(126,127,129,130)G
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Phoenix Corporation of the Quad Cities Low bidder | $175,911 | ||
| 2 | D. Construction, Inc. | $191,750 | +9.0% | |
| 3 | Gallagher Asphalt Corporation | $205,101 | +16.6% | |
| 4 | P. T. Ferro Construction Co. | $240,966 | +37.0% | |
| 5 | Austin Tyler Construction, Inc. | $260,675 | +48.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Phoenix Corpora… | #2 D. Construction… | #3 Gallagher Aspha… | #4 P. T. Ferro Con… | #5 Austin Tyler Co… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Z0030850 | TEMP INFO SIGNING | 42 | SQ FT | $18.00 | $25.00 | $20.00 | $50.00 | $50.00 | |
| 2 | 48102100 | AGG WEDGE SHLD TYPE B | 8,495 | TON | $17.00 | $20.00 | $22.75 | $27.00 | $30.00 | |
| 3 | 67100100 | MOBILIZATION | 1 | L SUM | $14,490.00 | $10,800.00 | $6,000.00 | $1.00 | $3,000.00 | |
| 4 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $16,250.00 | $10,000.00 | $5,000.00 | $9,500.00 | $725.00 |