(580,581)PP-1
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Keeley & Sons, Inc. Low bidder | $198,952 | ||
| 2 | Kinney Contractors, Inc. | $220,887 | +11.0% | |
| 3 | Mayer Landscaping, Inc. | $338,412 | +70.1% | |
| 4 | RCS Construction, Inc. | $498,008 | +150.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Keeley & Sons, … | #2 Kinney Contract… | #3 Mayer Landscapi… | #4 RCS Constructio… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 44200050 | WELDED WIRE REINF | 183 | SQ YD | $8.85 | $15.00 | $18.75 | $12.69 | |
| 2 | 44201007 | CL B PATCH T2 13 | 440 | SQ YD | $193.45 | $200.00 | $360.00 | $315.50 | |
| 3 | 44201011 | CL B PATCH T3 13 | 101 | SQ YD | $193.45 | $198.00 | $360.00 | $313.34 | |
| 4 | 44201013 | CL B PATCH T4 13 | 82 | SQ YD | $193.45 | $196.00 | $360.00 | $317.09 | |
| 5 | 44201299 | DOWEL BARS 1 1/2 | 1,212 | EACH | $24.90 | $30.00 | $30.00 | $31.15 | |
| 6 | 44213200 | SAW CUTS | 3,000 | FOOT | $5.92 | $4.00 | $5.50 | $11.79 | |
| 7 | 44213204 | TIE BARS 3/4 | 14 | EACH | $11.00 | $15.00 | $11.85 | $36.75 | |
| 8 | 67100100 | MOBILIZATION | 1 | L SUM | $12,000.00 | $13,000.00 | $16,200.00 | $88,488.20 | |
| 9 | 70100320 | TRAF CONT-PROT 701422 | 1 | L SUM | $6,780.00 | $13,000.00 | $11,800.00 | $44,724.36 | |
| 10 | 70100825 | TRAF CONT-PROT 701456 | 1 | L SUM | $1,500.00 | $4,000.00 | $4,250.00 | $15,913.48 | |
| 11 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $2,780.00 | $11,000.00 | $3,150.00 | $14,408.98 | |
| 12 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $1,760.00 | $1.00 | $4,350.00 | $10,440.64 | |
| 13 | 70102634 | TR CONT & PROT 701611 | 1 | L SUM | $10.00 | $1.00 | $7,750.00 | $9,821.14 | |
| 14 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $2,390.00 | $500.00 | $3,500.00 | $9,614.64 | |
| 15 | 70200100 | NIGHT WORK ZONE LIGHT | 1 | L SUM | $1,500.00 | $4,000.00 | $6,675.00 | $32,166.80 |