(108,109)CR
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | G. M. Sipes Construction, Inc. Low bidder | $131,005 | ||
| 2 | Lion Construction 1, LLC | $225,502 | +72.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 G. M. Sipes Con… | #2 Lion Constructi… |
|---|---|---|---|---|---|---|---|
| 1 | X1200050 | BOX CULVERT REMOVAL | 60 | FOOT | $200.00 | $300.00 | |
| 2 | Z0030850 | TEMP INFO SIGNING | 42 | SQ FT | $50.00 | $50.00 | |
| 3 | 20400800 | FURNISHED EXCAVATION | 5.2 | CU YD | $275.00 | $100.00 | |
| 4 | 20800150 | TRENCH BACKFILL | 12.6 | CU YD | $675.00 | $80.00 | |
| 5 | 44201019 | CL B PATCH T2 14 | 32 | SQ YD | $625.00 | $937.50 | |
| 6 | 44201299 | DOWEL BARS 1 1/2 | 80 | EACH | $45.00 | $45.00 | |
| 7 | 44213200 | SAW CUTS | 156 | FOOT | $20.00 | $10.00 | |
| 8 | 48101200 | AGGREGATE SHLDS B | 2 | TON | $250.00 | $50.00 | |
| 9 | 50105220 | PIPE CULVERT REMOV | 50 | FOOT | $100.00 | $100.00 | |
| 10 | 542A0223 | P CUL CL A 1 18 | 38 | FOOT | $150.00 | $150.00 | |
| 11 | 542A5479 | P CUL CL A 1 EQRS 24 | 38 | FOOT | $225.00 | $225.00 | |
| 12 | 54213663 | PRC FLAR END SEC 18 | 2 | EACH | $2,250.00 | $1,500.00 | |
| 13 | 54214509 | PRC FL END S EQ RS 24 | 3 | EACH | $2,500.00 | $2,500.00 | |
| 14 | 63500310 | REM & REIN DELINEATOR | 4 | EACH | $150.00 | $200.00 | |
| 15 | 66900200 | NON SPL WASTE DISPOSL | 20 | CU YD | $250.00 | $1,500.00 | |
| 16 | 66900530 | SOIL DISPOSAL ANALY | 2 | EACH | $1,250.00 | $2,400.00 | |
| 17 | 66901001 | REG SUB P-CONST PLAN | 1 | LSUM | $2,500.00 | $3,000.00 | |
| 18 | 66901002 | ON-SITE MON REG SUB | 2 | CAL DA | $1,200.00 | $2,500.00 | |
| 19 | 66901003 | REG SUB F CON REPORT | 1 | LSUM | $3,500.00 | $2,500.00 | |
| 20 | 67100100 | MOBILIZATION | 1 | L SUM | $8,000.00 | $12,764.28 | |
| 21 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $24,000.00 | $80,000.00 |