Bid tab 72E88

Let Sep 18, 2026 · District 6 · Schuyler

‹ Sep 2026 results

10DR

Let date
Friday, September 18, 2026
Contract
72E88 · job page
District
District 6
County
Schuyler
Highway
Limits
Pipe culvert removal and replacement on IL 99, 0.8 miles south of CH 5 (Camden Road / La Prairie Road), south of Camden.
Classification
·
Project number

Bidders 6

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 Rees Construction Company of Quincy Low bidder $81,487
2 Otto Baum Company, Inc. $83,200 +2.1%
3 Hood Construction Group Midwest $85,145 +4.5%
4 Phoenix Corporation of the Quad Cities $91,186 +11.9%
5 County Contractors, Inc. $95,285 +16.9%
6 Laverdiere Construction, Inc. $113,102 +38.8%

Bid tab: unit prices 10 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 Rees Constructi…#2 Otto Baum Compa…#3 Hood Constructi…#4 Phoenix Corpora…#5 County Contract…#6 Laverdiere Cons…
1X7011800 TRAF CONT-PROT BLR 211L SUM $1,800.00 $1,630.82 $2,800.00 $1,500.00 $1,600.00 $5,000.00
2X7200203 DETOUR SIGNING1L SUM $15,387.00 $13,959.84 $13,000.00 $12,840.00 $13,750.00 $19,260.00
320800150 TRENCH BACKFILL97CU YD $42.00 $102.65 $65.00 $60.00 $115.00 $148.00
444200150 PAVT PATCH T4 1259SQ YD $233.00 $316.57 $160.00 $330.00 $300.00 $252.00
548101200 AGGREGATE SHLDS B6TON $129.00 $153.72 $75.00 $150.00 $100.00 $120.00
650105220 PIPE CULVERT REMOV78FOOT $116.00 $21.11 $75.00 $72.00 $30.00 $21.75
7542A1909 P CUL CL A 3 2478FOOT $255.00 $126.55 $350.00 $255.00 $425.00 $355.00
854213669 PRC FLAR END SEC 242EACH $2,372.00 $1,753.42 $4,800.00 $3,000.00 $2,750.00 $6,886.50
967100100 MOBILIZATION1L SUM $7,425.00 $18,855.24 $6,600.00 $17,250.00 $5,500.00 $10,000.00
1070107025 CHANGEABLE MESSAGE SN38CAL DA $121.00 $109.81 $100.00 $50.00 $105.00 $151.00