D7 PATCHING 2025-1
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Kinney Contractors, Inc. Low bidder | $519,237 | ||
| 2 | G. M. Sipes Construction, Inc. | $527,444 | +1.6% | |
| 3 | Beniach Construction Co., Inc. | $618,945 | +19.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Kinney Contract… | #2 G. M. Sipes Con… | #3 Beniach Constru… |
|---|---|---|---|---|---|---|---|---|
| 1 | XP000012 | ARROWBOARD TRAILR MNT | 320 | HOUR | $7.00 | $0.0100 | $157.00 | |
| 2 | XP000013 | ATTEN CRASH TRUCK MNT | 320 | HOUR | $100.00 | $0.0100 | $163.00 | |
| 3 | X4420573 | CL A PATCH T1 12 SPL | 336 | SQ YD | $294.00 | $425.00 | $434.00 | |
| 4 | X4420575 | CL A PATCH T2 12 SPL | 281 | SQ YD | $286.00 | $375.00 | $275.00 | |
| 5 | X4420577 | CL A PATCH T3 12 SPL | 69 | SQ YD | $282.00 | $375.00 | $270.00 | |
| 6 | X4420579 | CL A PATCH T4 12 SPL | 167 | SQ YD | $279.00 | $375.00 | $270.00 | |
| 7 | 44213000 | PATCH REINFORCEMENT | 852.2 | SQ YD | $70.00 | $75.00 | $121.00 | |
| 8 | 44213200 | SAW CUTS | 5,752 | FOOT | $3.50 | $4.95 | $0.0100 | |
| 9 | 44213204 | TIE BARS 3/4 | 80 | EACH | $17.00 | $15.00 | $15.00 | |
| 10 | 67100100 | MOBILIZATION | 1 | L SUM | $26,000.00 | $25,000.00 | $15,000.00 | |
| 11 | 70100420 | TRAF CONT-PROT 701411 | 1 | EACH | $1,700.00 | $2,750.00 | $664.00 | |
| 12 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $73,000.00 | $25,000.00 | $52,800.00 | |
| 13 | 70100825 | TRAF CONT-PROT 701456 | 1 | L SUM | $8,000.00 | $0.0100 | $2,500.00 | |
| 14 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $150.00 | $25.00 | $121.00 | |
| 15 | 88600100 | DET LOOP T1 | 1,500 | FOOT | $30.50 | $29.15 | $34.00 |