K(B-1)BJR,BDR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Otto Baum Company, Inc. Low bidder | $1,947,800 | ||
| 2 | Freesen, a div of UCM, Inc. | $1,981,958 | +1.8% | |
| 3 | Sangamo Construction Company | $2,016,220 | +3.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Otto Baum Compa… | #2 Freesen, a div … | #3 Sangamo Constru… |
|---|---|---|---|---|---|---|---|---|
| 1 | X5030250 | BR DECK GROOVING LONG | 3,580 | SQ YD | $18.38 | $14.86 | $10.58 | |
| 2 | X5230172 | DRAINAGE SCUPPERS ADJ | 30 | EACH | $540.69 | $799.66 | $1,505.72 | |
| 3 | X7200201 | WIDTH RESTRICT SIGN | 1 | L SUM | $2,392.81 | $2,362.50 | $4,756.85 | |
| 4 | Z0001800 | APPR SLAB REPAIR (PD) | 10 | SQ YD | $976.52 | $1,253.71 | $1,059.19 | |
| 5 | Z0012130 | BR DECK SCAR 3/4 | 4,694 | SQ YD | $76.27 | $47.25 | $44.82 | |
| 6 | Z0012166 | BR DK MIC C OVL 2 3/4 | 4,694 | SQ YD | $88.68 | $128.94 | $108.46 | |
| 7 | Z0012754 | STR REP CON DP = < 5 | 70 | SQ FT | $388.85 | $255.99 | $290.82 | |
| 8 | Z0016001 | DECK SLAB REP (FD-T1) | 10 | SQ YD | $1,681.92 | $1,723.18 | $1,780.35 | |
| 9 | Z0029090 | DIAMOND GRIND BR SEC | 4,800 | SQ YD | $12.37 | $12.58 | $10.96 | |
| 10 | Z0034393 | MODULAR EXPAN JT 9 | 42 | FOOT | $3,609.80 | $4,609.85 | $4,480.99 | |
| 11 | Z0073200 | TEMP SHORING & CRIB | 2 | EACH | $15,524.64 | $10,018.52 | $14,581.02 | |
| 12 | Z0076604 | TRAINEES TPG | 1,500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 13 | 35650300 | BASE CSE WIDENING 8 | 303 | SQ YD | $144.68 | $140.37 | $110.66 | |
| 14 | 40600290 | BIT MATLS TACK CT | 960 | POUND | $1.33 | $2.33 | $1.32 | |
| 15 | 40600982 | HMA SURF REM BUTT JT | 356 | SQ YD | $34.62 | $37.16 | $34.45 | |
| 16 | 40600990 | TEMPORARY RAMP | 86 | SQ YD | $15.95 | $12.90 | $72.97 | |
| 17 | 40602978 | HMA BC IL-9.5 N50 | 25 | TON | $223.49 | $333.59 | $222.39 | |
| 18 | 40604050 | HMA SC IL-9.5 C N50 | 140 | TON | $22.49 | $316.58 | $222.39 | |
| 19 | 44004250 | PAVED SHLD REMOVAL | 303 | SQ YD | $63.68 | $58.65 | $53.70 | |
| 20 | 48102100 | AGG WEDGE SHLD TYPE B | 40 | TON | $138.64 | $103.50 | $119.21 | |
| 21 | 50102400 | CONC REM | 29.1 | CU YD | $2,525.71 | $2,997.35 | $3,086.67 | |
| 22 | 50300255 | CONC SUP-STR | 36.4 | CU YD | $4,219.18 | $3,543.04 | $4,007.03 | |
| 23 | 50300300 | PROTECTIVE COAT | 4,772 | SQ YD | $4.72 | $3.47 | $3.43 | |
| 24 | 50500505 | STUD SHEAR CONNECTORS | 8 | EACH | $63.81 | $63.00 | $63.50 | |
| 25 | 50800205 | REINF BARS, EPOXY CTD | 5,580 | POUND | $3.26 | $2.55 | $2.61 | |
| 26 | 50800515 | BAR SPLICERS | 72 | EACH | $44.49 | $70.25 | $60.71 | |
| 27 | 50800530 | MECHANICAL SPLICERS | 143 | EACH | $66.76 | $71.59 | $74.91 | |
| 28 | 52000110 | PREF JT STRIP SEAL | 126 | FOOT | $369.02 | $332.77 | $362.36 | |
| 29 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $1,379.14 | $4,196.54 | $2,791.67 | |
| 30 | 67100100 | MOBILIZATION | 1 | L SUM | $124,713.92 | $58,005.02 | $118,957.00 | |
| 31 | 70100405 | TRAF CONT-PROT 701321 | 1 | EACH | $23,874.97 | $31,158.81 | $53,602.89 | |
| 32 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $850.78 | $3,528.72 | $9,789.83 | |
| 33 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $1,648.39 | $2,835.00 | $4,745.15 | |
| 34 | 70106500 | TEMP BR TRAF SIGNALS | 1 | EACH | $24,041.47 | $23,625.00 | $33,334.55 | |
| 35 | 70106700 | TEMP RUMBLE STRIPS | 6 | EACH | $1,515.45 | $525.00 | $1,406.05 | |
| 36 | 70107025 | CHANGEABLE MESSAGE SN | 300 | CAL DA | $106.35 | $46.46 | $72.11 | |
| 37 | 70400100 | TEMP CONC BARRIER | 1,700 | FOOT | $40.94 | $38.06 | $52.89 | |
| 38 | 70400200 | REL TEMP CONC BARRIER | 1,700 | FOOT | $6.38 | $3.81 | $9.54 | |
| 39 | 70600250 | IMP ATTN TEMP NRD TL3 | 2 | EACH | $5,175.83 | $4,042.50 | $5,592.08 | |
| 40 | 70600352 | IMP ATTN REL NRN TL3 | 2 | EACH | $1,080.89 | $1,360.25 | $1,562.98 | |
| 41 | 78009005 | MOD URETH PM LINE 5 | 9,000 | FOOT | $1.89 | $1.87 | $1.88 | |
| 42 | 78300201 | PVT MKG REM GRINDING | 1,400 | SQ FT | $5.85 | $5.25 | $5.29 |