2020-113-RS
- Let date
- Friday, June 11, 2021
- Contract
- 62L91 · job page
- District
- District 1
- County
- Cook
- Highway
- Limits
- (4.40-Mile) Smart overlay and ADA improvements project on IL 43 (Waukegan Rd.) from Ammer Rd. to Lake-Cook Rd. within the Villages of Glenview, Northfield, Northbrook and Deerfield. There is an omission within the project limits.
- Classification
- ·
- Project number
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Plote Construction, Inc. Low bidder | $3,981,000 | ||
| 2 | Peter Baker & Son Co. | $4,086,435 | +2.6% | |
| 3 | Arrow Road Construction Co. | $4,137,094 | +3.9% | |
| 4 | Builders Paving, LLC | $4,331,880 | +8.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Plote Construct… | #2 Peter Baker & S… | #3 Arrow Road Cons… | #4 Builders Paving… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $4,000.00 | $3,500.00 | $6,000.00 | $4,000.00 | |
| 2 | X0327036 | BIKE PATH REM | 108 | SQ YD | $25.00 | $18.00 | $21.00 | $15.00 | |
| 3 | X1700062 | BRICK PAVER REM & REP | 15 | SQ FT | $20.00 | $20.00 | $25.00 | $25.00 | |
| 4 | X2020110 | GRADING & SHAP SHLDRS | 209 | UNIT | $110.00 | $90.00 | $65.00 | $45.00 | |
| 5 | X2600011 | REM & REL SIGN PANEL | 2 | EACH | $600.00 | $150.00 | $150.00 | $160.00 | |
| 6 | X4400501 | COMB C&G REMOV REPL < = 10FT | 1,399 | FOOT | $38.00 | $38.00 | $38.00 | $41.00 | |
| 7 | X5537800 | SS CLEANED 12 | 540 | FOOT | $4.00 | $4.00 | $4.00 | $4.00 | |
| 8 | X6026050 | SANITARY MANHOLE ADJ | 1 | EACH | $1,000.00 | $1,000.00 | $1,000.00 | $1,050.00 | |
| 9 | X6030205 | FR & GRATES ADJUST SP | 5 | EACH | $550.00 | $550.00 | $550.00 | $560.00 | |
| 10 | X6030310 | FR & LIDS ADJUST SPL | 190 | EACH | $685.00 | $550.00 | $685.00 | $710.00 | |
| 11 | X7011015 | TR C-PROT EXPRESSWAYS | 1 | L SUM | $9,000.00 | $100.00 | $500.00 | $4,000.00 | |
| 12 | X7030005 | TEMP PAVT MKING REMOV | 43,497 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $0.3500 | |
| 13 | Z0001110 | GAS VALVE ADJUSTED | 1 | EACH | $385.00 | $385.00 | $385.00 | $400.00 | |
| 14 | Z0004562 | COMB C C&G REM & REPL | 2,544 | FOOT | $38.00 | $36.00 | $36.00 | $39.00 | |
| 15 | Z0018500 | DRAINAGE STR CLEANED | 90 | EACH | $350.00 | $350.00 | $350.00 | $350.00 | |
| 16 | Z0030850 | TEMP INFO SIGNING | 332 | SQ FT | $13.00 | $12.00 | $12.00 | $12.00 | |
| 17 | Z0033700 | LONG JOINT SEALANT | 85,053 | FOOT | $2.00 | $2.20 | $2.05 | $2.30 | |
| 18 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 19 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 20 | 20101200 | TREE ROOT PRUNING | 3 | EACH | $125.00 | $300.00 | $400.00 | $500.00 | |
| 21 | 20200100 | EARTH EXCAVATION | 181 | CU YD | $65.00 | $65.00 | $65.00 | $65.00 | |
| 22 | 21101615 | TOPSOIL F & P 4 | 1,217 | SQ YD | $7.50 | $4.95 | $4.95 | $5.00 | |
| 23 | 25200110 | SODDING SALT TOLERANT | 1,217 | SQ YD | $8.00 | $12.00 | $12.00 | $12.00 | |
| 24 | 25200200 | SUPPLE WATERING | 7 | UNIT | $10.00 | $50.00 | $50.00 | $50.00 | |
| 25 | 40600290 | BIT MATLS TACK CT | 72,467 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 26 | 40600400 | MIX CR JTS FLANGEWYS | 242 | TON | $250.00 | $300.00 | $100.00 | $500.00 | |
| 27 | 40600982 | HMA SURF REM BUTT JT | 1,006 | SQ YD | $10.00 | $1.00 | $5.50 | $19.00 | |
| 28 | 40601005 | HMA REPL OVER PATCH | 893 | TON | $75.00 | $100.00 | $45.00 | $95.00 | |
| 29 | 40604062 | HMA SC IL-9.5 D N70 | 244 | TON | $106.00 | $89.00 | $102.50 | $105.00 | |
| 30 | 40605026 | P HMA SC SMA 9.5 F N80 | 15,538 | TON | $106.00 | $102.00 | $102.50 | $100.00 | |
| 31 | 42001300 | PROTECTIVE COAT | 2,240 | SQ YD | $1.00 | $1.00 | $1.00 | $1.00 | |
| 32 | 42400200 | PC CONC SIDEWALK 5 | 13,790 | SQ FT | $7.00 | $7.00 | $7.00 | $7.10 | |
| 33 | 42400800 | DETECTABLE WARNINGS | 1,173 | SQ FT | $30.00 | $30.00 | $30.00 | $32.00 | |
| 34 | 44000156 | HMA SURF REM 1 3/4 | 161,037 | SQ YD | $2.25 | $4.25 | $3.00 | $2.75 | |
| 35 | 44000600 | SIDEWALK REM | 12,904 | SQ FT | $3.00 | $3.00 | $3.00 | $3.20 | |
| 36 | 44002212 | HMA RM OV PATCH 3 | 5,314 | SQ YD | $5.00 | $2.55 | $12.75 | $8.75 | |
| 37 | 44201753 | CL D PATCH T2 9 | 2,416 | SQ YD | $60.00 | $50.00 | $25.00 | $85.00 | |
| 38 | 44201757 | CL D PATCH T3 9 | 966 | SQ YD | $50.00 | $50.00 | $24.00 | $80.00 | |
| 39 | 44201759 | CL D PATCH T4 9 | 1,449 | SQ YD | $40.00 | $50.00 | $23.00 | $78.00 | |
| 40 | 48102100 | AGG WEDGE SHLD TYPE B | 661 | TON | $50.00 | $44.15 | $61.00 | $32.00 | |
| 41 | 60265700 | VV ADJUST | 2 | EACH | $450.00 | $450.00 | $450.00 | $460.00 | |
| 42 | 60266600 | VALVE BOX ADJ | 1 | EACH | $335.00 | $335.00 | $335.00 | $360.00 | |
| 43 | 60300305 | FR & LIDS ADJUST | 13 | EACH | $450.00 | $450.00 | $450.00 | $470.00 | |
| 44 | 66900200 | NON SPL WASTE DISPOSL | 181 | CU YD | $45.00 | $101.00 | $115.00 | $115.00 | |
| 45 | 66900530 | SOIL DISPOSAL ANALY | 15 | EACH | $1,650.00 | $1,800.00 | $1,600.00 | $1,330.00 | |
| 46 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,850.00 | $6,200.00 | $6,400.00 | $3,200.00 | |
| 47 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $1,200.00 | $1,000.00 | $500.00 | $2,500.00 | |
| 48 | 66901006 | REG SUB MON | 33 | CAL DA | $700.00 | $100.00 | $325.00 | $840.00 | |
| 49 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $3,800.00 | $2,000.00 | $2,500.00 | $2,900.00 | |
| 50 | 67100100 | MOBILIZATION | 1 | L SUM | $231,956.55 | $242,310.00 | $170,000.00 | $254,994.40 | |
| 51 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $100.00 | |
| 52 | 70102622 | TR CONT & PROT 701502 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $100.00 | |
| 53 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $126,300.00 | $48,360.00 | $495,000.00 | $130,000.00 | |
| 54 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $100.00 | |
| 55 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $100.00 | |
| 56 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $100.00 | |
| 57 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $2,000.00 | $1.00 | $1.00 | $100.00 | |
| 58 | 70107025 | CHANGEABLE MESSAGE SN | 8 | CAL DA | $85.00 | $60.00 | $60.00 | $65.00 | |
| 59 | 70200100 | NIGHT WORK ZONE LIGHT | 1 | L SUM | $2,000.00 | $100.00 | $500.00 | $1,000.00 | |
| 60 | 70300100 | SHORT TERM PAVT MKING | 14,429 | FOOT | $2.45 | $0.6000 | $0.4000 | $1.00 | |
| 61 | 70300150 | SHRT TRM PAVT MK REM | 4,810 | SQ FT | $0.0100 | $0.0100 | $1.50 | $0.0100 | |
| 62 | 70300210 | TEMP PVT MK LTR & SYM | 2,709 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $1.00 | |
| 63 | 70300220 | TEMP PVT MK LINE 4 | 80,159 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.2000 | |
| 64 | 70300240 | TEMP PVT MK LINE 6 | 14,129 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.3000 | |
| 65 | 70300250 | TEMP PVT MK LINE 8 | 915 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.6000 | |
| 66 | 70300260 | TEMP PVT MK LINE 12 | 3,324 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.8000 | |
| 67 | 70300280 | TEMP PVT MK LINE 24 | 1,535 | FOOT | $0.0100 | $0.0100 | $0.0100 | $1.20 | |
| 68 | 78000100 | THPL PVT MK LTR & SYM | 2,709 | SQ FT | $4.00 | $4.00 | $4.00 | $5.00 | |
| 69 | 78000200 | THPL PVT MK LINE 4 | 80,159 | FOOT | $0.5500 | $0.5500 | $0.5500 | $0.7500 | |
| 70 | 78000400 | THPL PVT MK LINE 6 | 14,129 | FOOT | $0.7500 | $0.7500 | $0.7500 | $1.12 | |
| 71 | 78000500 | THPL PVT MK LINE 8 | 915 | FOOT | $1.00 | $1.00 | $1.00 | $1.50 | |
| 72 | 78000600 | THPL PVT MK LINE 12 | 3,324 | FOOT | $1.50 | $1.50 | $1.50 | $2.25 | |
| 73 | 78000650 | THPL PVT MK LINE 24 | 1,535 | FOOT | $4.00 | $4.00 | $4.00 | $5.00 | |
| 74 | 78100100 | RAISED REFL PAVT MKR | 2,104 | EACH | $21.00 | $21.00 | $21.00 | $25.00 | |
| 75 | 78300200 | RAISED REF PVT MK REM | 2,104 | EACH | $10.00 | $10.00 | $4.50 | $15.00 | |
| 76 | 78300202 | PAVMT MRKG REM WTR BL | 363 | SQ FT | $5.00 | $10.00 | $15.00 | $10.00 | |
| 77 | 85000200 | MAIN EX TR SIG INSTAL | 1 | EACH | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 | |
| 78 | 88600600 | DET LOOP REPL | 5,370 | FOOT | $16.50 | $16.50 | $16.50 | $16.50 | |
| 79 | 89502376 | REBUILD EX HANDHOLE | 2 | EACH | $2,200.00 | $2,200.00 | $2,200.00 | $2,300.00 |