2014-072I
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Sumit Construction Co., Inc. Low bidder | $539,989 | ||
| 2 | Alliance Contractors, Inc. | $614,987 | +13.9% | |
| 3 | A Lamp Concrete Contractors, Inc. | $689,409 | +27.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Sumit Construct… | #2 Alliance Contra… | #3 A Lamp Concrete… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $18,000.00 | $19,500.00 | $42,000.00 | |
| 2 | X0326806 | WASHOUT BASIN | 1 | L SUM | $500.00 | $1,200.00 | $2,500.00 | |
| 3 | X0327036 | BIKE PATH REM | 204 | SQ YD | $22.00 | $20.00 | $20.00 | |
| 4 | X0327980 | PAVMT MRKG REM WTR BL | 2,968 | SQ FT | $4.00 | $5.25 | $2.25 | |
| 5 | X2600012 | REM & REL SN P&P ASSY | 3 | EACH | $160.00 | $140.00 | $350.00 | |
| 6 | X4240800 | DETECTABLE WARN SPL | 569 | SQ FT | $45.00 | $20.00 | $35.00 | |
| 7 | X4400220 | CURB REM & REPLACEMT | 327 | FOOT | $30.00 | $60.00 | $45.00 | |
| 8 | X4402020 | CONC MEDIAN SURF REM | 301 | SQ FT | $5.00 | $3.00 | $2.00 | |
| 9 | Z0004562 | COMB C C&G REM & REPL | 1,883 | FOOT | $40.00 | $70.00 | $45.00 | |
| 10 | Z0030850 | TEMP INFO SIGNING | 154.2 | SQ FT | $15.00 | $17.00 | $25.00 | |
| 11 | 20101200 | TREE ROOT PRUNING | 29 | EACH | $120.00 | $75.00 | $15.00 | |
| 12 | 20200100 | EARTH EXCAVATION | 279 | CU YD | $50.00 | $1.00 | $63.00 | |
| 13 | 21101625 | TOPSOIL F & P 6 | 1,342 | SQ YD | $10.00 | $7.98 | $2.00 | |
| 14 | 25000400 | NITROGEN FERT NUTR | 26 | POUND | $5.00 | $4.00 | $1.00 | |
| 15 | 25000600 | POTASSIUM FERT NUTR | 26 | POUND | $5.00 | $4.00 | $1.00 | |
| 16 | 25200110 | SODDING SALT TOLERANT | 1,342 | SQ YD | $12.00 | $12.65 | $8.00 | |
| 17 | 25200200 | SUPPLE WATERING | 20.1 | UNIT | $50.00 | $75.00 | $10.00 | |
| 18 | 31101200 | SUB GRAN MAT B 4 | 1,763 | SQ YD | $6.00 | $5.00 | $8.10 | |
| 19 | 40603340 | HMA SC "D" N70 | 38 | TON | $250.00 | $900.00 | $340.00 | |
| 20 | 40800025 | BIT MATLS PR CT | 25 | POUND | $2.00 | $5.00 | $1.00 | |
| 21 | 42001300 | PROTECTIVE COAT | 2,103 | SQ YD | $3.00 | $0.0100 | $0.0100 | |
| 22 | 42400200 | PC CONC SIDEWALK 5 | 12,674 | SQ FT | $9.00 | $8.00 | $11.75 | |
| 23 | 42400800 | DETECTABLE WARNINGS | 718 | SQ FT | $40.00 | $20.00 | $30.00 | |
| 24 | 44000155 | HMA SURF REM 1 1/2 | 423 | SQ YD | $14.00 | $5.00 | $21.00 | |
| 25 | 44000600 | SIDEWALK REM | 12,091 | SQ FT | $3.00 | $4.00 | $1.65 | |
| 26 | 60250200 | CB ADJUST | 2 | EACH | $450.00 | $200.00 | $450.00 | |
| 27 | 60260100 | INLETS ADJUST | 6 | EACH | $250.00 | $200.00 | $400.00 | |
| 28 | 60265700 | VV ADJUST | 5 | EACH | $350.00 | $200.00 | $450.00 | |
| 29 | 60300305 | FR & LIDS ADJUST | 3 | EACH | $350.00 | $200.00 | $450.00 | |
| 30 | 60618300 | CONC MEDIAN SURF 4 | 301 | SQ FT | $10.00 | $8.00 | $11.00 | |
| 31 | 66900200 | NON SPL WASTE DISPOSL | 279 | CU YD | $70.00 | $50.00 | $100.00 | |
| 32 | 66900450 | SPL WASTE PLNS/REPORT | 1 | L SUM | $5,000.00 | $1,500.00 | $25,300.00 | |
| 33 | 66900530 | SOIL DISPOSAL ANALY | 6 | EACH | $1,500.00 | $1,500.00 | $1,650.00 | |
| 34 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $2,000.00 | $500.00 | $3,000.00 | |
| 35 | 67100100 | MOBILIZATION | 1 | L SUM | $15,000.00 | $66,593.00 | $40,000.00 | |
| 36 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $100.00 | $25,914.00 | $87,000.00 | |
| 37 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $100.00 | $7,500.00 | $1.00 | |
| 38 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $100.00 | $1.00 | $1.00 | |
| 39 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $40,000.00 | $7,500.00 | $1.00 | |
| 40 | 78000400 | THPL PVT MK LINE 6 | 2,586 | FOOT | $1.20 | $2.00 | $2.80 | |
| 41 | 78000600 | THPL PVT MK LINE 12 | 382 | FOOT | $2.00 | $3.50 | $5.60 | |
| 42 | 78000650 | THPL PVT MK LINE 24 | 713 | FOOT | $4.00 | $8.00 | $11.20 | |
| 43 | 85000200 | MAIN EX TR SIG INSTAL | 3 | EACH | $900.00 | $840.00 | $925.00 | |
| 44 | 89502376 | REBUILD EX HANDHOLE | 3 | EACH | $4,000.00 | $3,775.00 | $4,200.00 |