(124Z)RS-4,(5-2)123 RS-3
- Let date
- Friday, March 11, 2022
- Contract
- 74962 · job page
- District
- District 7
- County
- Richland
- Highway
- Limits
- Milling, surfacing, PCC pavement, storm sewer cleaning and replacement of corrugated metal pipe with concrete pipe on IL 130 and IL 250 from south of West North Street to 0.1 miles north of US 50 in Olney.
Bidders 1
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Ambraw Asphalt Materials, Inc. Low bidder | $1,019,578 |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Ambraw Asphalt … |
|---|---|---|---|---|---|---|
| 1 | X0326440 | SURF REM VAR DP (SPL) | 172 | SQ YD | $5.29 | |
| 2 | X4060995 | TEMPORARY RAMP SPL | 623 | SQ YD | $30.00 | |
| 3 | X5537800 | SS CLEANED 12 | 101 | FOOT | $38.00 | |
| 4 | X7011800 | TRAF CONT-PROT BLR 21 | 1 | L SUM | $1,174.00 | |
| 5 | Z0016702 | DETOUR SIGNING | 1 | L SUM | $6,527.32 | |
| 6 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $7,500.00 | |
| 7 | Z0049799 | PROT RESET SURVEY MRK | 2 | EACH | $918.75 | |
| 8 | Z0054408 | ROCK FILL - SUBGRADE | 245 | CU YD | $79.37 | |
| 9 | 20800150 | TRENCH BACKFILL | 20 | CU YD | $57.00 | |
| 10 | 40600290 | BIT MATLS TACK CT | 9,500 | POUND | $0.6600 | |
| 11 | 40600370 | LONG JOINT SEALANT | 6,454 | FOOT | $3.47 | |
| 12 | 40600990 | TEMPORARY RAMP | 91 | SQ YD | $30.00 | |
| 13 | 40603219 | P HMA BC IL-9.5FG N90 | 1,380 | TON | $162.50 | |
| 14 | 40604164 | P HMA SC IL-9.5 D N90 | 1,576 | TON | $162.05 | |
| 15 | 40800050 | INCIDENTAL HMA SURF | 15 | TON | $208.69 | |
| 16 | 42000060 | WELDED WIRE REINF | 396 | SQ YD | $15.00 | |
| 17 | 42000540 | PCC PVT 12 | 370 | SQ YD | $170.81 | |
| 18 | 42300400 | PCC DRIVEWAY PAVT 8 | 26 | SQ YD | $75.00 | |
| 19 | 44000100 | PAVEMENT REM | 370 | SQ YD | $31.00 | |
| 20 | 44000164 | HMA SURF REM 3 3/4 | 14,074 | SQ YD | $5.29 | |
| 21 | 44000200 | DRIVE PAVEMENT REM | 26 | SQ YD | $19.00 | |
| 22 | 44000500 | COMB CURB GUTTER REM | 40 | FOOT | $14.00 | |
| 23 | 44201789 | CL D PATCH T2 12 | 98 | SQ YD | $370.23 | |
| 24 | 44201794 | CL D PATCH T3 12 | 35 | SQ YD | $370.23 | |
| 25 | 50105220 | PIPE CULVERT REMOV | 150 | FOOT | $11.00 | |
| 26 | 54213663 | PRC FLAR END SEC 18 | 1 | EACH | $1,924.00 | |
| 27 | 550A0090 | STORM SEW CL A 1 18 | 150 | FOOT | $70.00 | |
| 28 | 60260500 | INLETS ADJ NEW T3F&G | 4 | EACH | $774.00 | |
| 29 | 60605000 | COMB CC&G TB6.24 | 40 | FOOT | $57.00 | |
| 30 | 66700205 | PERM SURV MKRS T1 | 2 | EACH | $451.10 | |
| 31 | 66900200 | NON SPL WASTE DISPOSL | 265 | CU YD | $130.00 | |
| 32 | 66900530 | SOIL DISPOSAL ANALY | 3 | EACH | $1,918.00 | |
| 33 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $3,498.00 | |
| 34 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $3,498.00 | |
| 35 | 66901006 | REG SUB MON | 3 | CAL DA | $1,388.00 | |
| 36 | 67000400 | ENGR FIELD OFFICE A | 3 | CAL MO | $2,600.00 | |
| 37 | 67100100 | MOBILIZATION | 1 | L SUM | $58,808.50 | |
| 38 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $21,703.00 | |
| 39 | 70102622 | TR CONT & PROT 701502 | 1 | L SUM | $29,677.80 | |
| 40 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $92.39 | |
| 41 | 70300100 | SHORT TERM PAVT MKING | 2,013 | FOOT | $1.50 | |
| 42 | 70300150 | SHRT TRM PAVT MK REM | 222 | SQ FT | $9.86 | |
| 43 | 70300211 | TEMP PVT MK LTR & SYM PAINT | 434 | SQ FT | $3.00 | |
| 44 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 8,882 | FOOT | $0.5700 | |
| 45 | 70300261 | TEMP PVT MK LINE 12 - PAINT | 81 | FOOT | $1.71 | |
| 46 | 78000100 | THPL PVT MK LTR & SYM | 434 | SQ FT | $7.00 | |
| 47 | 78000200 | THPL PVT MK LINE 4 | 8,882 | FOOT | $1.36 | |
| 48 | 78000600 | THPL PVT MK LINE 12 | 81 | FOOT | $3.87 | |
| 49 | 78011000 | GRV RCSD PM LTR & SYM | 434 | SQ FT | $6.00 | |
| 50 | 78011025 | GRV RCSD PVT MRKG 5 | 8,882 | FOOT | $0.6700 | |
| 51 | 78011065 | GRV RCSD PVT MRKG 13 | 81 | FOOT | $3.00 | |
| 52 | 78100100 | RAISED REFL PAVT MKR | 169 | EACH | $47.13 | |
| 53 | 78300200 | RAISED REF PVT MK REM | 169 | EACH | $5.00 |