(53-6B)BJR,BRR
- Let date
- Friday, April 29, 2022
- Contract
- 66L75 · job page
- District
- District 3
- County
- Livingston
- Highway
- Limits
- Latex overlay, expansion joint replacement and deck repairs on the structures structures SN 053-0124 and SN 053-0125 carrying I-55 over Rooks creek, 3 miles southwest of Pontiac in Livingston County.
Bidders 1
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Tobey's Construction & Cartage, Inc. Low bidder | $1,906,501 |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Tobey's Constru… |
|---|---|---|---|---|---|---|
| 1 | X0323491 | SLOPE WALL CRACK SEAL | 397 | FOOT | $60.00 | |
| 2 | X0326394 | FLOOR DRAINS CLEANED | 124 | EACH | $70.00 | |
| 3 | X2700001 | TEMP RUMBLE STRIPS SP | 2 | EACH | $1,700.00 | |
| 4 | X4420569 | CL A PATCH T3 11 SPL | 128 | SQ YD | $268.00 | |
| 5 | X5030250 | BR DECK GROOVING LONG | 1,498 | SQ YD | $9.00 | |
| 6 | Z0006018 | BR DK LTX C OLY 3 | 2,342 | SQ YD | $158.00 | |
| 7 | Z0007101 | C&D LEAD PT CL RS N1 | 1 | L SUM | $6,383.00 | |
| 8 | Z0007102 | C&D LEAD PT CL RS N2 | 1 | L SUM | $6,383.00 | |
| 9 | Z0010501 | CLEAN & PT STL BR N1 | 1 | L SUM | $36,534.00 | |
| 10 | Z0010502 | CLEAN & PT STL BR N2 | 1 | L SUM | $36,534.00 | |
| 11 | Z0012146 | BR DECK SCAR 2 3/4 | 2,342 | SQ YD | $53.00 | |
| 12 | Z0012754 | STR REP CON DP = < 5 | 203 | SQ FT | $338.00 | |
| 13 | Z0016001 | DECK SLAB REP (FD-T1) | 15 | SQ YD | $1,325.00 | |
| 14 | Z0016002 | DECK SLAB REP (FD-T2) | 54 | SQ YD | $1,325.00 | |
| 15 | Z0029090 | DIAMOND GRIND BR SEC | 2,150 | SQ YD | $12.50 | |
| 16 | Z0065700 | SLOPE WALL REPAIR | 84 | SQ YD | $325.00 | |
| 17 | Z0065730 | SLOPEWALL SLUR PUMPNG | 55 | CU YD | $330.00 | |
| 18 | 40600290 | BIT MATLS TACK CT | 1,784 | POUND | $0.0100 | |
| 19 | 40600370 | LONG JOINT SEALANT | 376 | FOOT | $20.50 | |
| 20 | 40600400 | MIX CR JTS FLANGEWYS | 1.2 | TON | $1,038.00 | |
| 21 | 40603085 | HMA BC IL-19.0 N70 | 214 | TON | $178.00 | |
| 22 | 40604052 | HMA SC IL-9.5 C N70 | 228 | TON | $173.00 | |
| 23 | 40604064 | HMA SC IL-9.5 D N90 | 88 | TON | $513.00 | |
| 24 | 44000155 | HMA SURF REM 1 1/2 | 1,004 | SQ YD | $32.00 | |
| 25 | 44000157 | HMA SURF REM 2 | 1,068 | SQ YD | $16.00 | |
| 26 | 44000173 | HMA SURF REM 6 | 944 | SQ YD | $30.00 | |
| 27 | 44213000 | PATCH REINFORCEMENT | 128 | SQ YD | $90.00 | |
| 28 | 44213200 | SAW CUTS | 336 | FOOT | $6.00 | |
| 29 | 44213204 | TIE BARS 3/4 | 368 | EACH | $21.75 | |
| 30 | 50102400 | CONC REM | 28.8 | CU YD | $3,625.00 | |
| 31 | 50300255 | CONC SUP-STR | 28.8 | CU YD | $3,375.00 | |
| 32 | 50300300 | PROTECTIVE COAT | 2,416 | SQ YD | $2.75 | |
| 33 | 50800205 | REINF BARS, EPOXY CTD | 3,840 | POUND | $3.70 | |
| 34 | 50800515 | BAR SPLICERS | 48 | EACH | $56.00 | |
| 35 | 52000110 | PREF JT STRIP SEAL | 192 | FOOT | $181.50 | |
| 36 | 54390230 | INSERT CUL LIN 36 | 451 | FOOT | $260.00 | |
| 37 | 59000200 | EPOXY CRACK INJECTION | 286 | FOOT | $60.00 | |
| 38 | 64200116 | SHOULDER RUM STRIP 16 | 2,120 | FOOT | $4.05 | |
| 39 | 67000400 | ENGR FIELD OFFICE A | 5 | CAL MO | $3,400.00 | |
| 40 | 67100100 | MOBILIZATION | 1 | L SUM | $113,000.00 | |
| 41 | 70100205 | TRAF CONT-PROT 701401 | 2 | EACH | $500.00 | |
| 42 | 70100207 | TRAF CONT-PROT 701402 | 2 | EACH | $49,575.00 | |
| 43 | 70100420 | TRAF CONT-PROT 701411 | 4 | EACH | $500.00 | |
| 44 | 70100700 | TRAF CONT-PROT 701406 | 1 | L SUM | $4,000.00 | |
| 45 | 70103815 | TR CONT SURVEILLANCE | 10 | CAL DA | $1,800.00 | |
| 46 | 70106800 | CHANGEABLE MESSAGE SN | 10 | CAL MO | $1,200.00 | |
| 47 | 70300100 | SHORT TERM PAVT MKING | 820 | FOOT | $1.00 | |
| 48 | 70300150 | SHRT TRM PAVT MK REM | 274 | SQ FT | $6.00 | |
| 49 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 12,310 | FOOT | $0.4500 | |
| 50 | 70400100 | TEMP CONC BARRIER | 1,150 | FOOT | $23.50 | |
| 51 | 70400200 | REL TEMP CONC BARRIER | 1,050 | FOOT | $5.00 | |
| 52 | 70600250 | IMP ATTN TEMP NRD TL3 | 2 | EACH | $2,350.00 | |
| 53 | 70600350 | IMP ATTN REL NRD TL3 | 2 | EACH | $650.00 | |
| 54 | 78003131 | PREF PL PM TB STAN L6 | 1,260 | FOOT | $7.64 | |
| 55 | 78008210 | POLYUREA PM T1 LN 4 | 9,800 | FOOT | $1.55 | |
| 56 | 78008240 | POLYUREA PM T1 LN 8 | 1,250 | FOOT | $3.09 | |
| 57 | 78011025 | GRV RCSD PVT MRKG 5 | 8,672 | FOOT | $0.9000 | |
| 58 | 78011035 | GRV RCSD PVT MRKG 7 | 1,100 | FOOT | $1.40 | |
| 59 | 78011045 | GRV RCSD PVT MRKG 9 | 1,250 | FOOT | $1.80 | |
| 60 | 78100100 | RAISED REFL PAVT MKR | 8 | EACH | $637.00 | |
| 61 | 78300200 | RAISED REF PVT MK REM | 5 | EACH | $25.00 | |
| 62 | 78300202 | PAVMT MRKG REM WTR BL | 6,270 | SQ FT | $3.00 |