DIST 8 GUARDRAIL 2018-2
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Illini Excavation & Reclamation, Inc. Low bidder | $442,378 | ||
| 2 | Midwest Fence Corporation | $496,114 | +12.1% | |
| 3 | COLLINS & HERMANN, INC. | $643,602 | +45.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Illini Excavati… | #2 Midwest Fence C… | #3 COLLINS & HERMA… |
|---|---|---|---|---|---|---|---|---|
| 1 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 2 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 3 | 20400800 | FURNISHED EXCAVATION | 671.1 | CU YD | $40.50 | $80.00 | $31.94 | |
| 4 | 48101200 | AGGREGATE SHLDS B | 528 | TON | $37.50 | $72.00 | $55.28 | |
| 5 | 63000001 | SPBGR TY A 6FT POSTS | 2,887.5 | FOOT | $20.90 | $22.75 | $25.91 | |
| 6 | 63000003 | SPBGR TY A 9FT POSTS | 3,350 | FOOT | $25.90 | $26.75 | $35.84 | |
| 7 | 63000007 | SPBGR TY B 6FT POSTS | 75 | FOOT | $27.50 | $35.35 | $35.90 | |
| 8 | 63000030 | SPGR ATT TO CULVERT | 112.5 | FOOT | $165.50 | $202.00 | $156.94 | |
| 9 | 63100045 | TRAF BAR TERM T2 | 4 | EACH | $1,060.00 | $1,110.00 | $1,305.60 | |
| 10 | 63100075 | TRAF BAR TERM T5A | 10 | EACH | $770.00 | $1,010.00 | $1,122.00 | |
| 11 | 63100085 | TRAF BAR TERM T6 | 2 | EACH | $2,647.50 | $2,930.00 | $3,182.40 | |
| 12 | 63100167 | TR BAR TRM T1 SPL TAN | 39 | EACH | $2,573.00 | $2,730.00 | $3,121.20 | |
| 13 | 63200310 | GUARDRAIL REMOV | 8,593.5 | FOOT | $5.90 | $6.00 | $10.47 | |
| 14 | 67100100 | MOBILIZATION | 1 | L SUM | $9,600.00 | $7,000.00 | $19,799.99 | |
| 15 | 70100310 | TRAF CONT-PROT 701421 | 1 | L SUM | $4,500.00 | $3,800.00 | $3,859.00 | |
| 16 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $29,120.00 | $18,000.00 | $97,335.20 | |
| 17 | 70100825 | TRAF CONT-PROT 701456 | 1 | L SUM | $3,000.00 | $2,300.00 | $3,405.00 | |
| 18 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $1,000.00 | $1,350.00 | $3,087.20 | |
| 19 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $800.00 | $1,400.00 | $3,087.20 | |
| 20 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $800.00 | $550.00 | $3,087.20 | |
| 21 | 72501000 | TERMINAL MARKER - DA | 40 | EACH | $30.00 | $40.00 | $27.20 | |
| 22 | 78200005 | GRDRAIL REF TYPE A | 175 | EACH | $8.00 | $8.00 | $3.40 |