2019-068-RS&SW
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Gallagher Asphalt Corporation Low bidder | $2,478,606 | ||
| 2 | K-Five Construction Corporation | $2,568,834 | +3.6% | |
| 3 | MAT Construction Leasing, Inc. | $2,638,792 | +6.5% | |
| 4 | Bigane Paving Company | $2,656,766 | +7.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Gallagher Aspha… | #2 K-Five Construc… | #3 MAT Constructio… | #4 Bigane Paving C… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $4,700.00 | $25,000.00 | $3,500.00 | $6,980.00 | |
| 2 | X2800001 | IMPRTD THPL CROSSWALK | 125 | SQ YD | $150.00 | $144.00 | $144.00 | $144.00 | |
| 3 | X4240800 | DETECTABLE WARN SPL | 400 | SQ FT | $31.00 | $32.00 | $31.00 | $31.00 | |
| 4 | X4401198 | HMA SURF REM VAR DP | 13,858 | SQ YD | $2.50 | $3.00 | $3.10 | $3.75 | |
| 5 | X5537800 | SS CLEANED 12 | 600 | FOOT | $2.00 | $3.25 | $3.00 | $3.00 | |
| 6 | X7030005 | TEMP PAVT MKING REMOV | 25,150 | SQ FT | $0.0100 | $0.0100 | $0.7500 | $0.3900 | |
| 7 | Z0004562 | COMB C C&G REM & REPL | 950 | FOOT | $32.00 | $33.00 | $32.00 | $32.00 | |
| 8 | Z0018500 | DRAINAGE STR CLEANED | 45 | EACH | $300.00 | $290.00 | $300.00 | $325.00 | |
| 9 | Z0030850 | TEMP INFO SIGNING | 102.8 | SQ FT | $16.00 | $21.00 | $16.00 | $15.00 | |
| 10 | Z0033700 | LONG JOINT SEALANT | 29,500 | FOOT | $2.40 | $2.75 | $2.15 | $2.15 | |
| 11 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $6,000.00 | $15,000.00 | $6,000.00 | $5,000.00 | |
| 12 | 20200100 | EARTH EXCAVATION | 1,020 | CU YD | $35.00 | $45.00 | $65.00 | $70.00 | |
| 13 | 21101615 | TOPSOIL F & P 4 | 100 | SQ YD | $15.00 | $20.00 | $15.00 | $15.00 | |
| 14 | 25200200 | SUPPLE WATERING | 1 | UNIT | $150.00 | $250.00 | $150.00 | $150.00 | |
| 15 | 30300001 | AGG SUBGRADE IMPROVE | 1,995 | CU YD | $40.00 | $0.0100 | $33.00 | $58.00 | |
| 16 | 40600290 | BIT MATLS TACK CT | 37,380 | POUND | $0.0100 | $0.0100 | $0.5500 | $0.7500 | |
| 17 | 40600400 | MIX CR JTS FLANGEWYS | 85 | TON | $325.00 | $100.00 | $150.00 | $150.00 | |
| 18 | 40600982 | HMA SURF REM BUTT JT | 625 | SQ YD | $16.00 | $20.00 | $4.20 | $18.00 | |
| 19 | 40602985 | HMA BC IL-9.5 N70 | 4,627 | TON | $70.00 | $100.00 | $85.50 | $74.00 | |
| 20 | 40604062 | HMA SC IL-9.5 D N70 | 6,085 | TON | $85.00 | $103.00 | $84.00 | $74.00 | |
| 21 | 42001300 | PROTECTIVE COAT | 150 | SQ YD | $2.00 | $3.00 | $2.00 | $2.00 | |
| 22 | 42300400 | PCC DRIVEWAY PAVT 8 | 50 | SQ YD | $74.00 | $75.00 | $74.00 | $74.00 | |
| 23 | 42400200 | PC CONC SIDEWALK 5 | 4,030 | SQ FT | $6.25 | $6.50 | $6.25 | $6.25 | |
| 24 | 42400410 | PC CONC SIDEWALK 8 | 470 | SQ FT | $6.00 | $6.25 | $6.00 | $6.00 | |
| 25 | 44000164 | HMA SURF REM 3 3/4 | 41,307 | SQ YD | $3.95 | $8.00 | $4.20 | $4.00 | |
| 26 | 44000200 | DRIVE PAVEMENT REM | 50 | SQ YD | $22.00 | $23.00 | $22.00 | $22.00 | |
| 27 | 44000600 | SIDEWALK REM | 4,590 | SQ FT | $2.00 | $2.25 | $2.00 | $2.00 | |
| 28 | 44002215 | HMA RM OV PATCH 3 3/4 | 2,600 | SQ YD | $5.35 | $1.00 | $4.20 | $10.00 | |
| 29 | 44201773 | CL D PATCH T1 11 | 600 | SQ YD | $100.00 | $40.00 | $100.00 | $70.00 | |
| 30 | 44201777 | CL D PATCH T2 11 | 700 | SQ YD | $70.00 | $40.00 | $98.00 | $80.00 | |
| 31 | 44201781 | CL D PATCH T3 11 | 700 | SQ YD | $65.00 | $40.00 | $96.00 | $90.00 | |
| 32 | 44201783 | CL D PATCH T4 11 | 600 | SQ YD | $60.00 | $40.00 | $94.00 | $100.00 | |
| 33 | 44201796 | CL D PATCH T4 12 | 6,000 | SQ YD | $60.00 | $40.00 | $83.00 | $72.00 | |
| 34 | 60250200 | CB ADJUST | 20 | EACH | $285.00 | $350.00 | $325.00 | $325.00 | |
| 35 | 60252800 | CB RECONST | 2 | EACH | $975.00 | $1,900.00 | $1,800.00 | $1,800.00 | |
| 36 | 60255500 | MAN ADJUST | 7 | EACH | $430.00 | $550.00 | $500.00 | $500.00 | |
| 37 | 60257900 | MAN RECONST | 5 | EACH | $975.00 | $1,850.00 | $1,800.00 | $1,800.00 | |
| 38 | 60260100 | INLETS ADJUST | 10 | EACH | $265.00 | $350.00 | $325.00 | $325.00 | |
| 39 | 60300305 | FR & LIDS ADJUST | 25 | EACH | $430.00 | $550.00 | $500.00 | $500.00 | |
| 40 | 60406000 | FR & LIDS T1 OL | 4 | EACH | $265.00 | $350.00 | $325.00 | $325.00 | |
| 41 | 60406100 | FR & LIDS T1 CL | 3 | EACH | $265.00 | $350.00 | $325.00 | $325.00 | |
| 42 | 66900200 | NON SPL WASTE DISPOSL | 1,020 | CU YD | $81.00 | $10.00 | $70.00 | $65.00 | |
| 43 | 66900530 | SOIL DISPOSAL ANALY | 10 | EACH | $1,350.00 | $1,250.00 | $1,250.00 | $1,350.00 | |
| 44 | 66901001 | REG SUB P-CONST PLAN | 1 | LSUM | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | |
| 45 | 66901003 | REG SUB F CON REPORT | 1 | LSUM | $2,000.00 | $2,500.00 | $2,250.00 | $2,000.00 | |
| 46 | 66901006 | REG SUB MON | 11 | CAL DA | $800.00 | $1,000.00 | $720.00 | $800.00 | |
| 47 | 67000400 | ENGR FIELD OFFICE A | 9 | CAL MO | $1,500.00 | $3,800.00 | $1,500.00 | $3,000.00 | |
| 48 | 67100100 | MOBILIZATION | 1 | L SUM | $175,000.00 | $173,000.00 | $50,000.00 | $148,000.00 | |
| 49 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $1.00 | $10,000.00 | $11,800.00 | $1.00 | |
| 50 | 70102622 | TR CONT & PROT 701502 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | |
| 51 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $123,200.00 | $55,000.00 | $1.00 | $19,000.00 | |
| 52 | 70102634 | TR CONT & PROT 701611 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | |
| 53 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | |
| 54 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1,200.00 | $10,000.00 | $1.00 | $1.00 | |
| 55 | 70300100 | SHORT TERM PAVT MKING | 64,750 | FOOT | $0.0100 | $0.0100 | $0.7500 | $1.00 | |
| 56 | 70300150 | SHRT TRM PAVT MK REM | 21,583 | SQ FT | $0.0100 | $0.0100 | $0.7500 | $2.00 | |
| 57 | 70300210 | TEMP PVT MK LTR & SYM | 995.9 | SQ FT | $0.0100 | $0.0100 | $1.20 | $1.00 | |
| 58 | 70300220 | TEMP PVT MK LINE 4 | 18,950 | FOOT | $0.0100 | $0.0100 | $0.3500 | $0.1000 | |
| 59 | 70300240 | TEMP PVT MK LINE 6 | 3,385 | FOOT | $0.0100 | $0.0100 | $0.5000 | $0.2000 | |
| 60 | 70300260 | TEMP PVT MK LINE 12 | 345 | FOOT | $0.0100 | $0.0100 | $1.00 | $0.3000 | |
| 61 | 70300280 | TEMP PVT MK LINE 24 | 5,510 | FOOT | $0.0100 | $0.0100 | $1.50 | $1.00 | |
| 62 | 70300520 | PAVT MARK TAPE T3 4 | 16,155 | FOOT | $0.0100 | $0.0100 | $0.9500 | $0.8500 | |
| 63 | 78000100 | THPL PVT MK LTR & SYM | 995.9 | SQ FT | $4.00 | $4.00 | $4.00 | $4.00 | |
| 64 | 78000200 | THPL PVT MK LINE 4 | 18,950 | FOOT | $0.5000 | $0.5000 | $0.5000 | $0.5000 | |
| 65 | 78000400 | THPL PVT MK LINE 6 | 3,385 | FOOT | $0.7500 | $0.7500 | $0.7500 | $0.7500 | |
| 66 | 78000600 | THPL PVT MK LINE 12 | 345 | FOOT | $1.50 | $1.50 | $1.50 | $1.50 | |
| 67 | 78000650 | THPL PVT MK LINE 24 | 5,510 | FOOT | $4.00 | $4.00 | $4.00 | $4.00 | |
| 68 | 78100100 | RAISED REFL PAVT MKR | 510 | EACH | $23.50 | $23.50 | $23.40 | $23.50 | |
| 69 | 78300200 | RAISED REF PVT MK REM | 300 | EACH | $10.00 | $10.00 | $5.00 | $5.00 | |
| 70 | 85000200 | MAIN EX TR SIG INSTAL | 2 | EACH | $2,200.00 | $10,000.00 | $2,200.00 | $2,200.00 | |
| 71 | 88600600 | DET LOOP REPL | 250 | FOOT | $18.00 | $20.00 | $18.00 | $18.00 | |
| 72 | 89500400 | RELOC EX PED PUSH-BUT | 2 | EACH | $410.00 | $425.00 | $410.00 | $410.00 |