(107Z)BDR-1
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Freesen, a div of UCM, Inc. Low bidder | $551,176 | ||
| 2 | White Construction LLC | $723,446 | +31.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Freesen, a div … | #2 White Construct… |
|---|---|---|---|---|---|---|---|
| 1 | X4420557 | CL A PATCH T3 10 SPL | 112 | SQ YD | $436.38 | $575.00 | |
| 2 | X5030250 | BR DECK GROOVING LONG | 274 | SQ YD | $13.68 | $40.00 | |
| 3 | X5060601 | C&D N-LEAD PT C RS N1 | 1 | L SUM | $7,123.60 | $6,476.00 | |
| 4 | X7010228 | TC-PROT 701601 SPL | 1 | L SUM | $22,204.31 | $33,000.00 | |
| 5 | Z0010501 | CLEAN & PT STL BR N1 | 1 | L SUM | $64,121.20 | $68,000.00 | |
| 6 | Z0010615 | CLEAN EX INLETS | 2 | EACH | $836.41 | $2,000.00 | |
| 7 | Z0012130 | BR DECK SCAR 3/4 | 432 | SQ YD | $120.25 | $150.00 | |
| 8 | Z0012166 | BR DK MIC C OVL 2 3/4 | 432 | SQ YD | $151.76 | $150.00 | |
| 9 | Z0016002 | DECK SLAB REP (FD-T2) | 5 | SQ YD | $814.46 | $1,250.00 | |
| 10 | Z0029090 | DIAMOND GRIND BR SEC | 388 | SQ YD | $24.13 | $65.00 | |
| 11 | Z0073346 | SLEEPER SLAB | 64 | SQ YD | $364.46 | $500.00 | |
| 12 | 40600290 | BIT MATLS TACK CT | 395 | POUND | $4.48 | $9.50 | |
| 13 | 40600370 | LONG JOINT SEALANT | 395 | FOOT | $24.67 | $23.50 | |
| 14 | 40600985 | PCC SURF REM BUTT JT | 312 | SQ YD | $38.59 | $25.00 | |
| 15 | 40600990 | TEMPORARY RAMP | 107 | SQ YD | $13.53 | $40.00 | |
| 16 | 40604162 | P HMA SC IL-9.5 D N70 | 74 | TON | $385.02 | $345.00 | |
| 17 | 50102400 | CONC REM | 4.3 | CU YD | $3,679.47 | $8,500.00 | |
| 18 | 50157300 | PROTECTIVE SHIELD | 405 | SQ YD | $75.93 | $90.00 | |
| 19 | 50300255 | CONC SUP-STR | 5.2 | CU YD | $2,614.01 | $8,500.00 | |
| 20 | 50300300 | PROTECTIVE COAT | 452 | SQ YD | $3.32 | $5.00 | |
| 21 | 50800205 | REINF BARS, EPOXY CTD | 790 | POUND | $12.20 | $7.50 | |
| 22 | 50800515 | BAR SPLICERS | 8 | EACH | $76.84 | $125.00 | |
| 23 | 52000110 | PREF JT STRIP SEAL | 87 | FOOT | $279.10 | $300.00 | |
| 24 | 60260100 | INLETS ADJUST | 2 | EACH | $1,572.04 | $1,500.00 | |
| 25 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $2,901.05 | $2,500.00 | |
| 26 | 67100100 | MOBILIZATION | 1 | L SUM | $11,421.21 | $40,000.00 | |
| 27 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $9,110.26 | $20,000.00 | |
| 28 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $275.00 | $450.00 | |
| 29 | 70107025 | CHANGEABLE MESSAGE SN | 308 | CAL DA | $47.58 | $43.25 | |
| 30 | 70400100 | TEMP CONC BARRIER | 467 | FOOT | $39.62 | $40.00 | |
| 31 | 70400200 | REL TEMP CONC BARRIER | 467 | FOOT | $2.40 | $7.00 | |
| 32 | 70600255 | IMP ATTN TEMP FRN TL2 | 1 | EACH | $6,062.87 | $8,000.00 | |
| 33 | 70600322 | IMP ATTN REL FRN TL2 | 1 | EACH | $2,236.33 | $4,000.00 | |
| 34 | 78009005 | MOD URETH PM LINE 5 | 82 | FOOT | $187.00 | $170.00 | |
| 35 | 78300200 | RAISED REF PVT MK REM | 6 | EACH | $33.33 | $125.00 |