129RS
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Rock Road Companies, Inc. Low bidder | $895,519 | ||
| 2 | William Charles Construction Company, LLC | $920,426 | +2.8% | |
| 3 | Curran Contracting Company | $947,043 | +5.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Rock Road Compa… | #2 William Charles… | #3 Curran Contract… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0301242 | PIEZO AXLE SEN CL 2 | 46 | FOOT | $240.00 | $228.17 | $240.00 | |
| 2 | X7830060 | GRV RCSD PM LTR & SYM | 368 | SQ FT | $2.00 | $2.00 | $2.01 | |
| 3 | X7830070 | GRV RCSD PVT MRKG 5 | 30,052 | FOOT | $0.3000 | $0.3000 | $0.3000 | |
| 4 | X7830074 | GRV RCSD PVT MRKG 7 | 3,481 | FOOT | $0.4500 | $0.4500 | $0.4500 | |
| 5 | X7830076 | GRV RCSD PVT MRKG 9 | 5,762 | FOOT | $0.6000 | $0.6000 | $0.6000 | |
| 6 | X7830078 | GRV RCSD PVT MRKG 13 | 2,278 | FOOT | $0.9000 | $0.9000 | $0.9000 | |
| 7 | X7830090 | GRV RCSD PVT MRKG 25 | 774 | FOOT | $1.80 | $1.80 | $1.81 | |
| 8 | X8730810 | EC C CONOGA 30003 | 116 | FOOT | $6.85 | $3.07 | $6.85 | |
| 9 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $2,500.00 | $2,499.99 | $3,500.00 | |
| 10 | Z0028415 | GEOTECHNICAL REINF | 175 | SQ YD | $9.19 | $2.57 | $8.53 | |
| 11 | Z0033072 | VIDEO VEH DET SYS | 3 | EACH | $21,445.00 | $25,972.36 | $21,445.00 | |
| 12 | Z0033700 | LONG JOINT SEALANT | 19,860 | FOOT | $2.25 | $2.39 | $2.35 | |
| 13 | 20200100 | EARTH EXCAVATION | 15 | CU YD | $69.99 | $142.58 | $140.42 | |
| 14 | 21101615 | TOPSOIL F & P 4 | 55 | SQ YD | $4.04 | $4.00 | $4.00 | |
| 15 | 25200110 | SODDING SALT TOLERANT | 55 | SQ YD | $57.00 | $57.00 | $57.00 | |
| 16 | 25200200 | SUPPLE WATERING | 2 | UNIT | $50.00 | $50.00 | $50.15 | |
| 17 | 30300001 | AGG SUBGRADE IMPROVE | 29 | CU YD | $91.37 | $171.81 | $58.17 | |
| 18 | 40600295 | P BIT MATLS TACK CT | 22,343 | POUND | $0.5700 | $0.9500 | $0.0100 | |
| 19 | 40600990 | TEMPORARY RAMP | 1,143 | SQ YD | $0.0100 | $8.49 | $5.00 | |
| 20 | 40604162 | P HMA SC IL-9.5 D N70 | 5,561 | TON | $75.00 | $73.31 | $75.00 | |
| 21 | 40800050 | INCIDENTAL HMA SURF | 22 | TON | $125.27 | $332.90 | $130.00 | |
| 22 | 42400200 | PC CONC SIDEWALK 5 | 994 | SQ FT | $14.25 | $6.20 | $15.80 | |
| 23 | 42400800 | DETECTABLE WARNINGS | 148 | SQ FT | $20.00 | $40.00 | $26.08 | |
| 24 | 44000100 | PAVEMENT REM | 32 | SQ YD | $32.66 | $74.48 | $45.14 | |
| 25 | 44000157 | HMA SURF REM 2 | 49,651 | SQ YD | $2.30 | $1.51 | $2.50 | |
| 26 | 44000500 | COMB CURB GUTTER REM | 194 | FOOT | $18.83 | $12.31 | $10.03 | |
| 27 | 44000600 | SIDEWALK REM | 462 | SQ FT | $5.36 | $4.76 | $6.02 | |
| 28 | 44201789 | CL D PATCH T2 12 | 43 | SQ YD | $202.24 | $176.79 | $115.00 | |
| 29 | 44201794 | CL D PATCH T3 12 | 120 | SQ YD | $149.65 | $114.55 | $110.00 | |
| 30 | 44201796 | CL D PATCH T4 12 | 187 | SQ YD | $109.62 | $120.41 | $105.00 | |
| 31 | 44213200 | SAW CUTS | 303 | FOOT | $1.85 | $2.10 | $5.02 | |
| 32 | 60605000 | COMB CC&G TB6.24 | 194 | FOOT | $50.97 | $38.30 | $80.24 | |
| 33 | 67000400 | ENGR FIELD OFFICE A | 3 | CAL MO | $2,060.00 | $2,502.46 | $2,500.00 | |
| 34 | 67100100 | MOBILIZATION | 1 | L SUM | $13,500.00 | $55,416.00 | $57,000.00 | |
| 35 | 70100310 | TRAF CONT-PROT 701421 | 1 | L SUM | $13,500.00 | $6,999.97 | $10,000.00 | |
| 36 | 70100320 | TRAF CONT-PROT 701422 | 1 | L SUM | $1.00 | $1.00 | $1.00 | |
| 37 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $1.00 | $1.00 | $1.00 | |
| 38 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $1.00 | $1.00 | $1.00 | |
| 39 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.00 | $1.00 | |
| 40 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1.00 | $3,399.99 | $5,000.00 | |
| 41 | 70103815 | TR CONT SURVEILLANCE | 6 | CAL DA | $300.00 | $650.00 | $651.96 | |
| 42 | 70107025 | CHANGEABLE MESSAGE SN | 60 | CAL DA | $35.00 | $25.00 | $25.08 | |
| 43 | 70300100 | SHORT TERM PAVT MKING | 8,078 | FOOT | $0.7400 | $1.05 | $0.3500 | |
| 44 | 70300150 | SHRT TRM PAVT MK REM | 1,346 | SQ FT | $1.67 | $1.65 | $2.00 | |
| 45 | 78000100 | THPL PVT MK LTR & SYM | 768 | SQ FT | $3.50 | $3.50 | $3.51 | |
| 46 | 78000200 | THPL PVT MK LINE 4 | 31,075 | FOOT | $0.5500 | $0.5500 | $0.5500 | |
| 47 | 78000400 | THPL PVT MK LINE 6 | 3,481 | FOOT | $0.8300 | $0.8300 | $0.8300 | |
| 48 | 78000500 | THPL PVT MK LINE 8 | 6,048 | FOOT | $1.10 | $1.10 | $1.10 | |
| 49 | 78000600 | THPL PVT MK LINE 12 | 5,218 | FOOT | $1.65 | $1.65 | $1.65 | |
| 50 | 78000650 | THPL PVT MK LINE 24 | 774 | FOOT | $3.30 | $3.30 | $3.31 | |
| 51 | 78100100 | RAISED REFL PAVT MKR | 408 | EACH | $25.00 | $25.00 | $25.08 | |
| 52 | 78300200 | RAISED REF PVT MK REM | 400 | EACH | $8.39 | $13.63 | $12.00 | |
| 53 | 88600100 | DET LOOP T1 | 486 | FOOT | $26.22 | $18.97 | $26.22 | |
| 54 | 89502200 | MOD EX CONTR | 3 | EACH | $1,370.00 | $1,879.09 | $1,370.00 | |
| 55 | 89502300 | REM ELCBL FR CON | 100 | FOOT | $3.00 | $1.35 | $3.00 |