561RS-4
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | R. W. Dunteman Company Low bidder | $1,111,370 | ||
| 2 | K-Five Construction Corporation | $1,195,987 | +7.6% | |
| 3 | Plote Construction, Inc. | $1,315,842 | +18.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 R. W. Dunteman … | #2 K-Five Construc… | #3 Plote Construct… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $11,000.00 | $10,000.00 | $15,000.00 | |
| 2 | X0327611 | REM & REIN BRIC PAVER | 11 | SQ FT | $20.00 | $70.00 | $25.00 | |
| 3 | X2020110 | GRADING & SHAP SHLDRS | 44 | UNIT | $104.68 | $65.00 | $450.00 | |
| 4 | X5537800 | SS CLEANED 12 | 200 | FOOT | $3.00 | $2.50 | $3.00 | |
| 5 | X6030310 | FR & LIDS ADJUST SPL | 48 | EACH | $600.00 | $700.00 | $600.00 | |
| 6 | X7030005 | TEMP PAVT MKING REMOV | 1,874 | SQ FT | $0.1500 | $0.1500 | $0.0100 | |
| 7 | X8950205 | REBLD EX HANDHOLE SPL | 1 | EACH | $3,000.00 | $3,000.00 | $3,000.00 | |
| 8 | Z0004538 | HMA DRIVEWAY PAVT 10 | 1 | SQ YD | $793.40 | $500.00 | $100.00 | |
| 9 | Z0004562 | COMB C C&G REM & REPL | 1,600 | FOOT | $32.62 | $31.00 | $35.00 | |
| 10 | Z0018500 | DRAINAGE STR CLEANED | 5 | EACH | $306.00 | $400.00 | $306.00 | |
| 11 | Z0030850 | TEMP INFO SIGNING | 102.8 | SQ FT | $15.00 | $15.00 | $15.00 | |
| 12 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $4,000.00 | $5,000.00 | $6,500.00 | |
| 13 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 14 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 15 | 20200100 | EARTH EXCAVATION | 63 | CU YD | $60.71 | $140.00 | $46.00 | |
| 16 | 21101615 | TOPSOIL F & P 4 | 565 | SQ YD | $8.98 | $9.00 | $9.00 | |
| 17 | 25000400 | NITROGEN FERT NUTR | 8 | POUND | $4.00 | $4.00 | $4.00 | |
| 18 | 25000500 | PHOSPHORUS FERT NUTR | 8 | POUND | $4.00 | $4.00 | $4.00 | |
| 19 | 25000600 | POTASSIUM FERT NUTR | 8 | POUND | $4.00 | $4.00 | $4.00 | |
| 20 | 25200110 | SODDING SALT TOLERANT | 565 | SQ YD | $13.50 | $13.50 | $14.00 | |
| 21 | 25200200 | SUPPLE WATERING | 25 | UNIT | $75.00 | $75.00 | $40.00 | |
| 22 | 40600295 | P BIT MATLS TACK CT | 32,514 | POUND | $0.0100 | $0.0100 | $0.0100 | |
| 23 | 40600400 | MIX CR JTS FLANGEWYS | 90 | TON | $75.00 | $50.00 | $50.00 | |
| 24 | 40600827 | P LB MM IL-4.75 N50 | 1,850 | TON | $84.19 | $78.00 | $85.00 | |
| 25 | 40600982 | HMA SURF REM BUTT JT | 648 | SQ YD | $13.21 | $12.00 | $20.00 | |
| 26 | 40603340 | HMA SC "D" N70 | 3,764 | TON | $66.85 | $88.00 | $70.00 | |
| 27 | 40800050 | INCIDENTAL HMA SURF | 425 | TON | $84.46 | $88.00 | $86.00 | |
| 28 | 42001300 | PROTECTIVE COAT | 1,096 | SQ YD | $1.02 | $1.00 | $1.00 | |
| 29 | 42400200 | PC CONC SIDEWALK 5 | 6,657 | SQ FT | $6.63 | $6.25 | $6.65 | |
| 30 | 42400800 | DETECTABLE WARNINGS | 620 | SQ FT | $28.56 | $27.00 | $29.00 | |
| 31 | 44000155 | HMA SURF REM 1 1/2 | 5,052 | SQ YD | $3.14 | $2.00 | $5.15 | |
| 32 | 44000158 | HMA SURF REM 2 1/4 | 44,801 | SQ YD | $2.46 | $0.0100 | $0.0100 | |
| 33 | 44000159 | HMA SURF REM 2 1/2 | 44,801 | SQ YD | $0.0100 | $0.0100 | $0.0100 | |
| 34 | 44000200 | DRIVE PAVEMENT REM | 10 | SQ YD | $51.81 | $75.00 | $18.00 | |
| 35 | 44000600 | SIDEWALK REM | 6,692 | SQ FT | $2.53 | $2.20 | $2.15 | |
| 36 | 44201803 | CL D PATCH T2 13 | 227 | SQ YD | $109.20 | $50.00 | $145.00 | |
| 37 | 44201807 | CL D PATCH T3 13 | 220 | SQ YD | $97.65 | $50.00 | $140.00 | |
| 38 | 44201809 | CL D PATCH T4 13 | 420 | SQ YD | $90.88 | $50.00 | $135.00 | |
| 39 | 48102100 | AGG WEDGE SHLD TYPE B | 85 | TON | $70.54 | $80.00 | $16.00 | |
| 40 | 60250400 | CB ADJ NEW T1F OL | 3 | EACH | $625.00 | $700.00 | $625.00 | |
| 41 | 60252800 | CB RECONST | 1 | EACH | $1,000.00 | $1,300.00 | $1,000.00 | |
| 42 | 60255500 | MAN ADJUST | 35 | EACH | $400.00 | $400.00 | $400.00 | |
| 43 | 60266600 | VALVE BOX ADJ | 5 | EACH | $180.00 | $180.00 | $180.00 | |
| 44 | 60300105 | FR & GRATES ADJUST | 3 | EACH | $375.00 | $400.00 | $375.00 | |
| 45 | 60300305 | FR & LIDS ADJUST | 44 | EACH | $325.00 | $380.00 | $325.00 | |
| 46 | 60404940 | FR & GRATES T23 | 2 | EACH | $350.00 | $450.00 | $350.00 | |
| 47 | 60406000 | FR & LIDS T1 OL | 1 | EACH | $310.00 | $400.00 | $310.00 | |
| 48 | 60406100 | FR & LIDS T1 CL | 1 | EACH | $310.00 | $400.00 | $310.00 | |
| 49 | 66900200 | NON SPL WASTE DISPOSL | 63 | CU YD | $65.00 | $0.0100 | $65.00 | |
| 50 | 66900450 | SPL WASTE PLNS/REPORT | 1 | L SUM | $3,000.00 | $3,000.00 | $3,000.00 | |
| 51 | 66900530 | SOIL DISPOSAL ANALY | 4 | EACH | $1,400.00 | $1,400.00 | $1,400.00 | |
| 52 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $1,500.00 | $3,300.00 | $3,000.00 | |
| 53 | 67100100 | MOBILIZATION | 1 | L SUM | $66,660.00 | $189,850.00 | $78,775.00 | |
| 54 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $15,000.00 | $51,700.00 | $211,000.00 | |
| 55 | 70102626 | TR CONT & PROT 701606 | 1 | EACH | $1.00 | $1.00 | $1.00 | |
| 56 | 70102631 | TR CONT & PROT 701601 | 1 | EACH | $1.00 | $1.00 | $1.00 | |
| 57 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.00 | $1.00 | |
| 58 | 70102642 | TR CONT & PROT 701801 | 1 | EACH | $3,200.00 | $3,200.00 | $35,000.00 | |
| 59 | 70300100 | SHORT TERM PAVT MKING | 8,902 | FOOT | $0.0100 | $1.00 | $0.0100 | |
| 60 | 70300150 | SHRT TRM PAVT MK REM | 3,750 | SQ FT | $0.0100 | $2.00 | $0.0100 | |
| 61 | 70300210 | TEMP PVT MK LTR & SYM | 410 | SQ FT | $1.00 | $0.0100 | $0.0100 | |
| 62 | 70300220 | TEMP PVT MK LINE 4 | 35,515 | FOOT | $0.2000 | $0.0100 | $0.0100 | |
| 63 | 70300240 | TEMP PVT MK LINE 6 | 1,430 | FOOT | $0.3000 | $0.0100 | $0.0100 | |
| 64 | 70300250 | TEMP PVT MK LINE 8 | 225 | FOOT | $0.4000 | $0.0100 | $0.0100 | |
| 65 | 70300260 | TEMP PVT MK LINE 12 | 420 | FOOT | $0.7500 | $0.0100 | $0.0100 | |
| 66 | 70300280 | TEMP PVT MK LINE 24 | 255 | FOOT | $1.00 | $0.0100 | $0.0100 | |
| 67 | 70300520 | PAVT MARK TAPE T3 4 | 4,451 | FOOT | $0.4500 | $0.4500 | $0.0100 | |
| 68 | 72400310 | REMOV SIGN PANEL T1 | 27 | SQ FT | $9.00 | $9.00 | $9.00 | |
| 69 | 72400710 | RELOC SIGN PANEL T1 | 27 | SQ FT | $10.00 | $10.00 | $10.00 | |
| 70 | 78000100 | THPL PVT MK LTR & SYM | 410 | SQ FT | $3.70 | $3.25 | $3.70 | |
| 71 | 78000200 | THPL PVT MK LINE 4 | 35,515 | FOOT | $0.5300 | $0.5000 | $0.5300 | |
| 72 | 78000400 | THPL PVT MK LINE 6 | 1,430 | FOOT | $0.7900 | $0.7500 | $0.7900 | |
| 73 | 78000500 | THPL PVT MK LINE 8 | 225 | FOOT | $1.05 | $1.00 | $1.05 | |
| 74 | 78000600 | THPL PVT MK LINE 12 | 420 | FOOT | $1.80 | $1.50 | $1.80 | |
| 75 | 78000650 | THPL PVT MK LINE 24 | 255 | FOOT | $4.00 | $3.25 | $4.00 | |
| 76 | 78100100 | RAISED REFL PAVT MKR | 760 | EACH | $24.00 | $22.50 | $24.00 | |
| 77 | 78300200 | RAISED REF PVT MK REM | 464 | EACH | $13.93 | $9.45 | $8.00 | |
| 78 | 85000200 | MAIN EX TR SIG INSTAL | 1 | EACH | $2,500.00 | $2,500.00 | $2,500.00 | |
| 79 | 88600600 | DET LOOP REPL | 651 | FOOT | $17.00 | $17.00 | $17.00 | |
| 80 | 89500400 | RELOC EX PED PUSH-BUT | 6 | EACH | $310.00 | $310.00 | $310.00 | |
| 81 | 89502376 | REBUILD EX HANDHOLE | 2 | EACH | $2,100.00 | $2,100.00 | $2,100.00 |