FAP 0341 23 SMART2
- Let date
- Friday, April 25, 2025
- Contract
- 62V89 · job page
- District
- District 1
- County
- Cook
- Highway
- Limits
- (1.27-Mile) SMART Overlay and ADA Improvements: HMA surface removal and replacement, Class D patches, sidewalk and curb removal and replacement, drainage structures adjustments, minor traffic signal (APS) improvements, detector loops replacement, pavement markings. Located along IL 72 (Higgins Road) from Audubon Street to Lexington Drive within the Villages of Hoffman Estates and Schaumburg.
- Classification
- ·
- Project number
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Plote Construction, Inc. Low bidder | $2,516,963 | ||
| 2 | K-Five Construction Corporation | $2,681,503 | +6.5% | |
| 3 | Builders Paving, LLC | $2,718,818 | +8.0% | |
| 4 | R. W. Dunteman Company | $2,843,406 | +13.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Plote Construct… | #2 K-Five Construc… | #3 Builders Paving… | #4 R. W. Dunteman … |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $9,500.00 | $6,900.00 | $15,000.00 | $8,000.00 | |
| 2 | X1400367 | PED SIGNAL POST 10 FT | 5 | EACH | $1,332.78 | $1,399.81 | $1,350.00 | $1,366.49 | |
| 3 | X1400378 | PED SIGNAL POST 5 FT | 16 | EACH | $1,060.49 | $960.34 | $1,100.00 | $1,087.31 | |
| 4 | X2010516 | SELECTIVE CLEARING | 7 | UNIT | $450.00 | $470.00 | $470.00 | $450.00 | |
| 5 | X4400501 | CC&G RMVL REPL < = 10 | 85 | FOOT | $55.00 | $54.00 | $102.00 | $71.37 | |
| 6 | X4400503 | CC&G RMVL REPL > 10FT | 945 | FOOT | $55.00 | $54.00 | $82.00 | $70.73 | |
| 7 | X5537800 | SS CLEANED 12 | 860 | FOOT | $1.00 | $1.00 | $1.00 | $3.00 | |
| 8 | X6030310 | FR & LIDS ADJUST SPL | 8 | EACH | $1,250.00 | $1,250.00 | $1,250.00 | $1,250.00 | |
| 9 | X6700407 | ENGRS FLD OFC TY A D1 | 12 | CAL MO | $3,500.00 | $3,300.00 | $3,500.00 | $4,500.00 | |
| 10 | X8760200 | ACCESSIBLE PED SIGNAL | 34 | EACH | $1,752.92 | $1,808.59 | $1,750.00 | $1,797.25 | |
| 11 | X8780012 | CONC FDN TY A 12D | 84 | FOOT | $268.59 | $481.47 | $275.00 | $275.38 | |
| 12 | Z0018500 | DRAINAGE STR CLEANED | 86 | EACH | $320.00 | $315.00 | $315.00 | $350.00 | |
| 13 | Z0030850 | TEMP INFO SIGNING | 102.8 | SQ FT | $15.00 | $15.00 | $15.00 | $15.00 | |
| 14 | Z0033044 | RE-OPTIMIZE TR SIG SYS 1 | 3 | EACH | $575.00 | $525.00 | $575.00 | $589.54 | |
| 15 | 20200100 | EARTH EXCAVATION | 26 | CU YD | $96.00 | $65.00 | $50.00 | $65.00 | |
| 16 | 21101615 | TOPSOIL F & P 4 | 153 | SQ YD | $18.00 | $5.00 | $15.00 | $5.00 | |
| 17 | 25200110 | SODDING SALT TOLERANT | 153 | SQ YD | $32.00 | $50.00 | $25.00 | $50.00 | |
| 18 | 25200200 | SUPPLE WATERING | 8 | UNIT | $25.00 | $1.00 | $55.00 | $1.00 | |
| 19 | 40600290 | BIT MATLS TACK CT | 34,936 | POUND | $0.0100 | $0.9200 | $0.0100 | $0.6400 | |
| 20 | 40600370 | LONG JOINT SEALANT | 40,212 | FOOT | $2.45 | $2.33 | $3.00 | $2.34 | |
| 21 | 40600400 | MIX CR JTS FLANGEWYS | 116 | TON | $150.00 | $100.00 | $200.00 | $394.52 | |
| 22 | 40600982 | HMA SURF REM BUTT JT | 446 | SQ YD | $14.00 | $9.25 | $25.00 | $30.17 | |
| 23 | 40601005 | HMA REPL OVER PATCH | 375 | TON | $75.00 | $204.47 | $175.00 | $137.79 | |
| 24 | 40605026 | P HMA SC SMA 9.5 F N80 | 7,533 | TON | $126.00 | $117.88 | $104.00 | $107.04 | |
| 25 | 42001300 | PROTECTIVE COAT | 750 | SQ YD | $0.0100 | $0.0100 | $0.1000 | $3.00 | |
| 26 | 42400200 | PC CONC SIDEWALK 5 | 2,616 | SQ FT | $13.75 | $13.75 | $9.40 | $15.00 | |
| 27 | 42400800 | DETECTABLE WARNINGS | 330 | SQ FT | $32.00 | $32.00 | $38.00 | $55.00 | |
| 28 | 44000156 | HMA SURF REM 1 3/4 | 76,866 | SQ YD | $3.00 | $2.35 | $4.00 | $2.35 | |
| 29 | 44000600 | SIDEWALK REM | 2,805 | SQ FT | $3.00 | $3.00 | $4.00 | $5.00 | |
| 30 | 44002216 | HMA RM OV PATCH 4 | 2,025 | SQ YD | $5.00 | $0.0100 | $0.0100 | $13.68 | |
| 31 | 44003100 | MEDIAN REMOVAL | 2,515 | SQ FT | $5.50 | $5.50 | $3.00 | $9.72 | |
| 32 | 44201383 | CL C PATCH T4 12 | 20 | SQ YD | $355.00 | $355.00 | $250.00 | $226.77 | |
| 33 | 44201765 | CL D PATCH T2 10 | 2,604 | SQ YD | $60.00 | $40.00 | $80.00 | $131.85 | |
| 34 | 44201769 | CL D PATCH T3 10 | 120 | SQ YD | $50.00 | $40.00 | $80.00 | $120.37 | |
| 35 | 44201771 | CL D PATCH T4 10 | 345 | SQ YD | $45.00 | $40.00 | $80.00 | $109.83 | |
| 36 | 60250200 | CB ADJUST | 3 | EACH | $450.00 | $450.00 | $450.00 | $450.00 | |
| 37 | 60252800 | CB RECONST | 3 | EACH | $1,450.00 | $1,450.00 | $1,450.00 | $1,450.00 | |
| 38 | 60255500 | MAN ADJUST | 3 | EACH | $550.00 | $550.00 | $550.00 | $550.00 | |
| 39 | 60257900 | MAN RECONST | 3 | EACH | $1,850.00 | $1,850.00 | $1,850.00 | $1,850.00 | |
| 40 | 60300105 | FR & GRATES ADJUST | 13 | EACH | $450.00 | $450.00 | $450.00 | $450.00 | |
| 41 | 60300305 | FR & LIDS ADJUST | 16 | EACH | $450.00 | $450.00 | $450.00 | $450.00 | |
| 42 | 60404950 | FR & GRATES T24 | 2 | EACH | $485.00 | $485.00 | $485.00 | $485.00 | |
| 43 | 60406000 | FR & LIDS T1 OL | 3 | EACH | $455.00 | $455.00 | $455.00 | $455.00 | |
| 44 | 60406100 | FR & LIDS T1 CL | 3 | EACH | $455.00 | $455.00 | $455.00 | $455.00 | |
| 45 | 60605000 | COMB CC&G TY B-6.24 | 215 | FOOT | $52.00 | $52.00 | $67.00 | $78.78 | |
| 46 | 60618300 | CONC MEDIAN SURF 4 | 250 | SQ FT | $10.00 | $10.00 | $10.00 | $17.08 | |
| 47 | 60620000 | CONC MED TSB6.24 | 2,513 | SQ FT | $23.50 | $23.50 | $18.00 | $31.72 | |
| 48 | 66900200 | NON SPL WASTE DISPOSL | 26 | CU YD | $81.00 | $103.01 | $100.00 | $120.91 | |
| 49 | 66900530 | SOIL DISPOSAL ANALY | 2 | EACH | $900.00 | $900.00 | $900.00 | $900.00 | |
| 50 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $4,600.00 | $4,600.00 | $4,600.00 | $4,600.00 | |
| 51 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $500.00 | $500.00 | $500.00 | $500.00 | |
| 52 | 66901006 | REG SUB MON | 10 | CAL DA | $700.00 | $700.00 | $700.00 | $700.00 | |
| 53 | 67100100 | MOBILIZATION | 1 | L SUM | $151,000.00 | $145,000.00 | $331,535.19 | $165,073.97 | |
| 54 | 70100310 | TRAF CONT-PROT 701421 | 1 | L SUM | $1.00 | $4,409.51 | $4,000.00 | $75,194.25 | |
| 55 | 70100320 | TRAF CONT-PROT 701422 | 1 | L SUM | $1.00 | $4,000.00 | $4,000.00 | $3,934.00 | |
| 56 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $103,000.00 | $319,029.72 | $4,000.00 | $79,264.00 | |
| 57 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $4,000.00 | $4,000.00 | $3,934.00 | |
| 58 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1.00 | $4,000.00 | $4,000.00 | $3,934.00 | |
| 59 | 70200100 | NIGHT WORK ZONE LIGHT | 1 | L SUM | $2,000.00 | $50,000.00 | $15,000.00 | $7,574.52 | |
| 60 | 70300100 | SHORT TERM PAVT MKING | 7,802 | FOOT | $0.0100 | $0.0100 | $2.50 | $1.19 | |
| 61 | 70300150 | SHRT TRM PAVT MK REM | 2,605 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $1.30 | |
| 62 | 70300211 | TEMP PVT MK LTR & SYM PAINT | 2,002 | SQ FT | $0.0100 | $0.0100 | $1.75 | $1.75 | |
| 63 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 31,948 | FOOT | $0.0100 | $0.0100 | $0.3500 | $0.3500 | |
| 64 | 70300241 | TEMP PVT MK LINE 6 - PAINT | 6,853 | FOOT | $0.0100 | $0.0100 | $0.5500 | $0.5300 | |
| 65 | 70300251 | TEMP PVT MK LINE 8 - PAINT | 350 | FOOT | $0.0100 | $0.0100 | $0.7000 | $0.7000 | |
| 66 | 70300261 | TEMP PVT MK LINE 12 - PAINT | 1,950 | FOOT | $0.0100 | $0.0100 | $1.05 | $1.06 | |
| 67 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 845 | FOOT | $0.0100 | $0.0100 | $1.60 | $1.60 | |
| 68 | 78000100 | THPL PVT MK LTR & SYM | 2,002 | SQ FT | $5.75 | $5.75 | $5.75 | $5.75 | |
| 69 | 78000200 | THPL PVT MK LINE 4 | 31,948 | FOOT | $0.7500 | $0.7500 | $0.7500 | $0.7500 | |
| 70 | 78000400 | THPL PVT MK LINE 6 | 6,853 | FOOT | $0.8500 | $0.8500 | $0.8500 | $0.8500 | |
| 71 | 78000500 | THPL PVT MK LINE 8 | 350 | FOOT | $2.00 | $2.00 | $2.00 | $2.00 | |
| 72 | 78000600 | THPL PVT MK LINE 12 | 1,950 | FOOT | $3.32 | $3.32 | $3.30 | $3.32 | |
| 73 | 78000650 | THPL PVT MK LINE 24 | 845 | FOOT | $5.75 | $5.75 | $5.75 | $5.75 | |
| 74 | 78100100 | RAISED REFL PAVT MKR | 700 | EACH | $38.00 | $38.00 | $38.00 | $38.00 | |
| 75 | 78300200 | RAISED REF PVT MK REM | 654 | EACH | $15.00 | $0.0100 | $18.00 | $8.42 | |
| 76 | 81028200 | UNDRGRD C GALVS 2 | 365 | FOOT | $50.37 | $63.20 | $50.00 | $51.64 | |
| 77 | 85000200 | MAIN EX TR SIG INSTAL | 3 | EACH | $8,090.91 | $525.00 | $8,100.00 | $8,295.54 | |
| 78 | 87301215 | ELCBL C SIGNAL 14 2C | 5,815 | FOOT | $3.42 | $3.32 | $3.45 | $3.51 | |
| 79 | 87301225 | ELCBL C SIGNAL 14 3C | 2,090 | FOOT | $3.57 | $3.45 | $3.55 | $3.66 | |
| 80 | 87900200 | DRILL EX HANDHOLE | 22 | EACH | $816.36 | $869.08 | $825.00 | $837.01 | |
| 81 | 88102717 | PED SH LED 1F BM CDT | 8 | EACH | $813.48 | $1,163.88 | $825.00 | $834.05 | |
| 82 | 88600100 | DET LOOP T1 | 2,615 | FOOT | $27.63 | $31.50 | $27.75 | $28.33 | |
| 83 | 89500200 | RELOC EX PED SIG HEAD | 1 | EACH | $521.48 | $651.81 | $525.00 | $534.67 | |
| 84 | 89502300 | REM ELCBL FR CON | 792 | FOOT | $1.97 | $2.17 | $2.00 | $2.02 | |
| 85 | 89502375 | REMOV EX TS EQUIP | 2 | EACH | $1,179.55 | $3,910.87 | $1,200.00 | $1,209.38 | |