(TR 39 & TR 26)RS&W
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D. Construction, Inc. Low bidder | $375,288 | ||
| 2 | P. T. Ferro Construction Co. | $499,992 | +33.2% | |
| 3 | Scanlon Excavating & Concrete, Inc. | $553,550 | +47.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D. Construction… | #2 P. T. Ferro Con… | #3 Scanlon Excavat… |
|---|---|---|---|---|---|---|---|---|
| 1 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $12,400.00 | $2,625.00 | $20,000.00 | |
| 2 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $10,000.00 | $20,000.00 | $20,000.00 | |
| 3 | Z0030850 | TEMP INFO SIGNING | 84 | SQ FT | $25.00 | $25.00 | $22.00 | |
| 4 | 20200100 | EARTH EXCAVATION | 1,513 | CU YD | $30.00 | $45.00 | $65.00 | |
| 5 | 20400800 | FURNISHED EXCAVATION | 358 | CU YD | $30.00 | $65.00 | $75.00 | |
| 6 | 20800150 | TRENCH BACKFILL | 54 | CU YD | $70.00 | $88.00 | $50.00 | |
| 7 | 25000210 | SEEDING CL 2A | 2.5 | ACRE | $2,035.00 | $4,705.00 | $3,500.00 | |
| 8 | 25000400 | NITROGEN FERT NUTR | 214 | POUND | $2.20 | $3.00 | $4.00 | |
| 9 | 25000500 | PHOSPHORUS FERT NUTR | 214 | POUND | $2.20 | $3.00 | $4.00 | |
| 10 | 25000600 | POTASSIUM FERT NUTR | 214 | POUND | $2.20 | $3.00 | $4.00 | |
| 11 | 25100630 | EROSION CONTR BLANKET | 11,504 | SQ YD | $1.38 | $1.10 | $3.00 | |
| 12 | 28000250 | TEMP EROS CONTR SEED | 714 | POUND | $3.58 | $6.00 | $3.00 | |
| 13 | 28000305 | TEMP DITCH CHECKS | 348 | FOOT | $11.00 | $5.60 | $12.00 | |
| 14 | 28000500 | INLET & PIPE PROTECT | 13 | EACH | $220.00 | $100.00 | $150.00 | |
| 15 | 31100700 | SUB GRAN MAT A 8 | 3,983 | SQ YD | $11.00 | $23.00 | $18.00 | |
| 16 | 35501290 | HMA BASE CSE 3 | 2,655 | SQ YD | $18.00 | $24.00 | $30.00 | |
| 17 | 40200800 | AGG SURF CSE B | 299 | TON | $30.00 | $45.00 | $50.00 | |
| 18 | 40600290 | BIT MATLS TACK CT | 2,426 | POUND | $0.0100 | $0.0100 | $1.00 | |
| 19 | 40602978 | HMA BC IL-9.5 N50 | 82 | TON | $200.00 | $275.00 | $175.00 | |
| 20 | 44000100 | PAVEMENT REM | 233 | SQ YD | $20.00 | $15.00 | $41.82 | |
| 21 | 44201717 | CL D PATCH T2 6 | 49 | SQ YD | $90.00 | $120.00 | $225.00 | |
| 22 | 50105220 | PIPE CULVERT REMOV | 502 | FOOT | $20.00 | $28.00 | $25.00 | |
| 23 | 50800105 | REINFORCEMENT BARS | 180 | POUND | $5.00 | $3.50 | $10.00 | |
| 24 | 542A5473 | P CUL CL A 1 EQRS 18 | 78 | FOOT | $173.00 | $160.00 | $150.00 | |
| 25 | 542A5479 | P CUL CL A 1 EQRS 24 | 68 | FOOT | $185.00 | $190.00 | $175.00 | |
| 26 | 542D0223 | P CUL CL D 1 18 | 45 | FOOT | $139.00 | $130.00 | $100.00 | |
| 27 | 542D5470 | P CUL CL D 1 EQRS 15 | 28 | FOOT | $129.00 | $120.00 | $115.00 | |
| 28 | 542D5473 | P CUL CL D 1 EQRS 18 | 166 | FOOT | $135.00 | $120.00 | $100.00 | |
| 29 | 542D5479 | P CUL CL D 1 EQRS 24 | 64 | FOOT | $150.00 | $150.00 | $150.00 | |
| 30 | 54214713 | PRCF END S EL EQRS 18 | 6 | EACH | $1,500.00 | $1,405.00 | $1,400.00 | |
| 31 | 54214719 | PRCF END S EL EQRS 24 | 4 | EACH | $2,000.00 | $1,800.00 | $1,600.00 | |
| 32 | 54248510 | CONCRETE COLLAR | 2.4 | CU YD | $2,000.00 | $2,300.00 | $1,000.00 | |
| 33 | 54262718 | METAL FL END SEC 18" | 2 | EACH | $700.00 | $980.00 | $650.00 | |
| 34 | 54262815 | METAL FL ES EQ RS 15" | 2 | EACH | $600.00 | $900.00 | $650.00 | |
| 35 | 54262818 | METAL FL ES EQ RS 18" | 6 | EACH | $700.00 | $950.00 | $700.00 | |
| 36 | 54262824 | METAL FL ES EQ RS 24" | 4 | EACH | $800.00 | $1,100.00 | $1,000.00 | |
| 37 | 67100100 | MOBILIZATION | 1 | L SUM | $22,500.00 | $28,000.00 | $25,000.00 | |
| 38 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $0.0100 | $100.00 | $500.00 | |
| 39 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $0.0100 | $2,625.00 | $500.00 |