Bid tab 66L31

Let Jun 11, 2021 · District 3 · Kendall Sign up free

‹ Jun 2021 results

(129)SFY-Y

Let date
Friday, June 11, 2021
Contract
66L31 · job page
District
District 3
County
Kendall
Highway
Limits
This project consists of 3.94 miles of shoulder widening and rumble strip installation on_US 52 from 0.16 miles East of IL 17 to Grove Rd in Kendall County.

Bidders 2

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 D. Construction, Inc. Low bidder $688,542
2 P. T. Ferro Construction Co. $898,829 +30.5%

Bid tab: unit prices 12 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 D. Construction…#2 P. T. Ferro Con…
1X0800001 SHLDR REM SPL18,318SQ YD $7.00 $9.00
2Z0030850 TEMP INFO SIGNING42SQ FT $25.00 $25.00
340600290 BIT MATLS TACK CT8,261POUND $0.0100 $0.0100
440800050 INCIDENTAL HMA SURF3.6TON $200.00 $500.00
544000157 HMA SURF REM 230.2SQ YD $25.00 $25.00
648102100 AGG WEDGE SHLD TYPE B529TON $23.00 $35.00
748203029 HMA SHOULDERS 818,318SQ YD $25.00 $34.00
864200108 SHOULDER RUM STRIP 841,197FOOT $0.3000 $0.6000
967100100 MOBILIZATION1L SUM $38,764.00 $42,000.00
1070100500 TRAF CONT-PROT 7013261L SUM $10,000.00 $10,000.00
1170103815 TR CONT SURVEILLANCE5CAL DA $400.00 $0.0100
1278001110 PAINT PVT MK LINE 487,388FOOT $0.2800 $0.1400