D2 BP 2020-1
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Three Star Painting, Inc. Low bidder | $285,000 | ||
| 2 | ERA-Valdivia Contractors, Inc. | $424,805 | +49.1% | |
| 3 | Civil Coatings and Construction Inc. | $432,550 | +51.8% | |
| 4 | Venus Painting Co. | $482,200 | +69.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Three Star Pain… | #2 ERA-Valdivia Co… | #3 Civil Coatings … | #4 Venus Painting … |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X5067501 | BR CLN & PT WAR #1 | 1 | L SUM | $500.00 | $3,000.00 | $250.00 | $300.00 | |
| 2 | X5067502 | BR CLN & PT WAR #2 | 1 | L SUM | $500.00 | $3,000.00 | $250.00 | $300.00 | |
| 3 | X7010208 | TC-PROT 701402 SPL | 4 | EACH | $1,000.00 | $30,085.00 | $27,350.00 | $1,000.00 | |
| 4 | Z0007101 | C&D LEAD PT CL RS N1 | 1 | L SUM | $500.00 | $25,000.00 | $1,000.00 | $12,000.00 | |
| 5 | Z0007102 | C&D LEAD PT CL RS N2 | 1 | L SUM | $500.00 | $25,000.00 | $1,000.00 | $12,000.00 | |
| 6 | Z0010501 | CLEAN & PT STL BR N1 | 1 | L SUM | $124,737.50 | $87,500.00 | $123,750.00 | $200,000.00 | |
| 7 | Z0010502 | CLEAN & PT STL BR N2 | 1 | L SUM | $124,737.50 | $87,500.00 | $123,750.00 | $200,000.00 | |
| 8 | 67100100 | MOBILIZATION | 1 | L SUM | $14,250.00 | $15,000.00 | $20,000.00 | $40,000.00 | |
| 9 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $2,500.00 | $2,200.00 | $2,000.00 | $2,000.00 | |
| 10 | 70400100 | TEMP CONC BARRIER | 775 | FOOT | $12.00 | $49.50 | $45.00 | $6.00 | |
| 11 | 70400200 | REL TEMP CONC BARRIER | 1,075 | FOOT | $1.00 | $1.10 | $1.00 | $2.00 | |
| 12 | 70600250 | IMP ATTN TEMP NRD TL3 | 2 | EACH | $600.00 | $7,700.00 | $7,000.00 | $1,500.00 | |
| 13 | 70600350 | IMP ATTN REL NRD TL3 | 6 | EACH | $200.00 | $220.00 | $200.00 | $300.00 |