((201-3)R&(4-1,5)R)PP
- Let date
- Friday, August 1, 2025
- Contract
- 64U52 · job page
- District
- District 2
- County
- Winnebago
- Highway
- Limits
- 4.3 miles of pavement patching and widening on I-39 from 0.8 minorth of Blackhawk Rd to 0.4 mi north of Harrison Ave (including interchange ramps) and US 20 from 0.6 miles west of Mulford Rd to I-39.
- Classification
- ·
- Project number
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | G. M. Sipes Construction, Inc. Low bidder | $3,920,847 | ||
| 2 | Martin & Company Excavating | $4,476,192 | +14.2% | |
| 3 | Plote Construction, Inc. | $7,000,000 | +78.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 G. M. Sipes Con… | #2 Martin & Compan… | #3 Plote Construct… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $10,000.00 | $29,000.00 | $6,775.00 | |
| 2 | X0326806 | WASHOUT BASIN | 1 | L SUM | $1,000.00 | $6,000.00 | $20,000.00 | |
| 3 | X2100104 | GEOTECHNICAL REINF | 5,258 | SQ YD | $1.00 | $6.00 | $3.00 | |
| 4 | X4810110 | TEMP AGGREGATE WEDGE | 169 | TON | $10.00 | $71.00 | $65.00 | |
| 5 | X6700410 | ENGR FLD OFF A SPL | 3 | CAL MO | $2,000.00 | $6,900.00 | $5,500.00 | |
| 6 | X7010600 | TC-PROT 701406 SPL | 1 | L SUM | $5,000.00 | $10,100.00 | $125,000.00 | |
| 7 | X7200075 | REM & REIN SIGN PANEL | 50 | SQ FT | $15.00 | $188.00 | $75.00 | |
| 8 | Z0013797 | STAB CONSTR ENTRANCE | 224 | SQ YD | $20.00 | $51.00 | $30.00 | |
| 9 | Z0017099 | DOWEL BAR ASSEMBLY | 256 | EACH | $150.00 | $250.00 | $230.00 | |
| 10 | 20200100 | EARTH EXCAVATION | 3,495 | CU YD | $1.00 | $96.30 | $200.00 | |
| 11 | 20201200 | REM & DISP UNS MATL | 1,245 | CU YD | $1.00 | $48.00 | $200.00 | |
| 12 | 21101505 | TOPSOIL EXC & PLAC | 1,000 | CU YD | $20.00 | $56.00 | $45.00 | |
| 13 | 25000210 | SEEDING CL 2A | 1 | ACRE | $2,000.00 | $4,000.00 | $2,000.00 | |
| 14 | 25000310 | SEEDING CL 4 | 0.25 | ACRE | $8,000.00 | $16,000.00 | $8,000.00 | |
| 15 | 25000312 | SEEDING CL 4A | 0.75 | ACRE | $3,500.00 | $7,000.00 | $3,500.00 | |
| 16 | 25000320 | SEEDING CL 5 | 0.75 | ACRE | $3,500.00 | $7,000.00 | $3,500.00 | |
| 17 | 25000400 | NITROGEN FERT NUTR | 180 | POUND | $2.00 | $5.00 | $2.00 | |
| 18 | 25000500 | PHOSPHORUS FERT NUTR | 180 | POUND | $2.00 | $5.00 | $2.00 | |
| 19 | 25000600 | POTASSIUM FERT NUTR | 180 | POUND | $2.00 | $5.00 | $2.00 | |
| 20 | 25100127 | MULCH METHOD 3A | 2 | ACRE | $3,000.00 | $6,000.00 | $3,000.00 | |
| 21 | 28000250 | TEMP EROS CONTR SEED | 156 | POUND | $1.00 | $2.00 | $1.00 | |
| 22 | 28000305 | TEMP DITCH CHECKS | 26 | FOOT | $30.00 | $60.00 | $30.00 | |
| 23 | 28000400 | PERIMETER EROS BAR | 2,217 | FOOT | $5.00 | $10.00 | $5.00 | |
| 24 | 28001100 | TEMP EROS CONTR BLANK | 7,542 | SQ YD | $0.0100 | $1.00 | $0.0100 | |
| 25 | 30300124 | AGG SUBGRADE IMPR 24 | 5,258 | SQ YD | $40.00 | $91.00 | $100.00 | |
| 26 | 42000060 | WELDED WIRE REINF | 5,138 | SQ YD | $15.00 | $15.00 | $14.00 | |
| 27 | 44000100 | PAVEMENT REM | 1,719 | SQ YD | $125.00 | $66.00 | $125.00 | |
| 28 | 44004250 | PAVED SHLD REMOVAL | 2,077 | SQ YD | $100.00 | $66.00 | $58.00 | |
| 29 | 44201000 | CL B PATCH T4 12 | 5,138 | SQ YD | $395.00 | $271.00 | $710.00 | |
| 30 | 44201299 | DOWEL BARS 1 1/2 | 268 | EACH | $50.00 | $35.00 | $21.00 | |
| 31 | 44213200 | SAW CUTS | 2,461 | FOOT | $10.00 | $12.00 | $40.00 | |
| 32 | 44213204 | TIE BARS 3/4 | 1,285 | EACH | $25.00 | $30.00 | $23.00 | |
| 33 | 48100500 | AGGREGATE SHLDS A 6 | 482 | SQ YD | $100.00 | $41.00 | $40.00 | |
| 34 | 60100060 | CONC HDWL FOR P DRAIN | 1 | EACH | $1,000.00 | $650.00 | $2,500.00 | |
| 35 | 60100080 | FRENCH DRAINS | 19 | CU YD | $500.00 | $240.00 | $300.00 | |
| 36 | 60100085 | GEO FAB-FRENCH DRAIN | 170 | SQ YD | $1.00 | $8.00 | $12.00 | |
| 37 | 60108200 | PIPE UNDERDRAIN 6 SP | 62 | FOOT | $10.00 | $111.00 | $200.00 | |
| 38 | 60108206 | PIPE UNDERDR T 2 6 | 310 | FOOT | $10.00 | $90.00 | $135.00 | |
| 39 | 63500105 | DELINEATORS | 6 | EACH | $100.00 | $150.00 | $150.00 | |
| 40 | 66900200 | NON SPL WASTE DISPOSL | 4,670 | CU YD | $0.0100 | $167.00 | $90.00 | |
| 41 | 66900530 | SOIL DISPOSAL ANALY | 1 | EACH | $1,350.00 | $1,600.00 | $1,800.00 | |
| 42 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $3,400.00 | $4,000.00 | $3,350.00 | |
| 43 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $1,200.00 | $1,600.00 | $1,500.00 | |
| 44 | 66901006 | REG SUB MON | 14 | CAL DA | $2,500.00 | $2,000.00 | $950.00 | |
| 45 | 67100100 | MOBILIZATION | 1 | L SUM | $195,000.00 | $250,000.00 | $402,047.73 | |
| 46 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $600,000.00 | $135,000.00 | $25,000.00 | |
| 47 | 70103815 | TR CONT SURVEILLANCE | 25 | CAL DA | $0.0100 | $125.00 | $100.00 | |
| 48 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $150.00 | $65.00 | $35.00 | |
| 49 | 70200100 | NIGHT WORK ZONE LIGHT | 1 | L SUM | $15,000.00 | $166,000.00 | $12,500.00 | |
| 50 | 70300150 | SHRT TRM PAVT MK REM | 451 | SQ FT | $5.00 | $1.20 | $0.6000 | |
| 51 | 70307120 | TEMP PVT MK L4 T4 TAPE | 1,196 | FOOT | $4.00 | $2.25 | $1.15 | |
| 52 | 70307130 | TEMP PVT MK L6 T4 TAPE | 105 | FOOT | $12.50 | $3.00 | $1.75 | |
| 53 | 72000200 | SIGN PANEL T2 | 32 | SQ FT | $25.00 | $52.00 | $32.00 | |
| 54 | 72800100 | TELES STL SIN SUPPORT | 86 | FOOT | $10.00 | $25.00 | $15.00 | |
| 55 | 78009004 | MOD URETH PM LINE 4 | 4,256 | FOOT | $3.30 | $4.00 | $3.30 | |
| 56 | 78009006 | MOD URETH PM LINE 6 | 532 | FOOT | $5.50 | $5.00 | $5.50 | |
| 57 | 78009012 | MOD URETH PM LINE 12 | 347 | FOOT | $11.00 | $10.00 | $11.00 | |
| 58 | 78100100 | RAISED REFL PAVT MKR | 146 | EACH | $165.00 | $115.00 | $10.00 | |
| 59 | 78300200 | RAISED REF PVT MK REM | 52 | EACH | $10.00 | $25.00 | $25.00 | |
| 60 | 78300202 | PVT MKG REM WTR BLAST | 1,462 | SQ FT | $8.00 | $5.00 | $2.65 |