28-5, 106(W-3, RS-8)
- Let date
- Friday, November 6, 2020
- Contract
- 78481 · job page
- District
- District 9
- County
- Franklin
- Highway
- Limits
- 0.64 miles of PCC replacement, HMA resurfacing, new curb and gutter and inlets; sidewalk and multi-use path will be replaced and/or constructed the length of the project on IL 149 in West Frankfort.
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Samron Midwest Contracting, Inc. Low bidder | $2,556,842 | ||
| 2 | E. T. Simonds Construction Company | $2,913,204 | +13.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Samron Midwest … | #2 E. T. Simonds C… |
|---|---|---|---|---|---|---|---|
| 1 | A2C025G5 | T-CERCIS CANAD CG 5G | 3 | EACH | $450.00 | $420.00 | |
| 2 | A2C19G06 | T-CRAPE MYRTL SP 3 CG | 2 | EACH | $660.00 | $630.00 | |
| 3 | X0327979 | PAVMT MRKG REM GRIND | 9,562 | SQ FT | $1.60 | $0.00 | |
| 4 | X1700067 | STAMP COL PCC SDWLK 5 | 4,330 | SQ FT | $12.50 | $15.49 | |
| 5 | X2200003 | FENCE (SPECIAL) | 200 | FOOT | $35.00 | $55.60 | |
| 6 | X4401198 | HMA SURF REM VAR DP | 9,509 | SQ YD | $3.30 | $3.00 | |
| 7 | X7240300 | SIGN REMOVAL | 19 | EACH | $600.00 | $428.53 | |
| 8 | Z0007601 | BLDG REMOV NO 1 | 1 | L SUM | $13,500.00 | $12,600.00 | |
| 9 | Z0007602 | BLDG REMOV NO 2 | 1 | L SUM | $10,000.00 | $9,450.00 | |
| 10 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $29,000.00 | $45,000.00 | |
| 11 | Z0033700 | LONG JOINT SEALANT | 5,004 | FOOT | $4.00 | $4.53 | |
| 12 | Z0034105 | MATL TRANSFER DEVICE | 1,738 | TON | $2.80 | $4.76 | |
| 13 | Z0049901 | R&D NON-FR ASB BLD 1 | 1 | L SUM | $2,000.00 | $0.00 | |
| 14 | Z0075496 | CONC RETAIN WALL REM | 16 | FOOT | $75.00 | $165.75 | |
| 15 | Z0076600 | TRAINEES | 1,000 | HOUR | $0.8000 | $0.8000 | |
| 16 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | $15.00 | |
| 17 | 20100110 | TREE REMOV 6-15 | 22 | UNIT | $166.00 | $157.50 | |
| 18 | 20100210 | TREE REMOV OVER 15 | 66 | UNIT | $67.00 | $63.00 | |
| 19 | 20200100 | EARTH EXCAVATION | 6,989 | CU YD | $18.00 | $1.17 | |
| 20 | 20800150 | TRENCH BACKFILL | 297 | CU YD | $35.00 | $39.49 | |
| 21 | 20900110 | POROUS GRAN BACKFILL | 624 | CU YD | $40.00 | $54.71 | |
| 22 | 25000100 | SEEDING CL 1 | 1 | ACRE | $2,200.00 | $2,100.00 | |
| 23 | 25000350 | SEEDING CL 7 | 1 | ACRE | $1,700.00 | $1,575.00 | |
| 24 | 25000400 | NITROGEN FERT NUTR | 171 | POUND | $2.25 | $2.10 | |
| 25 | 25000500 | PHOSPHORUS FERT NUTR | 86 | POUND | $2.25 | $2.10 | |
| 26 | 25000600 | POTASSIUM FERT NUTR | 86 | POUND | $2.25 | $2.10 | |
| 27 | 25000700 | AGR GROUND LIMESTONE | 2 | TON | $110.00 | $105.00 | |
| 28 | 25100115 | MULCH METHOD 2 | 2 | ACRE | $1,100.00 | $1,050.00 | |
| 29 | 25100630 | EROSION CONTR BLANKET | 4,171 | SQ YD | $2.00 | $1.94 | |
| 30 | 28000250 | TEMP EROS CONTR SEED | 285 | POUND | $1.25 | $5.71 | |
| 31 | 28000500 | INLET & PIPE PROTECT | 22 | EACH | $330.00 | $263.57 | |
| 32 | 31100300 | SUB GRAN MAT A 4 | 169 | SQ YD | $25.00 | $19.44 | |
| 33 | 31100500 | SUB GRAN MAT A 6 | 5,001 | SQ YD | $10.00 | $14.40 | |
| 34 | 40600290 | BIT MATLS TACK CT | 7,544 | POUND | $0.0100 | $0.00 | |
| 35 | 40600990 | TEMPORARY RAMP | 56 | SQ YD | $40.00 | $256.94 | |
| 36 | 40603219 | P HMA BC IL-9.5FG N90 | 799 | TON | $100.00 | $91.61 | |
| 37 | 40604164 | P HMA SC IL-9.5 D N90 | 939 | TON | $110.00 | $110.08 | |
| 38 | 40800050 | INCIDENTAL HMA SURF | 19 | TON | $570.00 | $212.20 | |
| 39 | 42000501 | PCC PVT 10 JOINTED | 4,781 | SQ YD | $68.20 | $88.50 | |
| 40 | 42001300 | PROTECTIVE COAT | 4,781 | SQ YD | $0.00 | $0.00 | |
| 41 | 42300200 | PCC DRIVEWAY PAVT 6 | 41 | SQ YD | $117.00 | $70.00 | |
| 42 | 42300300 | PCC DRIVEWAY PAVT 7 | 2,675 | SQ YD | $70.00 | $65.78 | |
| 43 | 42300400 | PCC DRIVEWAY PAVT 8 | 2,007 | SQ YD | $72.00 | $69.33 | |
| 44 | 42400200 | PC CONC SIDEWALK 5 | 42,812 | SQ FT | $4.80 | $7.44 | |
| 45 | 42400800 | DETECTABLE WARNINGS | 650 | SQ FT | $31.00 | $31.50 | |
| 46 | 44000100 | PAVEMENT REM | 6,694 | SQ YD | $10.00 | $12.89 | |
| 47 | 44000155 | HMA SURF REM 1 1/2 | 1,667 | SQ YD | $4.50 | $4.55 | |
| 48 | 44000200 | DRIVE PAVEMENT REM | 2,967 | SQ YD | $10.00 | $15.74 | |
| 49 | 44000300 | CURB REM | 1,009 | FOOT | $5.50 | $11.63 | |
| 50 | 44000500 | COMB CURB GUTTER REM | 3,093 | FOOT | $12.00 | $8.76 | |
| 51 | 44000600 | SIDEWALK REM | 13,984 | SQ FT | $1.50 | $2.76 | |
| 52 | 44003100 | MEDIAN REMOVAL | 488 | SQ FT | $2.50 | $12.79 | |
| 53 | 44004250 | PAVED SHLD REMOVAL | 1,150 | SQ YD | $24.00 | $9.28 | |
| 54 | 50800205 | REINF BARS, EPOXY CTD | 226 | POUND | $30.00 | $9.84 | |
| 55 | 52200900 | CONC STR RETAIN WALL | 105 | CU YD | $1.00 | $5.12 | |
| 56 | 54248510 | CONCRETE COLLAR | 1 | CU YD | $1,000.00 | $1,500.00 | |
| 57 | 550B0360 | STORM SEW CL B 2 15 | 143 | FOOT | $69.00 | $85.51 | |
| 58 | 550B0380 | STORM SEW CL B 2 18 | 175 | FOOT | $72.00 | $76.96 | |
| 59 | 550B0400 | STORM SEW CL B 2 21 | 375 | FOOT | $88.00 | $72.03 | |
| 60 | 550B0410 | STORM SEW CL B 2 24 | 262 | FOOT | $81.00 | $69.70 | |
| 61 | 550B0430 | STORM SEW CL B 2 30 | 527 | FOOT | $93.00 | $90.56 | |
| 62 | 60218300 | MAN TA 4 DIA T1F OL | 3 | EACH | $2,600.00 | $3,484.03 | |
| 63 | 60240210 | INLETS TB T1F OL | 1 | EACH | $2,320.00 | $3,297.02 | |
| 64 | 60240220 | INLETS TB T3F&G | 22 | EACH | $2,500.00 | $3,317.93 | |
| 65 | 60240301 | INLETS TB T8G | 3 | EACH | $2,120.00 | $3,126.53 | |
| 66 | 60255700 | MAN ADJ NEW T1F OL | 9 | EACH | $855.00 | $2,632.47 | |
| 67 | 60256900 | MAN ADJ NEW T15F&L | 1 | EACH | $1,060.00 | $2,872.42 | |
| 68 | 60260500 | INLETS ADJ NEW T3F&G | 6 | EACH | $1,020.00 | $2,677.25 | |
| 69 | 60261500 | INLETS ADJ NEW T15F&L | 2 | EACH | $900.00 | $3,279.42 | |
| 70 | 60500060 | REMOV INLETS | 6 | EACH | $1,270.00 | $1,089.54 | |
| 71 | 60500090 | REM INLET- MAIN FLOW | 17 | EACH | $1,500.00 | $1,880.15 | |
| 72 | 60605000 | COMB CC&G TB6.24 | 5,368 | FOOT | $35.20 | $39.08 | |
| 73 | 66700305 | PERM SURV MKRS T2 | 3 | EACH | $221.00 | $309.75 | |
| 74 | 66900200 | NON SPL WASTE DISPOSL | 305 | CU YD | $76.30 | $35.44 | |
| 75 | 66900530 | SOIL DISPOSAL ANALY | 10 | EACH | $1,900.00 | $1,260.00 | |
| 76 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $5,600.00 | $2,310.00 | |
| 77 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $3,400.00 | $1,942.50 | |
| 78 | 66901006 | REG SUB MON | 1 | CAL DA | $2,800.00 | $945.00 | |
| 79 | 67000400 | ENGR FIELD OFFICE A | 15 | CAL MO | $1,325.00 | $2,000.00 | |
| 80 | 67100100 | MOBILIZATION | 1 | L SUM | $153,290.00 | $254,902.04 | |
| 81 | 67201100 | SEAL ABAN MONIT WELLS | 13 | EACH | $445.00 | $1,100.00 | |
| 82 | 70102622 | TR CONT & PROT 701502 | 1 | L SUM | $60,000.00 | $107,885.06 | |
| 83 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $5,700.00 | $0.00 | |
| 84 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $6,300.00 | $8,545.08 | |
| 85 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $80.00 | $50.00 | |
| 86 | 70300100 | SHORT TERM PAVT MKING | 2,253 | FOOT | $1.00 | $0.3200 | |
| 87 | 70300150 | SHRT TRM PAVT MK REM | 751 | SQ FT | $1.70 | $3.08 | |
| 88 | 70300210 | TEMP PVT MK LTR & SYM | 232 | SQ FT | $2.80 | $0.00 | |
| 89 | 70300220 | TEMP PVT MK LINE 4 | 9,620 | FOOT | $0.5500 | $0.00 | |
| 90 | 70300260 | TEMP PVT MK LINE 12 | 1,160 | FOOT | $2.80 | $0.00 | |
| 91 | 70300280 | TEMP PVT MK LINE 24 | 260 | FOOT | $5.50 | $0.00 | |
| 92 | 78009000 | MOD URETH PM LTR-SYM | 232 | SQ FT | $11.00 | $10.50 | |
| 93 | 78009004 | MOD URETH PM LINE 4 | 9,620 | FOOT | $1.00 | $0.8900 | |
| 94 | 78009012 | MOD URETH PM LINE 12 | 1,160 | FOOT | $11.00 | $10.50 | |
| 95 | 78009024 | MOD URETH PM LINE 24 | 260 | FOOT | $22.00 | $21.00 | |
| 96 | 78100100 | RAISED REFL PAVT MKR | 95 | EACH | $66.00 | $62.21 | |
| 97 | 78300200 | RAISED REF PVT MK REM | 95 | EACH | $6.00 | $18.86 | |
| 98 | 84200600 | REM LT U NO SALV | 8 | EACH | $940.00 | $964.84 |