FAP 0360 22 RS
- Let date
- Friday, August 2, 2024
- Contract
- 62T86 · job page
- District
- District 1
- County
- Kane
- Highway
- Limits
- (0.55-Mile) SMART Overlay project consisting of hot-mix asphalt surface removal pavement patching, grading and shaping shoulders, hot-mix asphalt surface, detector loop replacement, and thermoplastic pavement marking on Hill Avenue from Montgomery Road to the Kendall County Line within the City of Aurora, in Kane County.
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D. Construction, Inc. Low bidder | $274,271 | ||
| 2 | Builders Paving, LLC | $298,000 | +8.7% | |
| 3 | K-Five Construction Corporation | $308,958 | +12.6% | |
| 4 | Geneva Construction Company | $327,171 | +19.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D. Construction… | #2 Builders Paving… | #3 K-Five Construc… | #4 Geneva Construc… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X2020110 | GRADING & SHAP SHLDRS | 40 | UNIT | $100.00 | $70.00 | $130.75 | $200.00 | |
| 2 | X4400501 | CC&G RMVL REPL < = 10 | 9 | FOOT | $250.00 | $115.00 | $185.00 | $115.00 | |
| 3 | X4400503 | CC&G RMVL REPL > 10FT | 120 | FOOT | $80.00 | $95.00 | $122.00 | $78.00 | |
| 4 | X6700407 | ENGRS FLD OFC TY A D1 | 12 | CAL MO | $1,500.00 | $2,800.00 | $3,300.00 | $3,900.00 | |
| 5 | Z0030850 | TEMP INFO SIGNING | 51.4 | SQ FT | $25.00 | $20.00 | $20.00 | $20.00 | |
| 6 | 21101615 | TOPSOIL F & P 4 | 22 | SQ YD | $66.00 | $25.00 | $16.00 | $25.00 | |
| 7 | 25200110 | SODDING SALT TOLERANT | 22 | SQ YD | $192.50 | $75.00 | $24.00 | $25.00 | |
| 8 | 25200200 | SUPPLE WATERING | 5 | UNIT | $38.50 | $100.00 | $90.00 | $10.00 | |
| 9 | 40600290 | BIT MATLS TACK CT | 4,619 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 10 | 40600370 | LONG JOINT SEALANT | 3,420 | FOOT | $4.00 | $4.00 | $4.90 | $4.10 | |
| 11 | 40600400 | MIX CR JTS FLANGEWYS | 16 | TON | $0.0100 | $675.00 | $50.00 | $200.00 | |
| 12 | 40600982 | HMA SURF REM BUTT JT | 89 | SQ YD | $0.0100 | $42.50 | $0.0100 | $20.00 | |
| 13 | 40604062 | HMA SC IL-9.5 D N70 | 863 | TON | $80.00 | $82.00 | $90.00 | $106.00 | |
| 14 | 42001300 | PROTECTIVE COAT | 26 | SQ YD | $1.00 | $2.20 | $5.00 | $1.00 | |
| 15 | 44000155 | HMA SURF REM 1 1/2 | 10,264 | SQ YD | $2.00 | $2.80 | $3.50 | $2.60 | |
| 16 | 44201809 | CL D PATCH T4 13 | 235 | SQ YD | $140.00 | $150.00 | $37.00 | $190.00 | |
| 17 | 48101200 | AGGREGATE SHLDS B | 159 | TON | $50.00 | $82.50 | $85.31 | $70.00 | |
| 18 | 60300305 | FR & LIDS ADJUST | 6 | EACH | $725.00 | $1,000.00 | $1,000.00 | $750.00 | |
| 19 | 67100100 | MOBILIZATION | 1 | L SUM | $16,450.00 | $20,281.02 | $19,000.00 | $19,000.00 | |
| 20 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $0.0100 | $1.00 | $1.00 | $100.00 | |
| 21 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $34,650.00 | $1.00 | $1.00 | $100.00 | |
| 22 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $0.0100 | $3,500.00 | $43,699.24 | $5,765.00 | |
| 23 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $0.0100 | $2,000.00 | $2,000.00 | $100.00 | |
| 24 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $0.0100 | $1.00 | $1.00 | $100.00 | |
| 25 | 70300100 | SHORT TERM PAVT MKING | 3,062 | FOOT | $0.0100 | $1.00 | $1.00 | $1.25 | |
| 26 | 70300150 | SHRT TRM PAVT MK REM | 511 | SQ FT | $0.0100 | $2.50 | $2.00 | $1.21 | |
| 27 | 70300211 | TEMP PVT MK LTR & SYM PAINT | 36 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $1.35 | |
| 28 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 7,861 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.4500 | |
| 29 | 70300241 | TEMP PVT MK LINE 6 - PAINT | 138 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.7000 | |
| 30 | 70300261 | TEMP PVT MK LINE 12 - PAINT | 77 | FOOT | $0.0100 | $0.0100 | $0.0100 | $1.35 | |
| 31 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 27 | FOOT | $0.0100 | $0.0100 | $0.0100 | $2.70 | |
| 32 | 70307120 | TEMP PVT MK L4 T4 TAPE | 1,531 | FOOT | $0.0100 | $1.00 | $1.50 | $1.20 | |
| 33 | 78000100 | THPL PVT MK LTR & SYM | 36 | SQ FT | $6.33 | $5.75 | $4.40 | $4.40 | |
| 34 | 78000200 | THPL PVT MK LINE 4 | 7,861 | FOOT | $1.60 | $1.45 | $0.7400 | $0.7400 | |
| 35 | 78000400 | THPL PVT MK LINE 6 | 138 | FOOT | $1.89 | $1.72 | $1.10 | $1.10 | |
| 36 | 78000600 | THPL PVT MK LINE 12 | 77 | FOOT | $3.65 | $3.32 | $2.20 | $2.20 | |
| 37 | 78000650 | THPL PVT MK LINE 24 | 27 | FOOT | $6.33 | $5.75 | $4.40 | $4.40 | |
| 38 | 78003137 | PREF PL PM TB STD L7 | 39 | FOOT | $82.50 | $75.00 | $5.00 | $5.00 | |
| 39 | 78009004 | MOD URETH PM LINE 4 | 309 | FOOT | $5.50 | $5.00 | $17.00 | $17.00 | |
| 40 | 78011040 | GRV RCSD PVT MRKG 8 | 348 | FOOT | $3.36 | $3.05 | $8.00 | $8.00 | |
| 41 | 78100100 | RAISED REFL PAVT MKR | 268 | EACH | $41.86 | $38.05 | $0.0100 | $33.00 | |
| 42 | 78200011 | BARR WALL REF TYPE C | 4 | EACH | $100.00 | $15.00 | $15.00 | $15.00 | |
| 43 | 78300200 | RAISED REF PVT MK REM | 228 | EACH | $10.00 | $15.00 | $0.0100 | $15.00 |