(3076-1 & 3077)RS-1
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D. Construction, Inc. Low bidder | $1,892,784 | ||
| 2 | Iroquois Paving Corporation | $1,899,725 | +0.4% | |
| 3 | Gallagher Asphalt Corporation | $1,977,000 | +4.4% | |
| 4 | K-Five Construction Corporation | $2,058,698 | +8.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D. Construction… | #2 Iroquois Paving… | #3 Gallagher Aspha… | #4 K-Five Construc… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $10,000.00 | $9,650.00 | $6,400.00 | $4,800.00 | |
| 2 | X2010350 | TREE REMOV ACRES SPL | 0.8 | ACRE | $4,950.00 | $3,500.00 | $4,500.00 | $3,500.00 | |
| 3 | X2020110 | GRADING & SHAP SHLDRS | 167 | UNIT | $40.00 | $10.15 | $51.00 | $45.00 | |
| 4 | X2502014 | SEEDING CL 4A MOD | 0.8 | ACRE | $4,654.10 | $2,450.00 | $2,450.00 | $2,450.00 | |
| 5 | X5420608 | PIPE CULV CLEANED 8 | 20 | FOOT | $11.00 | $2.00 | $10.00 | $10.00 | |
| 6 | X5420612 | PIPE CULV CLEANED 12 | 110 | FOOT | $4.40 | $2.25 | $4.00 | $4.00 | |
| 7 | X5420615 | PIPE CULV CLEANED 15 | 70 | FOOT | $4.40 | $2.50 | $4.00 | $4.00 | |
| 8 | X5420624 | PIPE CULV CLEANED 24 | 161 | FOOT | $5.50 | $3.00 | $5.00 | $5.00 | |
| 9 | X5537800 | SS CLEANED 12 | 300 | FOOT | $2.20 | $2.25 | $2.00 | $2.00 | |
| 10 | X5537900 | SS CLEANED 15 | 1,600 | FOOT | $3.30 | $2.50 | $3.00 | $3.00 | |
| 11 | X5538000 | SS CLEANED 18 | 300 | FOOT | $4.40 | $3.00 | $4.00 | $4.00 | |
| 12 | X5538200 | SS CLEANED 24 | 300 | FOOT | $5.50 | $3.00 | $5.00 | $5.00 | |
| 13 | X6026624 | VALVE BOX ADJ SPL | 4 | EACH | $660.00 | $375.00 | $305.00 | $600.00 | |
| 14 | X6030310 | FR & LIDS ADJUST SPL | 59 | EACH | $700.00 | $645.00 | $600.00 | $700.00 | |
| 15 | X7030005 | TEMP PAVT MKING REMOV | 23,202 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 16 | Z0004562 | COMB C C&G REM & REPL | 3,862 | FOOT | $39.60 | $40.50 | $30.00 | $36.00 | |
| 17 | Z0018500 | DRAINAGE STR CLEANED | 96 | EACH | $242.00 | $237.00 | $220.00 | $220.00 | |
| 18 | Z0030850 | TEMP INFO SIGNING | 52 | SQ FT | $25.00 | $18.00 | $13.50 | $18.00 | |
| 19 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $3,500.00 | $5,125.00 | $3,800.00 | $3,000.00 | |
| 20 | Z0064800 | SELECTIVE CLEARING | 49 | UNIT | $313.50 | $50.00 | $285.00 | $50.00 | |
| 21 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 22 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 23 | 20100110 | TREE REMOV 6-15 | 75 | UNIT | $13.20 | $25.00 | $12.00 | $25.00 | |
| 24 | 20100210 | TREE REMOV OVER 15 | 18 | UNIT | $15.40 | $30.00 | $14.00 | $30.00 | |
| 25 | 20101300 | TREE PRUN 1-10 | 15 | EACH | $22.00 | $225.00 | $20.00 | $150.00 | |
| 26 | 20101350 | TREE PRUN OVER 10 | 15 | EACH | $33.00 | $245.00 | $30.00 | $165.00 | |
| 27 | 20200100 | EARTH EXCAVATION | 41 | CU YD | $71.50 | $50.00 | $46.00 | $65.00 | |
| 28 | 21101505 | TOPSOIL EXC & PLAC | 30 | CU YD | $94.60 | $45.00 | $45.00 | $45.00 | |
| 29 | 25000400 | NITROGEN FERT NUTR | 76 | POUND | $3.30 | $3.00 | $3.00 | $3.00 | |
| 30 | 25000500 | PHOSPHORUS FERT NUTR | 76 | POUND | $3.30 | $3.00 | $3.00 | $3.00 | |
| 31 | 25000600 | POTASSIUM FERT NUTR | 76 | POUND | $3.30 | $3.00 | $3.00 | $3.00 | |
| 32 | 25100115 | MULCH METHOD 2 | 0.8 | ACRE | $2,161.50 | $1,800.00 | $1,800.00 | $1,800.00 | |
| 33 | 25200110 | SODDING SALT TOLERANT | 265 | SQ YD | $7.70 | $10.00 | $10.00 | $10.00 | |
| 34 | 35501316 | HMA BASE CSE 8 | 57 | SQ YD | $55.00 | $46.00 | $77.00 | $78.00 | |
| 35 | 40600290 | BIT MATLS TACK CT | 49,510 | POUND | $0.0100 | $0.5000 | $0.0100 | $0.0100 | |
| 36 | 40600400 | MIX CR JTS FLANGEWYS | 109 | TON | $0.0100 | $0.0100 | $295.00 | $15.00 | |
| 37 | 40600827 | P LB MM IL-4.75 N50 | 3,002 | TON | $70.00 | $88.50 | $90.00 | $103.00 | |
| 38 | 40600982 | HMA SURF REM BUTT JT | 432 | SQ YD | $10.00 | $14.50 | $9.70 | $5.00 | |
| 39 | 40603335 | HMA SC "D" N50 | 6 | TON | $200.00 | $201.00 | $225.00 | $250.00 | |
| 40 | 40603565 | P HMA SC "E" N70 | 7,131 | TON | $60.00 | $74.50 | $74.60 | $93.75 | |
| 41 | 42001300 | PROTECTIVE COAT | 1,495 | SQ YD | $1.10 | $1.00 | $0.8000 | $0.0100 | |
| 42 | 42400200 | PC CONC SIDEWALK 5 | 7,767 | SQ FT | $8.25 | $7.40 | $6.00 | $7.50 | |
| 43 | 42400800 | DETECTABLE WARNINGS | 383 | SQ FT | $33.00 | $26.00 | $30.00 | $30.00 | |
| 44 | 44000159 | HMA SURF REM 2 1/2 | 72,763 | SQ YD | $2.65 | $1.25 | $1.65 | $2.51 | |
| 45 | 44000200 | DRIVE PAVEMENT REM | 57 | SQ YD | $27.50 | $13.50 | $48.00 | $25.00 | |
| 46 | 44000600 | SIDEWALK REM | 7,118 | SQ FT | $2.20 | $1.70 | $1.75 | $2.00 | |
| 47 | 44201789 | CL D PATCH T2 12 | 840 | SQ YD | $80.00 | $55.00 | $128.00 | $30.00 | |
| 48 | 44201794 | CL D PATCH T3 12 | 483 | SQ YD | $72.00 | $50.00 | $96.00 | $30.00 | |
| 49 | 44201796 | CL D PATCH T4 12 | 2,612 | SQ YD | $66.00 | $45.00 | $88.00 | $30.00 | |
| 50 | 48102100 | AGG WEDGE SHLD TYPE B | 668 | TON | $25.00 | $22.00 | $24.35 | $30.00 | |
| 51 | 60266600 | VALVE BOX ADJ | 4 | EACH | $330.00 | $245.00 | $200.00 | $300.00 | |
| 52 | 60300305 | FR & LIDS ADJUST | 3 | EACH | $440.00 | $445.00 | $450.00 | $400.00 | |
| 53 | 60406000 | FR & LIDS T1 OL | 1 | EACH | $385.00 | $365.00 | $350.00 | $350.00 | |
| 54 | 60406100 | FR & LIDS T1 CL | 1 | EACH | $385.00 | $365.00 | $350.00 | $350.00 | |
| 55 | 63100167 | TR BAR TRM T1 SPL TAN | 2 | EACH | $4,248.24 | $3,200.00 | $3,600.00 | $3,200.00 | |
| 56 | 63200310 | GUARDRAIL REMOV | 100 | FOOT | $12.51 | $12.75 | $8.00 | $7.00 | |
| 57 | 66900200 | NON SPL WASTE DISPOSL | 41 | CU YD | $110.00 | $86.00 | $86.00 | $50.00 | |
| 58 | 66900530 | SOIL DISPOSAL ANALY | 1 | EACH | $1,650.00 | $1,450.00 | $1,450.00 | $1,600.00 | |
| 59 | 66901001 | REG SUB P-CONST PLAN | 1 | LSUM | $2,640.00 | $2,100.00 | $2,100.00 | $2,321.38 | |
| 60 | 66901002 | ON-SITE MON REG SUB | 3 | CAL DA | $1,045.00 | $800.00 | $800.00 | $800.00 | |
| 61 | 66901003 | REG SUB F CON REPORT | 1 | LSUM | $2,640.00 | $1,800.00 | $1,800.00 | $1,989.76 | |
| 62 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $3,000.00 | $2,500.00 | $3,000.00 | $2,500.00 | |
| 63 | 67100100 | MOBILIZATION | 1 | L SUM | $50,000.00 | $105,000.00 | $72,910.08 | $124,000.00 | |
| 64 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $0.0100 | $1.00 | $1.00 | $1.00 | |
| 65 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $0.0100 | $1.00 | $1.00 | $1.00 | |
| 66 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $0.0100 | $8,550.00 | $3,200.00 | $20,000.00 | |
| 67 | 70102622 | TR CONT & PROT 701502 | 1 | L SUM | $0.0100 | $1.00 | $1.00 | $1.00 | |
| 68 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $0.0100 | $1.00 | $1.00 | $1.00 | |
| 69 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $0.0100 | $125,400.00 | $10,500.00 | $10,000.00 | |
| 70 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $0.0100 | $1.00 | $1.00 | $1.00 | |
| 71 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $135,000.00 | $4,000.00 | $2,000.00 | $10,000.00 | |
| 72 | 70300100 | SHORT TERM PAVT MKING | 27,672 | FOOT | $0.0100 | $0.0100 | $0.4000 | $1.25 | |
| 73 | 70300150 | SHRT TRM PAVT MK REM | 9,224 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $1.00 | |
| 74 | 70300210 | TEMP PVT MK LTR & SYM | 819 | SQ FT | $0.0100 | $0.0100 | $2.25 | $0.0100 | |
| 75 | 70300220 | TEMP PVT MK LINE 4 | 53,917 | FOOT | $0.0100 | $0.0100 | $0.1000 | $0.0100 | |
| 76 | 70300240 | TEMP PVT MK LINE 6 | 4,117 | FOOT | $0.0100 | $0.0100 | $0.1000 | $0.0100 | |
| 77 | 70300260 | TEMP PVT MK LINE 12 | 626 | FOOT | $0.0100 | $0.0100 | $0.1000 | $0.0100 | |
| 78 | 70300280 | TEMP PVT MK LINE 24 | 582 | FOOT | $0.0100 | $0.0100 | $2.25 | $0.0100 | |
| 79 | 70300520 | PAVT MARK TAPE T3 4 | 6,918 | FOOT | $0.0100 | $1.50 | $1.20 | $1.70 | |
| 80 | 72501000 | TERMINAL MARKER - DA | 2 | EACH | $52.78 | $50.00 | $30.00 | $50.00 | |
| 81 | 78000100 | THPL PVT MK LTR & SYM | 819 | SQ FT | $4.40 | $4.00 | $4.25 | $4.53 | |
| 82 | 78000200 | THPL PVT MK LINE 4 | 53,917 | FOOT | $0.5500 | $0.5000 | $0.5500 | $0.5500 | |
| 83 | 78000400 | THPL PVT MK LINE 6 | 4,117 | FOOT | $0.7700 | $0.9000 | $0.8800 | $1.02 | |
| 84 | 78000600 | THPL PVT MK LINE 12 | 626 | FOOT | $1.54 | $2.25 | $2.00 | $2.55 | |
| 85 | 78000650 | THPL PVT MK LINE 24 | 582 | FOOT | $4.13 | $4.25 | $4.25 | $4.81 | |
| 86 | 78100100 | RAISED REFL PAVT MKR | 1,234 | EACH | $22.00 | $22.00 | $24.65 | $24.94 | |
| 87 | 78200006 | GRDRAIL REF TYPE B | 4 | EACH | $10.56 | $10.00 | $12.00 | $10.00 | |
| 88 | 78300200 | RAISED REF PVT MK REM | 1,111 | EACH | $6.00 | $0.0100 | $6.00 | $8.50 | |
| 89 | 85000200 | MAIN EX TR SIG INSTAL | 1 | EACH | $242.00 | $2,200.00 | $2,200.00 | $2,493.56 | |
| 90 | 88600600 | DET LOOP REPL | 2,333 | FOOT | $17.60 | $16.00 | $16.00 | $18.13 | |
| 91 | 89500400 | RELOC EX PED PUSH-BUT | 9 | EACH | $352.00 | $320.00 | $320.00 | $362.70 | |
| 92 | 89502376 | REBUILD EX HANDHOLE | 1 | EACH | $2,200.00 | $2,250.00 | $2,000.00 | $2,266.88 |