FAP 0870 22 BJ2
- Let date
- Friday, March 7, 2025
- Contract
- 62T31 · job page
- District
- District 1
- County
- Dupage
- Highway
- Limits
- Gross and Net Length = 3,713 feet (0.703 miles) and 341 feet (0.065 miles). Bridge Preservation Project: Deck Overlay, Joint Replacement / Repair at IL 53 over Ginko Way (Morton Arboretum) and over East Branch DuPage River. This project is located in Unincorporated DuPage County.
- Classification
- ·
- Project number
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D. Construction, Inc. Low bidder | $1,159,146 | ||
| 2 | Martam Construction Incorporated | $1,350,431 | +16.5% | |
| 3 | Areatha Construction Co., Inc. | $1,387,796 | +19.7% | |
| 4 | Rausch Infrastructure, LLC | $1,689,561 | +45.8% | |
| 5 | Lorig Construction Company | $1,731,652 | +49.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D. Construction… | #2 Martam Construc… | #3 Areatha Constru… | #4 Rausch Infrastr… | #5 Lorig Construct… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X4400503 | CC&G RMVL REPL > 10FT | 274 | FOOT | $50.00 | $63.00 | $67.00 | $118.00 | $180.00 | |
| 2 | X5030250 | BR DECK GROOVING LONG | 1,283 | SQ YD | $6.99 | $8.80 | $7.60 | $8.00 | $8.00 | |
| 3 | X6330801 | GDRL POST REPAIR | 1 | EACH | $484.00 | $500.00 | $440.00 | $345.00 | $500.00 | |
| 4 | X6700407 | ENGRS FLD OFC TY A D1 | 12 | CAL MO | $6,000.00 | $3,200.00 | $2,500.00 | $6,000.00 | $2,800.00 | |
| 5 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $71,680.00 | $125,500.00 | $19,350.00 | $70,000.00 | $270,000.00 | |
| 6 | X7830050 | RRPM REFLECTOR REMOVL | 154 | EACH | $10.00 | $20.00 | $20.00 | $11.00 | $12.00 | |
| 7 | X7830052 | RRPM REFLECTOR REPLAC | 154 | EACH | $17.60 | $20.00 | $15.00 | $17.00 | $20.00 | |
| 8 | Z0001700 | APPR SLAB REPAIR (FD) | 16 | SQ YD | $1,000.00 | $1,100.00 | $1,114.05 | $2,300.00 | $1,350.00 | |
| 9 | Z0006016 | BR DK LTX C OLY 2 3/4 | 1,871 | SQ YD | $120.00 | $128.00 | $150.00 | $175.00 | $172.00 | |
| 10 | Z0012130 | BR DECK SCAR 3/4 | 1,435 | SQ YD | $60.00 | $63.00 | $80.95 | $71.00 | $68.00 | |
| 11 | Z0012142 | BR DECK SCAR 2 1/4 | 449 | SQ YD | $60.00 | $63.00 | $86.45 | $134.00 | $92.00 | |
| 12 | Z0012754 | STR REP CON DP = < 5 | 127 | SQ FT | $200.00 | $195.00 | $185.65 | $202.00 | $350.00 | |
| 13 | Z0018051 | DRAINAGE SCUPPERS ADJ | 6 | EACH | $1,000.00 | $1,400.00 | $950.10 | $2,000.00 | $900.00 | |
| 14 | Z0029090 | DIAMOND GRIND BR SEC | 1,871 | SQ YD | $7.12 | $8.00 | $10.80 | $8.00 | $7.50 | |
| 15 | Z0030850 | TEMP INFO SIGNING | 72 | SQ FT | $30.00 | $15.00 | $18.00 | $13.00 | $22.00 | |
| 16 | Z0041895 | POLYMER CONCRETE | 25 | CU FT | $950.00 | $1,200.00 | $1,950.35 | $2,100.00 | $2,600.00 | |
| 17 | Z0065700 | SLOPE WALL REPAIR | 2 | SQ YD | $2,000.00 | $1,850.00 | $2,631.35 | $1,886.00 | $1,175.00 | |
| 18 | Z0073510 | TEMP TR SIGNAL TIMING | 1 | EACH | $880.00 | $1,500.00 | $800.00 | $922.00 | $800.00 | |
| 19 | 20200100 | EARTH EXCAVATION | 106 | CU YD | $50.00 | $83.00 | $28.20 | $149.00 | $81.00 | |
| 20 | 28100107 | STONE RIPRAP CL A4 | 578 | SQ YD | $75.00 | $85.00 | $128.85 | $147.00 | $215.00 | |
| 21 | 28200200 | FILTER FABRIC | 580 | SQ YD | $10.00 | $5.00 | $3.75 | $14.00 | $6.00 | |
| 22 | 40600290 | BIT MATLS TACK CT | 115 | POUND | $0.0100 | $1.00 | $3.00 | $0.1200 | $0.0100 | |
| 23 | 40600982 | HMA SURF REM BUTT JT | 580 | SQ YD | $0.0100 | $22.00 | $13.00 | $23.00 | $21.00 | |
| 24 | 40604172 | P HMA SC IL-9.5 E N70 | 26 | TON | $200.00 | $950.00 | $909.65 | $979.00 | $1,600.00 | |
| 25 | 44000157 | HMA SURF REM 2 | 469 | SQ YD | $8.00 | $42.00 | $6.70 | $43.00 | $32.00 | |
| 26 | 50102400 | CONC REM | 26.4 | CU YD | $2,000.00 | $2,400.00 | $1,486.35 | $2,500.00 | $3,100.00 | |
| 27 | 50104650 | SLOPE WALL REMOV | 578 | SQ YD | $60.00 | $115.00 | $173.15 | $65.00 | $74.00 | |
| 28 | 50157300 | PROTECTIVE SHIELD | 407 | SQ YD | $80.00 | $63.00 | $0.0100 | $164.00 | $1.00 | |
| 29 | 50201101 | COFFERDAM TYP 1 LOC 1 | 1 | EACH | $0.0100 | $36,000.00 | $60,606.85 | $20,000.00 | $1,000.00 | |
| 30 | 50300255 | CONC SUP-STR | 26.3 | CU YD | $2,500.00 | $2,560.00 | $3,279.05 | $5,000.00 | $3,700.00 | |
| 31 | 50300300 | PROTECTIVE COAT | 2,878 | SQ YD | $1.00 | $2.00 | $3.60 | $6.00 | $1.50 | |
| 32 | 50800205 | REINF BARS, EPOXY CTD | 2,970 | POUND | $4.50 | $5.00 | $4.00 | $2.75 | $4.00 | |
| 33 | 50800515 | BAR SPLICERS | 48 | EACH | $65.00 | $65.00 | $54.55 | $143.00 | $70.00 | |
| 34 | 52000110 | PREF JT STRIP SEAL | 184 | FOOT | $250.00 | $245.00 | $420.20 | $384.00 | $275.00 | |
| 35 | 54213663 | PRC FLAR END SEC 18 | 1 | EACH | $2,000.00 | $2,200.00 | $1,800.00 | $5,400.00 | $3,700.00 | |
| 36 | 63302700 | REM RE-E T B TERM T6 | 1 | EACH | $3,555.20 | $2,400.00 | $2,600.00 | $2,900.00 | $3,300.00 | |
| 37 | 66900200 | NON SPL WASTE DISPOSL | 110 | CU YD | $90.00 | $98.00 | $134.60 | $122.00 | $100.00 | |
| 38 | 66900530 | SOIL DISPOSAL ANALY | 2 | EACH | $1,650.00 | $1,600.00 | $1,480.00 | $1,936.00 | $1,000.00 | |
| 39 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,250.00 | $3,700.00 | $3,400.00 | $2,650.00 | $2,400.00 | |
| 40 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $2,250.00 | $600.00 | $500.00 | $2,420.00 | $2,100.00 | |
| 41 | 66901006 | REG SUB MON | 3 | CAL DA | $900.00 | $800.00 | $700.00 | $1,140.00 | $1,200.00 | |
| 42 | 67100100 | MOBILIZATION | 1 | L SUM | $69,500.00 | $82,000.00 | $83,700.00 | $101,000.00 | $90,000.00 | |
| 43 | 70107025 | CHANGEABLE MESSAGE SN | 268 | CAL DA | $50.00 | $33.00 | $30.00 | $34.00 | $32.00 | |
| 44 | 70300150 | SHRT TRM PAVT MK REM | 2,936 | SQ FT | $0.0100 | $1.00 | $0.6000 | $0.9000 | $0.6000 | |
| 45 | 70307100 | TEMP PVT MK LTR & SYM T4 TAPE | 256 | SQ FT | $0.0100 | $4.00 | $8.00 | $4.30 | $5.00 | |
| 46 | 70307120 | TEMP PVT MK L4 T4 TAPE | 12,006 | FOOT | $0.0100 | $1.20 | $1.35 | $1.20 | $1.30 | |
| 47 | 70307130 | TEMP PVT MK L6 T4 TAPE | 2,296 | FOOT | $0.0100 | $1.80 | $2.00 | $1.90 | $1.65 | |
| 48 | 70307160 | TEMP PVT MK L12 T4 TAPE | 184 | FOOT | $0.0100 | $3.60 | $4.00 | $3.80 | $4.00 | |
| 49 | 70307210 | TEMP PVT MK L24 T4 TAPE | 142 | FOOT | $0.0100 | $7.00 | $8.00 | $7.60 | $8.00 | |
| 50 | 70400100 | TEMP CONC BARRIER | 1,050 | FOOT | $30.00 | $32.00 | $32.05 | $40.00 | $23.00 | |
| 51 | 70400200 | REL TEMP CONC BARRIER | 950 | FOOT | $15.00 | $6.00 | $7.50 | $7.50 | $5.00 | |
| 52 | 70600255 | IMP ATTN TEMP FRN TL2 | 4 | EACH | $6,000.00 | $4,800.00 | $4,340.00 | $5,000.00 | $4,500.00 | |
| 53 | 70600322 | IMP ATTN REL FRN TL2 | 4 | EACH | $2,500.00 | $2,300.00 | $2,118.00 | $2,440.00 | $2,300.00 | |
| 54 | 78000100 | THPL PVT MK LTR & SYM | 256 | SQ FT | $6.33 | $6.00 | $4.00 | $4.60 | $6.00 | |
| 55 | 78000200 | THPL PVT MK LINE 4 | 10,228 | FOOT | $0.9400 | $1.00 | $0.7000 | $0.7000 | $1.00 | |
| 56 | 78000400 | THPL PVT MK LINE 6 | 2,224 | FOOT | $1.89 | $1.90 | $1.00 | $1.10 | $1.50 | |
| 57 | 78000600 | THPL PVT MK LINE 12 | 184 | FOOT | $3.65 | $3.60 | $2.00 | $2.30 | $3.00 | |
| 58 | 78000650 | THPL PVT MK LINE 24 | 142 | FOOT | $6.33 | $7.20 | $4.00 | $4.60 | $6.00 | |
| 59 | 78004635 | PREF PL PM TD STD L 7 | 130 | FOOT | $37.40 | $38.00 | $8.00 | $9.20 | $28.00 | |
| 60 | 78009004 | MOD URETH PM LINE 4 | 1,035 | FOOT | $7.65 | $7.70 | $4.50 | $5.10 | $6.00 | |
| 61 | 78009006 | MOD URETH PM LINE 6 | 73 | FOOT | $13.92 | $14.00 | $6.50 | $7.40 | $10.00 | |
| 62 | 78011040 | GRV RCSD PVT MRKG 8 | 129 | FOOT | $6.22 | $6.00 | $7.50 | $8.60 | $17.00 | |
| 63 | 78100100 | RAISED REFL PAVT MKR | 8 | EACH | $533.50 | $520.00 | $275.00 | $316.00 | $550.00 | |
| 64 | 78200011 | BARR WALL REF TYPE C | 38 | EACH | $26.97 | $10.00 | $15.00 | $9.00 | $15.00 | |
| 65 | 78300200 | RAISED REF PVT MK REM | 8 | EACH | $40.00 | $30.00 | $20.00 | $11.50 | $25.00 | |
| 66 | 78300202 | PVT MKG REM WTR BLAST | 5,584 | SQ FT | $3.30 | $0.0500 | $1.50 | $0.0600 | $1.25 |