D5 BRIDGE PAINTING 2019-2
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | ERA-Valdivia Contractors, Inc. Low bidder | $545,673 | ||
| 2 | Eagle Painting & Maintenance Company, Inc. | $558,190 | +2.3% | |
| 3 | Three Star Painting, Inc. | $740,000 | +35.6% | |
| 4 | Venus Painting Co. | $1,189,450 | +118.0% | |
| 5 | Civil Coatings and Construction Inc. | $1,514,010 | +177.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 ERA-Valdivia Co… | #2 Eagle Painting … | #3 Three Star Pain… | #4 Venus Painting … | #5 Civil Coatings … |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X2700001 | TEMP RUMBLE STRIPS SP | 48 | EACH | $100.00 | $80.00 | $1.00 | $200.00 | $720.00 | |
| 2 | X5067501 | BR CLN & PT WAR #1 | 1 | L SUM | $4,500.00 | $500.00 | $500.00 | $300.00 | $500.00 | |
| 3 | X5067502 | BR CLN & PT WAR #2 | 1 | L SUM | $4,500.00 | $500.00 | $500.00 | $300.00 | $500.00 | |
| 4 | X5067503 | BR CLN & PT WAR #3 | 1 | L SUM | $4,500.00 | $500.00 | $500.00 | $300.00 | $500.00 | |
| 5 | X5067504 | BR CLN & PT WAR #4 | 1 | L SUM | $4,500.00 | $500.00 | $500.00 | $300.00 | $500.00 | |
| 6 | X5067505 | BR CLN & PT WAR #5 | 1 | L SUM | $4,500.00 | $500.00 | $500.00 | $300.00 | $500.00 | |
| 7 | X7015005 | CHANGEABLE MESSAGE SN | 107 | CAL DA | $25.00 | $60.00 | $1.00 | $30.00 | $100.00 | |
| 8 | X7200201 | WIDTH RESTRICT SIGN | 1 | L SUM | $198.00 | $180.00 | $250.00 | $140.00 | $4,200.00 | |
| 9 | Z0007101 | C&D LEAD PT CL RS N1 | 1 | L SUM | $21,125.00 | $12,500.00 | $500.00 | $8,000.00 | $1,000.00 | |
| 10 | Z0007102 | C&D LEAD PT CL RS N2 | 1 | L SUM | $21,125.00 | $12,500.00 | $500.00 | $8,000.00 | $1,000.00 | |
| 11 | Z0007103 | C&D LEAD PT CL RS N3 | 1 | L SUM | $39,000.00 | $22,000.00 | $500.00 | $8,000.00 | $1,000.00 | |
| 12 | Z0007104 | C&D LEAD PT CL RS N4 | 1 | L SUM | $30,875.00 | $19,000.00 | $500.00 | $8,000.00 | $1,000.00 | |
| 13 | Z0007105 | C&D LEAD PT CL RS N5 | 1 | L SUM | $31,525.00 | $20,000.00 | $500.00 | $8,000.00 | $1,000.00 | |
| 14 | Z0010501 | CLEAN & PT STL BR N1 | 1 | L SUM | $58,500.00 | $51,000.00 | $90,474.20 | $205,000.00 | $175,000.00 | |
| 15 | Z0010502 | CLEAN & PT STL BR N2 | 1 | L SUM | $58,500.00 | $51,000.00 | $90,474.20 | $205,000.00 | $175,000.00 | |
| 16 | Z0010503 | CLEAN & PT STL BR N3 | 1 | L SUM | $72,000.00 | $87,000.00 | $183,008.20 | $205,000.00 | $300,000.00 | |
| 17 | Z0010504 | CLEAN & PT STL BR N4 | 1 | L SUM | $57,000.00 | $76,000.00 | $152,444.20 | $205,000.00 | $250,000.00 | |
| 18 | Z0010505 | CLEAN & PT STL BR N5 | 1 | L SUM | $58,200.00 | $82,000.00 | $152,444.20 | $205,000.00 | $277,750.00 | |
| 19 | 67100100 | MOBILIZATION | 1 | L SUM | $30,000.00 | $35,000.00 | $37,000.00 | $80,000.00 | $75,000.00 | |
| 20 | 70100207 | TRAF CONT-PROT 701402 | 5 | EACH | $1,500.00 | $6,750.00 | $1,000.00 | $200.00 | $23,500.00 | |
| 21 | 70100325 | TRAF CONT-PROT 701423 | 1 | EACH | $1,500.00 | $3,600.00 | $1,000.00 | $8,000.00 | $14,000.00 | |
| 22 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $1,500.00 | $3,000.00 | $1,000.00 | $3,000.00 | $5,000.00 | |
| 23 | 70400100 | TEMP CONC BARRIER | 1,650 | FOOT | $10.00 | $8.00 | $10.00 | $6.00 | $10.00 | |
| 24 | 70400200 | REL TEMP CONC BARRIER | 1,650 | FOOT | $5.00 | $10.00 | $1.00 | $2.00 | $5.00 | |
| 25 | 70600250 | IMP ATTN TEMP NRD TL3 | 6 | EACH | $250.00 | $500.00 | $300.00 | $600.00 | $3,975.00 | |
| 26 | 70600350 | IMP ATTN REL NRD TL3 | 6 | EACH | $150.00 | $700.00 | $300.00 | $200.00 | $3,200.00 |