(75-1B-(3,4))BDR-BRR-BJR-BP
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Freesen, a div of UCM, Inc. Low bidder | $3,754,547 | ||
| 2 | County Contractors, Inc. | $4,584,596 | +22.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Freesen, a div … | #2 County Contract… |
|---|---|---|---|---|---|---|---|
| 1 | X0325748 | ACRYLIC COATING | 7.4 | SQ YD | $403.75 | $625.00 | |
| 2 | X0325749 | FIBER WRAP | 74 | SQ FT | $164.03 | $245.00 | |
| 3 | X1200030 | FILL INLETS TEMP | 4 | EACH | $1,047.67 | $4,175.00 | |
| 4 | X5030250 | BR DECK GROOVING LONG | 4,768 | SQ YD | $9.00 | $7.00 | |
| 5 | X5060601 | C&D N-LEAD PT C RS N1 | 1 | L SUM | $3,096.45 | $3,110.00 | |
| 6 | X5060602 | C&D N-LEAD PT C RS N2 | 1 | L SUM | $3,096.45 | $3,110.00 | |
| 7 | X5060603 | C&D N-LEAD PT C RS N3 | 1 | L SUM | $5,844.30 | $5,870.00 | |
| 8 | X5060604 | C&D N-LEAD PT C RS N4 | 1 | L SUM | $5,844.30 | $5,870.00 | |
| 9 | X6024503 | INLET ADJ NEW F&G SPL | 6 | EACH | $5,378.29 | $5,565.00 | |
| 10 | X7010208 | TC-PROT 701402 SPL | 4 | EACH | $26,498.54 | $26,250.00 | |
| 11 | X7200201 | WIDTH RESTRICT SIGN | 1 | L SUM | $3,045.00 | $5,250.00 | |
| 12 | Z0001800 | APPROACH SL REP (PD) | 200 | SQ YD | $360.75 | $575.00 | |
| 13 | Z0010501 | CLEAN & PT STL BR N1 | 1 | L SUM | $27,862.80 | $27,990.00 | |
| 14 | Z0010502 | CLEAN & PT STL BR N2 | 1 | L SUM | $27,862.80 | $27,990.00 | |
| 15 | Z0010503 | CLEAN & PT STL BR N3 | 1 | L SUM | $41,993.70 | $42,200.00 | |
| 16 | Z0010504 | CLEAN & PT STL BR N4 | 1 | L SUM | $41,993.70 | $42,200.00 | |
| 17 | Z0010615 | CLEAN EX INLETS | 6 | EACH | $441.85 | $530.00 | |
| 18 | Z0012130 | BR DECK SCAR 3/4 | 7,884 | SQ YD | $34.51 | $49.00 | |
| 19 | Z0012166 | BR DK MIC C OVL 2 3/4 | 7,884 | SQ YD | $95.52 | $98.00 | |
| 20 | Z0012754 | STR REP CON DP = < 5 | 201 | SQ FT | $192.43 | $300.00 | |
| 21 | Z0016001 | DECK SLAB REP (FD-T1) | 3 | SQ YD | $1,494.50 | $1,450.00 | |
| 22 | Z0016002 | DECK SLAB REP (FD-T2) | 31 | SQ YD | $854.57 | $1,500.00 | |
| 23 | Z0018051 | DRAINAGE SCUPPERS ADJ | 3 | EACH | $980.67 | $1,100.00 | |
| 24 | Z0029090 | DIAMOND GRIND BR SEC | 7,946 | SQ YD | $11.66 | $14.00 | |
| 25 | Z0041895 | POLYMER CONCRETE | 45 | CU FT | $1,378.39 | $1,200.00 | |
| 26 | Z0043800 | P P CONC I-BM REPAIR | 22 | SQ FT | $638.55 | $1,200.00 | |
| 27 | Z0076600 | TRAINEES | 2,000 | HOUR | $0.8000 | $0.8000 | |
| 28 | Z0076604 | TRAINEES TPG | 2,000 | HOUR | $15.00 | $15.00 | |
| 29 | 20800150 | TRENCH BACKFILL | 2 | CU YD | $361.27 | $225.00 | |
| 30 | 40600290 | BIT MATLS TACK CT | 4,526 | POUND | $3.65 | $3.85 | |
| 31 | 40600982 | HMA SURF REM BUTT JT | 496 | SQ YD | $37.66 | $39.75 | |
| 32 | 40600985 | PCC SURF REM BUTT JT | 744 | SQ YD | $37.66 | $39.75 | |
| 33 | 40600990 | TEMPORARY RAMP | 414 | SQ YD | $22.87 | $15.00 | |
| 34 | 40603219 | P HMA BC IL-9.5FG N90 | 240 | TON | $339.80 | $358.00 | |
| 35 | 40604164 | P HMA SC IL-9.5 D N90 | 555 | TON | $291.88 | $308.00 | |
| 36 | 44004250 | PAVED SHLD REMOVAL | 5,558 | SQ YD | $30.62 | $32.00 | |
| 37 | 48102100 | AGG WEDGE SHLD TYPE B | 64 | TON | $139.19 | $90.00 | |
| 38 | 48203029 | HMA SHOULDERS 8 | 5,547 | SQ YD | $97.73 | $104.00 | |
| 39 | 48203100 | HMA SHOULDERS | 302 | TON | $262.00 | $276.00 | |
| 40 | 50102400 | CONC REM | 52.8 | CU YD | $2,633.44 | $3,130.00 | |
| 41 | 50105220 | PIPE CULVERT REMOV | 32 | FOOT | $27.62 | $24.00 | |
| 42 | 50300255 | CONC SUP-STR | 61.8 | CU YD | $2,704.89 | $3,925.00 | |
| 43 | 50300300 | PROTECTIVE COAT | 7,970 | SQ YD | $3.12 | $5.00 | |
| 44 | 50800205 | REINF BARS, EPOXY CTD | 8,290 | POUND | $3.32 | $2.65 | |
| 45 | 50800515 | BAR SPLICERS | 88 | EACH | $54.97 | $72.00 | |
| 46 | 52000110 | PREF JT STRIP SEAL | 494 | FOOT | $226.56 | $260.00 | |
| 47 | 542D0217 | P CUL CL D 1 12 | 32 | FOOT | $45.94 | $65.00 | |
| 48 | 54262712 | METAL FL END SEC 12" | 2 | EACH | $330.65 | $730.00 | |
| 49 | 60500060 | REMOV INLETS | 2 | EACH | $441.86 | $1,175.00 | |
| 50 | 61000115 | TY E INLET BOX 610001 | 1 | EACH | $4,218.50 | $6,915.00 | |
| 51 | 61000225 | TY F INLET BOX 610001 | 1 | EACH | $4,882.66 | $8,350.00 | |
| 52 | 63000001 | SPBGR TY A 6FT POSTS | 1,700 | FOOT | $35.54 | $35.00 | |
| 53 | 63100089 | TRAF BAR TERM T6B | 8 | EACH | $5,444.25 | $5,470.00 | |
| 54 | 63100167 | TR BAR TRM T1 SPL TAN | 8 | EACH | $3,963.75 | $3,980.00 | |
| 55 | 63200310 | GUARDRAIL REMOV | 2,326 | FOOT | $6.84 | $11.00 | |
| 56 | 64200116 | SHOULDER RUM STRIP 16 | 6,620 | FOOT | $2.83 | $3.75 | |
| 57 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $3,078.89 | $2,450.00 | |
| 58 | 67100100 | MOBILIZATION | 1 | L SUM | $22,342.62 | $286,000.00 | |
| 59 | 70100700 | TRAF CONT-PROT 701406 | 1 | L SUM | $13,061.28 | $28,500.00 | |
| 60 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $3,648.75 | $28,500.00 | |
| 61 | 70107025 | CHANGEABLE MESSAGE SN | 360 | CAL DA | $49.35 | $50.00 | |
| 62 | 70300100 | SHORT TERM PAVT MKING | 600 | FOOT | $1.52 | $4.00 | |
| 63 | 70300150 | SHRT TRM PAVT MK REM | 200 | SQ FT | $4.83 | $6.00 | |
| 64 | 70400100 | TEMP CONC BARRIER | 2,682 | FOOT | $21.69 | $40.00 | |
| 65 | 70400200 | REL TEMP CONC BARRIER | 2,682 | FOOT | $2.45 | $9.00 | |
| 66 | 70600260 | IMP ATTN TEMP FRN TL3 | 4 | EACH | $9,484.66 | $7,950.00 | |
| 67 | 70600332 | IMP ATTN REL FRN TL3 | 4 | EACH | $1,194.12 | $1,864.00 | |
| 68 | 72501000 | TERMINAL MARKER - DA | 8 | EACH | $49.88 | $50.00 | |
| 69 | 78009005 | MOD URETH PM LINE 5 | 6,814 | FOOT | $2.84 | $2.85 | |
| 70 | 78100100 | RAISED REFL PAVT MKR | 16 | EACH | $424.01 | $425.00 | |
| 71 | 78200005 | GRDRAIL REF TYPE A | 24 | EACH | $9.98 | $10.00 | |
| 72 | 78200010 | BARR WALL REF TYPE B | 68 | EACH | $23.31 | $57.00 | |
| 73 | 78300200 | RAISED REF PVT MK REM | 16 | EACH | $18.13 | $30.00 | |
| 74 | 78300202 | PAVMT MRKG REM WTR BL | 10,096 | SQ FT | $1.27 | $1.30 |