(24BR2)BR
- Let date
- Friday, March 8, 2024
- Contract
- 66M28 · job page
- District
- District 3
- County
- Livingston
- Highway
- Limits
- This job is located on FAP 317 (US-24), approximately 2.8 mile west of IL 115 north at Piper city in Livingston county, (SN 053-0097). Bridge replacement.
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Iroquois Paving Corporation Low bidder | $902,137 | ||
| 2 | Tobey's Construction & Cartage, Inc. | $949,084 | +5.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Iroquois Paving… | #2 Tobey's Constru… |
|---|---|---|---|---|---|---|---|
| 1 | X5810103 | MEMB WTRPRF SYS B STR | 175 | SQ YD | $68.50 | $44.00 | |
| 2 | X6350204 | LINEAR DELIN PANELS 4 | 8 | EACH | $130.00 | $125.00 | |
| 3 | Z0030850 | TEMP INFO SIGNING | 63 | SQ FT | $36.00 | $35.00 | |
| 4 | 20101400 | NITROGEN FERT NUTR | 70 | POUND | $4.15 | $4.00 | |
| 5 | 20101500 | PHOSPHORUS FERT NUTR | 70 | POUND | $4.15 | $4.00 | |
| 6 | 20101600 | POTASSIUM FERT NUTR | 70 | POUND | $4.15 | $4.00 | |
| 7 | 20200100 | EARTH EXCAVATION | 270 | CU YD | $48.50 | $45.00 | |
| 8 | 20400800 | FURNISHED EXCAVATION | 140 | CU YD | $11.75 | $21.00 | |
| 9 | 20700220 | POROUS GRAN EMBANK | 585 | CU YD | $74.50 | $68.00 | |
| 10 | 25000200 | SEEDING CL 2 | 0.75 | ACRE | $2,600.00 | $2,500.00 | |
| 11 | 25100630 | EROSION CONTR BLANKET | 2,800 | SQ YD | $1.70 | $1.62 | |
| 12 | 25100635 | HD EROS CONTR BLANKET | 450 | SQ YD | $4.15 | $4.00 | |
| 13 | 28000250 | TEMP EROS CONTR SEED | 68 | POUND | $7.25 | $2.00 | |
| 14 | 28000305 | TEMP DITCH CHECKS | 96 | FOOT | $13.00 | $12.50 | |
| 15 | 28000400 | PERIMETER EROS BAR | 1,128 | FOOT | $2.10 | $2.00 | |
| 16 | 28000500 | INLET & PIPE PROTECT | 2 | EACH | $130.00 | $125.00 | |
| 17 | 28001100 | TEMP EROS CONTR BLANK | 2,800 | SQ YD | $1.70 | $1.62 | |
| 18 | 28001200 | TEMP HD EROS CONTR BL | 450 | SQ YD | $4.15 | $4.00 | |
| 19 | 28100107 | STONE RIPRAP CL A4 | 146 | SQ YD | $105.00 | $90.00 | |
| 20 | 28200200 | FILTER FABRIC | 146 | SQ YD | $4.05 | $2.00 | |
| 21 | 31100910 | SUB GRAN MAT A 12 | 228 | SQ YD | $39.45 | $38.25 | |
| 22 | 35501316 | HMA BASE CSE 8 | 213 | SQ YD | $89.50 | $102.00 | |
| 23 | 40600275 | BIT MATLS PR CT | 480 | POUND | $0.0100 | $0.0100 | |
| 24 | 40600290 | BIT MATLS TACK CT | 702 | POUND | $0.0100 | $0.0100 | |
| 25 | 40600370 | LONG JOINT SEALANT | 1,500 | FOOT | $6.90 | $6.65 | |
| 26 | 40603085 | HMA BC IL-19.0 N70 | 27 | TON | $220.00 | $220.00 | |
| 27 | 40604002 | HMA SC IL-9.5FG C N70 | 140 | TON | $164.00 | $225.00 | |
| 28 | 44000100 | PAVEMENT REM | 202 | SQ YD | $27.50 | $43.00 | |
| 29 | 44000155 | HMA SURF REM 1 1/2 | 1,780 | SQ YD | $2.85 | $7.25 | |
| 30 | 44004250 | PAVED SHLD REMOVAL | 124 | SQ YD | $17.25 | $43.00 | |
| 31 | 48102100 | AGG WEDGE SHLD TYPE B | 101 | TON | $46.50 | $67.00 | |
| 32 | 48203029 | HMA SHOULDERS 8 | 480 | SQ YD | $66.00 | $105.00 | |
| 33 | 50100100 | REM EXIST STRUCT | 1 | EACH | $58,500.00 | $52,000.00 | |
| 34 | 50105220 | PIPE CULVERT REMOV | 45 | FOOT | $23.00 | $16.00 | |
| 35 | 50200100 | STRUCTURE EXCAVATION | 435 | CU YD | $32.00 | $38.00 | |
| 36 | 50800205 | REINF BARS, EPOXY CTD | 7,810 | POUND | $3.60 | $3.70 | |
| 37 | 51500100 | NAME PLATES | 1 | EACH | $785.00 | $450.00 | |
| 38 | 52200020 | TEMP SOIL RETEN SYSTM | 477 | SQ FT | $0.0100 | $63.00 | |
| 39 | 54003000 | CONC BOX CUL | 79.4 | CU YD | $1,280.00 | $1,470.00 | |
| 40 | 54011111 | PCBC 11X11 | 110 | FOOT | $1,995.00 | $1,825.00 | |
| 41 | 542A0229 | P CUL CL A 1 24 | 46 | FOOT | $134.00 | $89.00 | |
| 42 | 54261624 | CONC ES 542001 24 1:6 | 2 | EACH | $8,100.00 | $9,000.00 | |
| 43 | 59100100 | GEOCOMPOSITE WALL DR | 175 | SQ YD | $30.50 | $39.00 | |
| 44 | 63000001 | SPBGR TY A 6FT POSTS | 450 | FOOT | $61.00 | $48.50 | |
| 45 | 63000030 | SPGR ATT TO CULVERT | 50 | FOOT | $285.00 | $275.00 | |
| 46 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $3,995.00 | $3,850.00 | |
| 47 | 63200310 | GUARDRAIL REMOV | 706 | FOOT | $7.00 | $5.00 | |
| 48 | 67000400 | ENGR FIELD OFFICE A | 8 | CAL MO | $2,600.00 | $2,600.00 | |
| 49 | 67100100 | MOBILIZATION | 1 | L SUM | $53,500.00 | $57,000.00 | |
| 50 | 70100405 | TRAF CONT-PROT 701321 | 1 | EACH | $8,475.00 | $7,450.00 | |
| 51 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $105.00 | $100.00 | |
| 52 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $105.00 | $100.00 | |
| 53 | 70106500 | TEMP BR TRAF SIGNALS | 1 | EACH | $21,000.00 | $20,150.00 | |
| 54 | 70300100 | SHORT TERM PAVT MKING | 144 | FOOT | $0.0100 | $1.50 | |
| 55 | 70300150 | SHRT TRM PAVT MK REM | 48 | SQ FT | $0.0100 | $30.00 | |
| 56 | 70307120 | TEMP PVT MK L4 T4 TAPE | 2,761 | FOOT | $1.25 | $1.20 | |
| 57 | 70307130 | TEMP PVT MK L6 T4 TAPE | 500 | FOOT | $1.60 | $1.55 | |
| 58 | 70307210 | TEMP PVT MK L24 T4 TAPE | 41 | FOOT | $7.50 | $7.20 | |
| 59 | 70400100 | TEMP CONC BARRIER | 337.5 | FOOT | $61.25 | $43.00 | |
| 60 | 70400125 | PIN TEMP CONC BARRIER | 48 | EACH | $28.00 | $27.00 | |
| 61 | 70400200 | REL TEMP CONC BARRIER | 337.5 | FOOT | $8.50 | $13.00 | |
| 62 | 70600250 | IMP ATTN TEMP NRD TL3 | 2 | EACH | $3,950.00 | $3,800.00 | |
| 63 | 70600350 | IMP ATTN REL NRD TL3 | 2 | EACH | $1,350.00 | $1,300.00 | |
| 64 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $52.00 | $50.00 | |
| 65 | 78009004 | MOD URETH PM LINE 4 | 2,000 | FOOT | $3.30 | $3.20 | |
| 66 | 78009006 | MOD URETH PM LINE 6 | 260 | FOOT | $5.00 | $4.90 | |
| 67 | 78100100 | RAISED REFL PAVT MKR | 13 | EACH | $217.00 | $210.00 | |
| 68 | 78200005 | GRDRAIL REF TYPE A | 16 | EACH | $15.50 | $15.00 | |
| 69 | 78200011 | BARR WALL REF TYPE C | 54 | EACH | $19.00 | $10.00 | |
| 70 | 78300200 | RAISED REF PVT MK REM | 13 | EACH | $0.0100 | $10.00 | |
| 71 | 78300201 | PVT MKG REM GRINDING | 1,865 | SQ FT | $3.05 | $3.00 |