2015-083-B
Bidders 7
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D. Construction, Inc. Low bidder | $360,217 | ||
| 2 | Lorig Construction Company | $371,928 | +3.3% | |
| 3 | Norvilla, LLC | $372,157 | +3.3% | |
| 4 | Martam Construction Incorporated | $378,883 | +5.2% | |
| 5 | Alliance Contractors, Inc. | $404,254 | +12.2% | |
| 6 | Copenhaver Construction, Inc. | $448,410 | +24.5% | |
| 7 | Areatha Construction Co., Inc. | $631,696 | +75.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D. Construction… | #2 Lorig Construct… | #3 Norvilla, LLC | #4 Martam Construc… | #5 Alliance Contra… | #6 Copenhaver Cons… | #7 Areatha Constru… |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0322128 | MEMBR WTRPR B STRUCT | 46 | SQ YD | $74.25 | $140.00 | $143.00 | $76.00 | $67.50 | $45.00 | $71.00 | |
| 2 | X2502024 | SEEDING CL 4B MOD | 0.25 | ACRE | $8,195.00 | $4,900.00 | $5,243.00 | $19,000.00 | $16,700.00 | $6,000.00 | $4,840.00 | |
| 3 | X2511630 | EROS CONT BLANKET SPL | 1,210 | SQ YD | $2.20 | $1.50 | $1.65 | $2.00 | $1.75 | $4.00 | $3.50 | |
| 4 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $15,000.00 | $39,000.00 | $12,570.00 | $36,000.00 | $6,900.00 | $51,000.00 | $7,245.00 | |
| 5 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $5,000.00 | $10,000.00 | $5,125.00 | $6,000.00 | $4,789.00 | $12,000.00 | $7,500.00 | |
| 6 | Z0022800 | FENCE REMOVAL | 187 | FOOT | $5.09 | $12.00 | $5.70 | $5.00 | $4.63 | $6.00 | $5.00 | |
| 7 | Z0030850 | TEMP INFO SIGNING | 38 | SQ FT | $30.00 | $18.00 | $12.85 | $20.00 | $18.00 | $20.00 | $19.00 | |
| 8 | Z0054400 | ROCK FILL | 41 | CU YD | $50.00 | $110.00 | $152.55 | $54.00 | $42.00 | $45.00 | $100.00 | |
| 9 | Z0073510 | TEMP TR SIGNAL TIMING | 9 | EACH | $247.50 | $225.00 | $240.75 | $250.00 | $225.00 | $400.00 | $500.00 | |
| 10 | 20100110 | TREE REMOV 6-15 | 20 | UNIT | $18.70 | $17.00 | $17.85 | $20.00 | $17.00 | $20.00 | $45.00 | |
| 11 | 20100210 | TREE REMOV OVER 15 | 89 | UNIT | $27.50 | $25.00 | $26.25 | $30.00 | $25.00 | $35.00 | $45.00 | |
| 12 | 20101100 | TREE TRUNK PROTECTION | 1 | EACH | $82.50 | $75.00 | $78.75 | $80.00 | $75.00 | $100.00 | $250.00 | |
| 13 | 20101300 | TREE PRUN 1-10 | 7 | EACH | $55.00 | $50.00 | $53.50 | $60.00 | $50.00 | $70.00 | $200.00 | |
| 14 | 20200100 | EARTH EXCAVATION | 500 | CU YD | $30.00 | $37.00 | $35.00 | $28.00 | $10.00 | $29.00 | $75.00 | |
| 15 | 20201200 | REM & DISP UNS MATL | 34 | CU YD | $50.00 | $40.00 | $50.00 | $68.00 | $10.00 | $35.00 | $85.00 | |
| 16 | 20700220 | POROUS GRAN EMBANK | 90 | CU YD | $60.00 | $85.00 | $68.00 | $45.00 | $40.00 | $45.00 | $85.00 | |
| 17 | 21001000 | GEOTECH FAB F/GR STAB | 80 | SQ YD | $5.00 | $3.00 | $13.00 | $3.00 | $1.00 | $5.00 | $15.00 | |
| 18 | 21101505 | TOPSOIL EXC & PLAC | 60 | CU YD | $35.00 | $48.00 | $25.00 | $32.00 | $20.00 | $20.00 | $65.00 | |
| 19 | 21400100 | GRADING & SHAP DITCH | 75 | FOOT | $65.00 | $8.00 | $63.00 | $22.00 | $75.00 | $19.00 | $125.00 | |
| 20 | 28000400 | PERIMETER EROS BAR | 745 | FOOT | $2.75 | $3.25 | $8.00 | $4.00 | $3.00 | $2.00 | $6.00 | |
| 21 | 28100707 | STONE DUMP RIP CL A4 | 26 | SQ YD | $100.00 | $125.00 | $174.00 | $95.00 | $230.00 | $100.00 | $200.00 | |
| 22 | 28200200 | FILTER FABRIC | 55 | SQ YD | $5.00 | $3.00 | $15.00 | $3.00 | $1.00 | $10.00 | $10.00 | |
| 23 | 30300001 | AGG SUBGRADE IMPROVE | 34 | CU YD | $65.00 | $63.00 | $82.00 | $54.00 | $40.00 | $45.00 | $125.00 | |
| 24 | 30300112 | AGG SUBGRADE IMPR 12 | 384 | SQ YD | $25.00 | $22.00 | $24.00 | $18.00 | $14.15 | $15.00 | $45.00 | |
| 25 | 31101100 | SUB GRAN MAT B | 45 | CU YD | $55.00 | $70.00 | $78.00 | $54.00 | $40.00 | $41.00 | $85.00 | |
| 26 | 40700100 | BIT MATLS TACK CT | 168 | POUND | $0.0100 | $1.00 | $2.10 | $7.00 | $2.00 | $3.00 | $7.00 | |
| 27 | 40701876 | HMA PAVT FD 9 3/4 | 283 | SQ YD | $60.00 | $56.00 | $71.50 | $82.00 | $68.11 | $85.00 | $79.00 | |
| 28 | 44000100 | PAVEMENT REM | 309 | SQ YD | $15.00 | $21.00 | $27.00 | $15.00 | $20.00 | $15.00 | $35.00 | |
| 29 | 48203036 | HMA SHOULDERS 9 3/4 | 89 | SQ YD | $60.00 | $60.00 | $72.00 | $85.00 | $68.11 | $85.00 | $82.00 | |
| 30 | 50102400 | CONC REM | 28 | CU YD | $500.00 | $450.00 | $150.00 | $250.00 | $40.00 | $500.00 | $1,600.00 | |
| 31 | 50200100 | STRUCTURE EXCAVATION | 80 | CU YD | $50.00 | $45.00 | $78.00 | $56.00 | $10.00 | $82.00 | $100.00 | |
| 32 | 50200450 | REM/DISP UNS MATL-STR | 41 | CU YD | $50.00 | $45.00 | $119.00 | $68.00 | $10.00 | $57.00 | $125.00 | |
| 33 | 50800105 | REINFORCEMENT BARS | 10,410 | POUND | $1.75 | $1.60 | $1.45 | $2.00 | $1.85 | $2.00 | $3.00 | |
| 34 | 52200015 | PERM SHT PILING | 610 | SQ FT | $30.00 | $25.00 | $31.55 | $35.00 | $59.10 | $55.00 | $125.00 | |
| 35 | 54003000 | CONC BOX CUL | 54 | CU YD | $1,200.00 | $1,400.00 | $1,277.00 | $1,240.00 | $3,011.00 | $1,500.00 | $2,500.00 | |
| 36 | 63000003 | SPBGR TY A 9FT POSTS | 500 | FOOT | $30.10 | $31.50 | $26.25 | $27.00 | $27.36 | $35.00 | $29.00 | |
| 37 | 63000360 | LSG OV CUL 18'9" SPAN | 87.5 | FOOT | $29.00 | $43.50 | $31.50 | $33.00 | $26.36 | $50.00 | $28.00 | |
| 38 | 63100167 | TR BAR TRM T1 SPL TAN | 3 | EACH | $2,729.10 | $2,800.00 | $2,887.00 | $3,000.00 | $2,481.00 | $3,000.00 | $2,606.00 | |
| 39 | 63100169 | TR BAR TRM T1 SPL FLR | 1 | EACH | $2,541.00 | $2,800.00 | $2,645.00 | $2,750.00 | $2,310.00 | $3,500.00 | $2,426.00 | |
| 40 | 63200310 | GUARDRAIL REMOV | 406 | FOOT | $5.34 | $5.65 | $4.20 | $5.00 | $4.85 | $5.00 | $5.10 | |
| 41 | 66900200 | NON SPL WASTE DISPOSL | 575 | CU YD | $70.00 | $40.00 | $80.00 | $63.00 | $43.15 | $92.00 | $95.00 | |
| 42 | 66900450 | SPL WASTE PLNS/REPORT | 1 | L SUM | $8,030.00 | $3,600.00 | $2,889.00 | $4,000.00 | $3,780.00 | $7,500.00 | $6,900.00 | |
| 43 | 66900530 | SOIL DISPOSAL ANALY | 1 | EACH | $1,485.00 | $1,950.00 | $1,498.00 | $1,600.00 | $1,990.00 | $2,300.00 | $2,000.00 | |
| 44 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $3,500.00 | $1,900.00 | $2,140.00 | $3,200.00 | $500.00 | $1,000.00 | $3,000.00 | |
| 45 | 67100100 | MOBILIZATION | 1 | L SUM | $20,000.00 | $20,000.00 | $22,000.00 | $20,000.00 | $25,000.00 | $25,382.00 | $36,500.00 | |
| 46 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $38.50 | $44.00 | $32.10 | $35.00 | $35.00 | $50.00 | $37.00 | |
| 47 | 78000200 | THPL PVT MK LINE 4 | 400 | FOOT | $4.40 | $4.00 | $4.25 | $5.00 | $4.00 | $6.00 | $4.20 | |
| 48 | 78100100 | RAISED REFL PAVT MKR | 4 | EACH | $522.50 | $475.00 | $508.00 | $520.00 | $475.00 | $50.00 | $500.00 | |
| 49 | 78200006 | GRDRAIL REF TYPE B | 13 | EACH | $13.20 | $9.00 | $8.60 | $10.00 | $12.00 | $55.00 | $13.00 |