$137.21Avg low bid / CU YD
$139.84Avg of all bids
—Avg engineer's estimate
7Jobs · 338 CU YD
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 4 | 284 | $114.27 | $118.46 |
| 2025 | 3 | 54 | $257.87 | $228.50 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Sep 18, 2026 | 76V40 | VariousDistrict 8 | 30 CU YD | $197.80 | Keeley & Sons, Inc. |
| Apr 24, 2026 | 76V14 | VariousDistrict 8 | 30 CU YD | $197.80 | Keeley & Sons, Inc. |
| Feb 27, 2026 | 76U52 | VariousDistrict 8 | 30 CU YD | $130.00 | Kinney Contractors, Inc. |
| Jan 16, 2026 | 64L27 | StephensonDistrict 2 | 194 CU YD | $86.00 | Martin & Company Excavating |
| Aug 1, 2025 | 64U52 | WinnebagoDistrict 2 | 19 CU YD | $500.00 | G. M. Sipes Construction, Inc. |
| Mar 7, 2025 | 76T97 | VariousDistrict 8 | 30 CU YD | $120.00 | Kinney Contractors, Inc. |
| Jan 17, 2025 | 64M10 | LeeDistrict 2 | 5 CU YD | $165.00 | Martin & Company Excavating |