 | X2503100 | MOWING | 556 | UNIT | $34.19 | $20.90 | $12.00 | |
| 8 | X4201410 | BR APPR PAVT CONN SPL | 1,224 | SQ YD | $197.17 | $182.06 | $200.00 | |
| 9 | X5030250 | BR DECK GROOVING LONG | 5,799 | SQ YD | $9.57 | $9.01 | $12.00 | |
| 10 | X6350120 | DELINEATOR REMOVAL | 486 | EACH | $9.35 | $17.87 | $8.50 | |
| 11 | X7830050 | RAISD REF PM REFL REM | 64 | EACH | $10.09 | $25.00 | $17.00 | |
| 12 | Z0001903 | STRUCT STEEL REMOV | 12,272 | POUND | $2.04 | $2.13 | $1.30 | |
| 13 | Z0004552 | APPROACH SLAB REM | 1,226 | SQ YD | $38.69 | $70.29 | $175.00 | |
| 14 | Z0006021 | BR DK LTX C OLY 3 1/4 | 7,650 | SQ YD | $162.18 | $162.98 | $160.00 | |
| 15 | Z0007101 | C&D LEAD PT CL RS N1 | 1 | L SUM | $4,148.10 | $3,940.70 | $3,900.00 | |
| 16 | Z0007102 | C&D LEAD PT CL RS N2 | 1 | L SUM | $4,148.10 | $3,940.70 | $3,900.00 | |
| 17 | Z0007103 | C&D LEAD PT CL RS N3 | 1 | L SUM | $3,110.80 | $2,955.26 | $2,900.00 | |
| 18 | Z0007104 | C&D LEAD PT CL RS N4 | 1 | L SUM | $3,110.80 | $2,955.26 | $2,900.00 | |
| 19 | Z0010501 | CLEAN & PT STL BR N1 | 1 | L SUM | $23,505.90 | $22,330.61 | $22,000.00 | |
| 20 | Z0010502 | CLEAN & PT STL BR N2 | 1 | L SUM | $23,505.90 | $22,330.61 | $16,500.00 | |
| 21 | Z0010503 | CLEAN & PT STL BR N3 | 1 | L SUM | $17,629.70 | $16,748.22 | $16,500.00 | |
| 22 | Z0010504 | CLEAN & PT STL BR N4 | 1 | L SUM | $17,629.70 | $16,748.22 | $16,500.00 | |
| 23 | Z0012148 | BR DECK SCAR 3 | 7,830 | SQ YD | $47.90 | $67.93 | $50.00 | |
| 24 | Z0012754 | STR REP CON DP = < 5 | 931 | SQ FT | $179.64 | $136.21 | $145.00 | |
| 25 | Z0012755 | STR REP CON DP OVER 5 | 66 | SQ FT | $227.18 | $156.75 | $300.00 | |
| 26 | Z0015550 | DEBRIS REMOVAL | 2 | CU YD | $916.53 | $182.94 | $1,500.00 | |
| 27 | Z0016001 | DECK SLAB REP (FD-T1) | 1 | SQ YD | $1,765.07 | $1,567.50 | $1,675.00 | |
| 28 | Z0016002 | DECK SLAB REP (FD-T2) | 23 | SQ YD | $1,019.17 | $1,567.50 | $1,300.00 | |
| 29 | Z0029090 | DIAMOND GRIND BR SEC | 10,628 | SQ YD | $9.93 | $12.74 | $12.00 | |
| 30 | Z0034105 | MATL TRANSFER DEVICE | 26,997 | TON | $2.87 | $2.65 | $2.00 | |
| 31 | Z0041895 | POLYMER CONCRETE | 79.6 | CU FT | $874.55 | $525.13 | $1,100.00 | |
| 32 | Z0043800 | P P CONC I-BM REPAIR | 96.3 | SQ FT | $595.95 | $390.65 | $375.00 | |
| 33 | Z0065730 | SLOPEWALL SLUR PUMPNG | 15.3 | CU YD | $652.19 | $522.50 | $375.00 | |
| 34 | Z0076600 | TRAINEES | 1,500 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 35 | Z0076604 | TRAINEES TPG | 1,500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 36 | 20100110 | TREE REMOV 6-15 | 46 | UNIT | $89.25 | $53.71 | $75.00 | |
| 37 | 20200600 | EXC & GR EX SHOULDER | 105 | UNIT | $374.17 | $712.29 | $550.00 | |
| 38 | 20300100 | CHANNEL EXCAVATION | 50 | CU YD | $54.30 | $46.84 | $65.00 | |
| 39 | 20300200 | ROCK EXCAV CHANNEL | 13.5 | CU YD | $265.50 | $52.27 | $250.00 | |
| 40 | 28100805 | STONE DUMP RIP CL A3 | 15 | TON | $118.99 | $50.04 | $100.00 | |
| 41 | 40600295 | P BIT MATLS TACK CT | 233,550 | POUND | $0.00 | $0.00 | $0.00 | |
| 42 | 40600990 | TEMPORARY RAMP | 2,197 | SQ YD | $0.00 | $10.86 | $25.00 | |
| 43 | 40605024 | P SC SMA 9.5 E N80 | 26,997 | TON | $127.76 | $158.68 | $105.00 | |
| 44 | 40800050 | INCIDENTAL HMA SURF | 72 | TON | $216.82 | $255.46 | $250.00 | |
| 45 | 44000155 | HMA SURF REM 1 1/2 | 518,925 | SQ YD | $1.03 | $1.68 | $1.20 | |
| 46 | 44004250 | PAVED SHLD REMOVAL | 25,676 | SQ YD | $13.89 | $6.59 | $8.00 | |
| 47 | 44200050 | WELDED WIRE REINF | 186 | SQ YD | $29.50 | $20.00 | $30.00 | |
| 48 | 44200573 | CL A PATCH T1 12 | 8 | SQ YD | $350.00 | $275.00 | $225.00 | |
| 49 | 44200577 | CL A PATCH T2 12 | 769 | SQ YD | $170.00 | $200.00 | $215.00 | |
| 50 | 44200581 | CL A PATCH T3 12 | 355 | SQ YD | $166.00 | $200.00 | $210.00 | |
| 51 | 44200583 | CL A PATCH T4 12 | 5,526 | SQ YD | $163.00 | $175.00 | $192.00 | |
| 52 | 44200994 | CL B PATCH T2 12 | 369 | SQ YD | $225.00 | $200.00 | $185.00 | |
| 53 | 44200998 | CL B PATCH T3 12 | 150 | SQ YD | $220.00 | $200.00 | $175.00 | |
| 54 | 44201000 | CL B PATCH T4 12 | 36 | SQ YD | $200.00 | $200.00 | $170.00 | |
| 55 | 44201298 | DOWEL BARS 1 1/4 | 1,232 | EACH | $22.46 | $20.00 | $17.00 | |
| 56 | 44213000 | PATCH REINFORCEMENT | 6,658 | SQ YD | $46.19 | $55.00 | $50.00 | |
| 57 | 44213200 | SAW CUTS | 22,043 | FOOT | $5.97 | $0.0100 | $8.00 | |
| 58 | 44213204 | TIE BARS 3/4 | 4,732 | EACH | $17.01 | $0.0100 | $15.00 | |
| 59 | 48102100 | AGG WEDGE SHLD TYPE B | 404 | TON | $80.06 | $147.76 | $40.00 | |
| 60 | 48203100 | HMA SHOULDERS | 16,720 | TON | $74.42 | $98.79 | $75.00 | |
| 61 | 48300415 | PCC SHOULDERS 9 3/4 | 15,081 | SQ YD | $82.45 | $69.75 | $130.00 | |
| 62 | 48300615 | PCC SHOULDERS 11 3/4 | 11,065 | SQ YD | $64.53 | $81.56 | $70.00 | |
| 63 | 48301000 | PROTECTIVE COAT | 11,065 | SQ YD | $0.00 | $0.0100 | $0.00 | |
| 64 | 50102400 | CONC REM | 272.2 | CU YD | $1,672.02 | $814.27 | $1,750.00 | |
| 65 | 50157300 | PROTECTIVE SHIELD | 1,120 | SQ YD | $47.75 | $49.23 | $115.00 | |
| 66 | 50200100 | STRUCTURE EXCAVATION | 581.6 | CU YD | $26.88 | $32.24 | $100.00 | |
| 67 | 50300225 | CONC STRUCT | 207.5 | CU YD | $684.89 | $797.36 | $650.00 | |
| 68 | 50300255 | CONC SUP-STR | 393.9 | CU YD | $1,235.78 | $1,189.10 | $2,000.00 | |
| 69 | 50300300 | PROTECTIVE COAT | 9,306 | SQ YD | $1.12 | $2.09 | $1.50 | |
| 70 | 50301350 | CONC SUPSTR APP SLAB | 608.6 | CU YD | $443.58 | $478.49 | $500.00 | |
| 71 | 50800205 | REINF BARS, EPOXY CTD | 295,480 | POUND | $1.74 | $1.52 | $1.75 | |
| 72 | 50800515 | BAR SPLICERS | 2,341 | EACH | $53.49 | $53.01 | $55.00 | |
| 73 | 52000110 | PREF JT STRIP SEAL | 382 | FOOT | $229.95 | $235.13 | $165.00 | |
| 74 | 52100010 | ELAST BEARING ASSY T1 | 48 | EACH | $1,564.37 | $1,029.33 | $2,200.00 | |
| 75 | 52200020 | TEMP SOIL RETEN SYSTM | 480 | SQ FT | $201.16 | $227.16 | $295.00 | |
| 76 | 54003000 | CONC BOX CUL | 22.5 | CU YD | $1,023.79 | $2,036.18 | $750.00 | |
| 77 | 58600101 | GRANULAR BACKFILL STR | 803 | CU YD | $54.91 | $47.47 | $50.00 | |
| 78 | 59000200 | EPOXY CRACK INJECTION | 4 | FOOT | $276.76 | $130.63 | $125.00 | |
| 79 | 59100100 | GEOCOMPOSITE WALL DR | 94 | SQ YD | $22.95 | $36.58 | $60.00 | |
| 80 | 60100060 | CONC HDWL FOR P DRAIN | 32 | EACH | $264.17 | $156.75 | $350.00 | |
| 81 | 60146304 | P UNDR FOR STRUCT 4 | 928 | FOOT | $19.29 | $14.08 | $30.00 | |
| 82 | 60600605 | CONC CURB TB | 360 | FOOT | $50.48 | $39.24 | $20.00 | |
| 83 | 60905305 | BOX CUL TO BE CLEANED | 1,330 | FOOT | $17.28 | $16.87 | $90.00 | |
| 84 | 63000001 | SPBGR TY A 6FT POSTS | 7,452.5 | FOOT | $37.95 | $34.50 | $35.00 | |
| 85 | 63000003 | SPBGR TY A 9FT POSTS | 3,687.5 | FOOT | $45.65 | $41.50 | $40.00 | |
| 86 | 63100045 | TRAF BAR TERM T2 | 7 | EACH | $1,925.00 | $1,750.00 | $1,800.00 | |
| 87 | 63100085 | TRAF BAR TERM T6 | 24 | EACH | $4,290.00 | $3,900.00 | $4,000.00 | |
| 88 | 63100167 | TR BAR TRM T1 SPL TAN | 28 | EACH | $4,015.00 | $3,650.00 | $3,800.00 | |
| 89 | 63200310 | GUARDRAIL REMOV | 12,902 | FOOT | $5.78 | $5.25 | $5.25 | |
| 90 | 63500105 | DELINEATORS | 486 | EACH | $102.85 | $75.00 | $100.00 | |
| 91 | 64200116 | SHOULDER RUM STRIP 16 | 220,329 | FOOT | $0.1800 | $0.1800 | $0.1700 | |
| 92 | 67000400 | ENGR FIELD OFFICE A | 22 | CAL MO | $2,000.00 | $2,548.40 | $1,250.00 | |
| 93 | 67100100 | MOBILIZATION | 1 | L SUM | $1,112,604.93 | $1,308,318.07 | $1,188,000.00 | |
| 94 | 70100207 | TRAF CONT-PROT 701402 | 12 | EACH | $1,515.00 | $6,566.75 | $0.00 | |
| 95 | 70100420 | TRAF CONT-PROT 701411 | 8 | EACH | $4,500.00 | $2,809.43 | $3,500.00 | |
| 96 | 70100700 | TRAF CONT-PROT 701406 | 1 | L SUM | $9,109.06 | $151,105.68 | $0.00 | |
| 97 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $431,052.74 | $492,925.97 | $672,000.00 | |
| 98 | 70100825 | TRAF CONT-PROT 701456 | 1 | L SUM | $51,692.63 | $13,746.78 | $25,000.00 | |
| 99 | 70103815 | TR CONT SURVEILLANCE | 60 | CAL DA | $645.69 | $313.50 | $400.00 | |
| 100 | 70107025 | CHANGEABLE MESSAGE SN | 84 | CAL DA | $75.00 | $127.42 | $100.00 | |
| 101 | 70300100 | SHORT TERM PAVT MKING | 29,725 | FOOT | $0.4100 | $1.64 | $0.8500 | |
| 102 | 70300150 | SHRT TRM PAVT MK REM | 9,908 | SQ FT | $1.51 | $0.00 | $0.9000 | |
| 103 | 70300211 | TEMP PVT MK LTR & SYM PAINT | 42 | SQ FT | $0.00 | $0.00 | $0.00 | |
| 104 | 70300241 | TEMP PVT MK LINE 6 - PAINT | 270,492 | FOOT | $0.00 | $0.1600 | $0.00 | |
| 105 | 70300251 | TEMP PVT MK LINE 8 - PAINT | 6,527 | FOOT | $0.00 | $0.00 | $0.00 | |
| 106 | 70300261 | TEMP PVT MK LINE 12 - PAINT | 105 | FOOT | $0.00 | $0.00 | $0.00 | |
| 107 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 34 | FOOT | $0.00 | $0.00 | $0.00 | |
| 108 | 70400100 | TEMP CONC BARRIER | 5,739 | FOOT | $19.36 | $29.10 | $75.00 | |
| 109 | 70400125 | PIN TEMP CONC BARRIER | 144 | EACH | $20.73 | $167.20 | $50.00 | |
| 110 | 70400200 | REL TEMP CONC BARRIER | 5,739 | FOOT | $5.16 | $8.28 | $15.00 | |
| 111 | 70600250 | IMP ATTN TEMP NRD TL3 | 12 | EACH | $2,835.08 | $2,612.50 | $13,500.00 | |
| 112 | 70600350 | IMP ATTN REL NRD TL3 | 12 | EACH | $462.61 | $522.50 | $2,500.00 | |
| 113 | 72501000 | TERMINAL MARKER - DA | 28 | EACH | $46.20 | $42.00 | $45.00 | |
| 114 | 78000100 | THPL PVT MK LTR & SYM | 854 | SQ FT | $8.80 | $8.00 | $8.40 | |
| 115 | 78000400 | THPL PVT MK LINE 6 | 270,492 | FOOT | $0.7600 | $0.6900 | $0.7000 | |
| 116 | 78000500 | THPL PVT MK LINE 8 | 6,527 | FOOT | $0.8300 | $0.7500 | $0.7500 | |
| 117 | 78000600 | THPL PVT MK LINE 12 | 201 | FOOT | $8.80 | $8.00 | $8.25 | |
| 118 | 78000650 | THPL PVT MK LINE 24 | 34 | FOOT | $11.00 | $10.00 | $10.00 | |
| 119 | 78011000 | GRV RCSD PM LTR & SYM | 854 | SQ FT | $2.75 | $2.50 | $2.50 | |
| 120 | 78011035 | GRV RCSD PVT MRKG 7 | 270,492 | FOOT | $0.5500 | $0.5000 | $0.5000 | |
| 121 | 78011045 | GRV RCSD PVT MRKG 9 | 6,527 | FOOT | $0.7200 | $0.6500 | $0.6500 | |
| 122 | 78011065 | GRV RCSD PVT MRKG 13 | 201 | FOOT | $2.75 | $2.50 | $2.50 | |
| 123 | 78011125 | GRV RCSD PVT MRKG 25 | 34 | FOOT | $3.30 | $3.00 | $3.00 | |
| 124 | 78100100 | RAISED REFL PAVT MKR | 1,975 | EACH | $31.55 | $28.68 | $30.00 | |
| 125 | 78112000 | RAISED REFL PAVT MKR BRDG | 24 | EACH | $31.55 | $28.68 | $30.00 | |
| 126 | 78200005 | GRDRAIL REF TYPE A | 165 | EACH | $11.55 | $10.50 | $11.00 | |
| 127 | 78200010 | BARR WALL REF TYPE B | 152 | EACH | $13.04 | $25.00 | $17.00 | |
| 128 | 78300200 | RAISED REF PVT MK REM | 1,999 | EACH | $7.92 | $5.95 | $6.00 | |
| 129 | 78300201 | PAVMT MRKG REM GRIND | 139,723 | SQ FT | $0.00 | $0.6200 | $0.00 |