(110,111)PP&RS
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Martin & Company Excavating Low bidder | $3,123,589 | ||
| 2 | Rock Road Companies, Inc. | $3,227,219 | +3.3% | |
| 3 | Curran Contracting Company | $3,394,258 | +8.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Martin & Compan… | #2 Rock Road Compa… | #3 Curran Contract… |
|---|---|---|---|---|---|---|---|---|
| 1 | X4401196 | HMA SURF REM-LONG JT | 2,326 | SQ YD | $5.99 | $15.88 | $5.50 | |
| 2 | X6420110 | RUMBLE RESURFACING | 100 | SQ YD | $80.00 | $106.13 | $92.50 | |
| 3 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $9,500.00 | $7,730.00 | $3,980.00 | |
| 4 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $6,000.00 | $8,321.24 | $2,500.00 | |
| 5 | 40600295 | P BIT MATLS TACK CT | 109,405 | POUND | $0.1000 | $0.0100 | $0.0100 | |
| 6 | 40600370 | LONG JOINT SEALANT | 41,875 | FOOT | $3.00 | $2.38 | $2.40 | |
| 7 | 40600405 | MATL TRANSFER DEVICE | 25,528 | TON | $3.70 | $1.97 | $1.75 | |
| 8 | 40600900 | HMA BC HM N50 | 100 | TON | $50.00 | $118.75 | $120.00 | |
| 9 | 40600990 | TEMPORARY RAMP | 600 | SQ YD | $5.60 | $28.25 | $11.00 | |
| 10 | 40603080 | HMA BC IL-19.0 N50 | 15,317 | TON | $65.00 | $74.00 | $74.50 | |
| 11 | 40604060 | HMA SC IL-9.5 D N50 | 10,211 | TON | $65.00 | $75.00 | $74.50 | |
| 12 | 40800050 | INCIDENTAL HMA SURF | 750 | TON | $81.00 | $144.39 | $145.00 | |
| 13 | 44000162 | HMA SURF REM 3 1/4 | 127,297 | SQ YD | $2.22 | $2.00 | $2.75 | |
| 14 | 44201753 | CL D PATCH T2 9 | 1,387 | SQ YD | $70.00 | $107.52 | $100.00 | |
| 15 | 44201757 | CL D PATCH T3 9 | 1,387 | SQ YD | $70.00 | $101.07 | $75.00 | |
| 16 | 44201759 | CL D PATCH T4 9 | 1,387 | SQ YD | $70.00 | $89.30 | $65.00 | |
| 17 | 48102100 | AGG WEDGE SHLD TYPE B | 1,951 | TON | $20.00 | $29.04 | $34.50 | |
| 18 | 67000400 | ENGR FIELD OFFICE A | 4 | CAL MO | $2,600.00 | $2,185.26 | $2,500.00 | |
| 19 | 67100100 | MOBILIZATION | 1 | L SUM | $175,000.00 | $38,000.00 | $250,000.00 | |
| 20 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $2.00 | $1.00 | $1.00 | |
| 21 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $145,000.00 | $13,900.00 | $13,900.00 | |
| 22 | 70107025 | CHANGEABLE MESSAGE SN | 30 | CAL DA | $45.00 | $40.00 | $40.00 | |
| 23 | 70300100 | SHORT TERM PAVT MKING | 58,160 | FOOT | $0.1000 | $0.4300 | $0.2500 | |
| 24 | 70300150 | SHRT TRM PAVT MK REM | 19,193 | SQ FT | $1.10 | $1.00 | $0.2500 | |
| 25 | 72000100 | SIGN PANEL T1 | 359 | SQ FT | $27.00 | $30.00 | $30.00 | |
| 26 | 72000200 | SIGN PANEL T2 | 102 | SQ FT | $42.00 | $40.00 | $40.00 | |
| 27 | 72400310 | REMOV SIGN PANEL T1 | 314 | SQ FT | $11.00 | $10.00 | $10.00 | |
| 28 | 72400320 | REMOV SIGN PANEL T2 | 134 | SQ FT | $17.00 | $12.00 | $12.00 | |
| 29 | 72400710 | RELOC SIGN PANEL T1 | 74 | SQ FT | $17.00 | $35.00 | $35.00 | |
| 30 | 72400720 | RELOC SIGN PANEL T2 | 54 | SQ FT | $22.00 | $45.00 | $45.00 | |
| 31 | 72800100 | TELES STL SIN SUPPORT | 513 | FOOT | $18.00 | $17.00 | $17.00 | |
| 32 | 73000100 | WOOD SIN SUPPORT | 306 | FOOT | $39.00 | $20.00 | $20.00 | |
| 33 | 78000100 | THPL PVT MK LTR & SYM | 123 | SQ FT | $4.00 | $3.60 | $3.60 | |
| 34 | 78000200 | THPL PVT MK LINE 4 | 114,949 | FOOT | $0.6200 | $0.6000 | $0.6000 | |
| 35 | 78000600 | THPL PVT MK LINE 12 | 173 | FOOT | $1.90 | $1.80 | $1.80 | |
| 36 | 78000650 | THPL PVT MK LINE 24 | 72 | FOOT | $3.90 | $3.60 | $3.60 | |
| 37 | 78011000 | GRV RCSD PM LTR & SYM | 136 | SQ FT | $4.20 | $4.00 | $4.00 | |
| 38 | 78011025 | GRV RCSD PVT MRKG 5 | 114,949 | FOOT | $0.3300 | $0.3000 | $0.3000 | |
| 39 | 78011065 | GRV RCSD PVT MRKG 13 | 173 | FOOT | $2.10 | $2.00 | $2.00 | |
| 40 | 78011125 | GRV RCSD PVT MRKG 25 | 72 | FOOT | $4.40 | $4.00 | $4.00 | |
| 41 | 78300200 | RAISED REF PVT MK REM | 26 | EACH | $10.00 | $23.00 | $18.50 |