24-00078-00-BT
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | A Lamp Concrete Contractors, Inc. Low bidder | $1,344,596 | ||
| 2 | Martam Construction Incorporated | $1,528,287 | +13.7% | |
| 3 | R. W. Dunteman Company | $1,595,784 | +18.7% | |
| 4 | Copenhaver Construction, Inc. | $1,603,598 | +19.3% | |
| 5 | PirTano Construction Co., LLC | $1,700,000 | +26.4% | |
| 6 | Alliance Contractors, Inc. | $1,813,621 | +34.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 A Lamp Concrete… | #2 Martam Construc… | #3 R. W. Dunteman … | #4 Copenhaver Cons… | #5 PirTano Constru… | #6 Alliance Contra… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | K0012990 | P PL ORNAMENT T GAL P | 1 | UNIT | $2,400.00 | $3,640.00 | $3,500.00 | $2,500.00 | $3,025.00 | $3,500.00 | |
| 2 | K0029634 | WEED CONTR PRE-EM GRN | 2 | POUND | $50.00 | $52.00 | $50.00 | $300.00 | $56.00 | $50.00 | |
| 3 | K0036117 | MULCH PLACEMENT 2 | 20 | SQ YD | $10.00 | $10.40 | $10.00 | $12.00 | $11.00 | $10.00 | |
| 4 | XX009733 | REM&REL GRD ELEC SER | 1 | EACH | $3,600.00 | $3,744.00 | $3,600.00 | $4,700.00 | $1,975.00 | $3,600.00 | |
| 5 | X0324085 | EM VEH P S LSC 20 3C | 150 | FOOT | $1.30 | $1.35 | $1.30 | $2.00 | $6.50 | $1.30 | |
| 6 | X0326806 | WASHOUT BASIN | 1 | L SUM | $1,250.00 | $1,373.95 | $2,000.00 | $1,200.00 | $2,340.00 | $750.00 | |
| 7 | X0327149 | RELOCATE BENCH | 1 | EACH | $675.00 | $1,956.39 | $1,800.00 | $600.00 | $970.00 | $4,150.00 | |
| 8 | X0327989 | REMOVE EXSTNG BR PAV | 9,133 | SQ FT | $1.60 | $3.05 | $4.10 | $3.00 | $3.00 | $4.00 | |
| 9 | X1400367 | PED SIGNAL POST 10 FT | 5 | EACH | $1,576.00 | $1,639.04 | $1,576.00 | $1,900.00 | $1,580.00 | $1,576.00 | |
| 10 | X1400378 | PED SIGNAL POST 5 FT | 3 | EACH | $1,352.00 | $1,406.08 | $1,352.00 | $1,600.00 | $1,210.00 | $1,352.00 | |
| 11 | X1700067 | STAMP COL PCC SDWLK 5 | 7,870 | SQ FT | $15.00 | $23.37 | $20.35 | $25.00 | $26.75 | $50.00 | |
| 12 | X2130010 | EXPLOR TRENCH SPL | 100 | FOOT | $10.00 | $45.09 | $52.30 | $20.00 | $170.00 | $20.00 | |
| 13 | X4022000 | TEMP ACCESS- COM ENT | 2 | EACH | $500.00 | $985.66 | $480.00 | $200.00 | $2,330.00 | $1.00 | |
| 14 | X6026050 | SANITARY MANHOLE ADJ | 1 | EACH | $1,300.00 | $1,355.96 | $1,150.00 | $1,500.00 | $2,075.00 | $695.00 | |
| 15 | X8100863 | INTERCEPT EX CONDUIT | 1 | EACH | $715.00 | $743.60 | $715.00 | $900.00 | $525.00 | $715.00 | |
| 16 | X8140238 | REBLD EX DBL HANDHOLE | 4 | EACH | $4,643.00 | $4,828.72 | $4,643.00 | $5,600.00 | $4,435.00 | $4,643.00 | |
| 17 | X8760002 | APS EXT BRACKET | 1 | EACH | $438.00 | $455.52 | $438.00 | $500.00 | $315.00 | $438.00 | |
| 18 | X8760200 | ACCESSIBLE PED SIGNAL | 22 | EACH | $2,406.00 | $2,502.24 | $2,406.00 | $2,800.00 | $2,225.00 | $2,406.00 | |
| 19 | X8780012 | CONC FDN TY A 12D | 36 | FOOT | $369.00 | $383.76 | $369.00 | $470.00 | $325.00 | $369.00 | |
| 20 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $13,900.00 | $17,045.54 | $13,900.00 | $17,000.00 | $30,000.00 | $13,900.00 | |
| 21 | Z0033044 | RE-OPTIMIZE TR SIG SYS 1 | 5 | EACH | $1,340.00 | $1,393.60 | $1,340.00 | $1,800.00 | $615.00 | $1,340.00 | |
| 22 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 23 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | |
| 24 | 20101000 | TEMPORARY FENCE | 125 | FOOT | $6.00 | $10.40 | $10.00 | $6.00 | $8.00 | $10.00 | |
| 25 | 20200100 | EARTH EXCAVATION | 1,125 | CU YD | $58.00 | $35.94 | $67.00 | $45.00 | $45.00 | $10.00 | |
| 26 | 20201200 | REM & DISP UNS MATL | 1,154 | CU YD | $15.00 | $35.90 | $67.00 | $45.00 | $35.00 | $10.00 | |
| 27 | 20400800 | FURNISHED EXCAVATION | 26 | CU YD | $1.00 | $65.43 | $108.50 | $10.00 | $1.00 | $20.00 | |
| 28 | 21101615 | TOPSOIL F & P 4 | 6,992 | SQ YD | $6.50 | $0.1000 | $0.1000 | $4.00 | $10.00 | $0.1000 | |
| 29 | 25000210 | SEEDING CL 2A | 1.5 | ACRE | $5,500.00 | $25,168.00 | $24,200.00 | $6,000.00 | $3,100.00 | $24,200.00 | |
| 30 | 25000400 | NITROGEN FERT NUTR | 131 | POUND | $3.00 | $1.04 | $1.00 | $1.00 | $3.00 | $1.00 | |
| 31 | 25000600 | POTASSIUM FERT NUTR | 131 | POUND | $3.00 | $1.04 | $1.00 | $1.00 | $3.00 | $1.00 | |
| 32 | 25100630 | EROSION CONTR BLANKET | 6,992 | SQ YD | $1.25 | $1.56 | $1.50 | $2.00 | $1.00 | $1.50 | |
| 33 | 25200200 | SUPPLE WATERING | 1 | UNIT | $100.00 | $260.00 | $250.00 | $0.0100 | $28.00 | $250.00 | |
| 34 | 28000250 | TEMP EROS CONTR SEED | 145 | POUND | $5.00 | $0.1000 | $0.1000 | $0.0100 | $7.00 | $0.1000 | |
| 35 | 28000400 | PERIMETER EROS BAR | 3,092 | FOOT | $1.00 | $2.86 | $2.75 | $3.00 | $2.25 | $2.75 | |
| 36 | 28000510 | INLET FILTERS | 29 | EACH | $15.00 | $234.00 | $185.00 | $200.00 | $300.00 | $25.00 | |
| 37 | 35101600 | AGG BASE CSE B 4 | 1,874 | SQ YD | $9.85 | $6.03 | $12.75 | $12.00 | $12.00 | $7.20 | |
| 38 | 35102000 | AGG BASE CSE B 8 | 2,186 | SQ YD | $20.00 | $9.81 | $17.25 | $16.00 | $22.00 | $14.40 | |
| 39 | 35501316 | HMA BASE CSE 8 | 182 | SQ YD | $61.00 | $176.05 | $80.00 | $120.00 | $121.50 | $100.80 | |
| 40 | 35800100 | PREPARATION OF BASE | 4,395 | SQ YD | $0.0100 | $1.56 | $1.50 | $3.00 | $3.50 | $1.90 | |
| 41 | 40600275 | BIT MATLS PR CT | 9,888 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $1.00 | $0.0100 | |
| 42 | 40604060 | HMA SC IL-9.5 D N50 | 527 | TON | $130.00 | $150.28 | $140.00 | $160.00 | $155.00 | $118.00 | |
| 43 | 42300400 | PCC DRIVEWAY PAVT 8 | 314 | SQ YD | $122.00 | $115.76 | $86.50 | $125.00 | $90.00 | $116.10 | |
| 44 | 42400200 | PC CONC SIDEWALK 5 | 8,993 | SQ FT | $8.50 | $10.34 | $8.75 | $12.00 | $10.50 | $20.00 | |
| 45 | 42400800 | DETECTABLE WARNINGS | 447 | SQ FT | $35.00 | $43.12 | $37.25 | $35.00 | $46.00 | $40.00 | |
| 46 | 44000157 | HMA SURF REM 2 | 2,442 | SQ YD | $8.50 | $7.80 | $13.96 | $9.00 | $5.00 | $20.00 | |
| 47 | 44000200 | DRIVE PAVEMENT REM | 472 | SQ YD | $16.50 | $10.21 | $27.50 | $16.00 | $21.00 | $20.00 | |
| 48 | 44000500 | COMB CURB GUTTER REM | 912 | FOOT | $8.25 | $5.18 | $16.00 | $8.00 | $9.00 | $15.00 | |
| 49 | 44000600 | SIDEWALK REM | 8,785 | SQ FT | $1.00 | $1.84 | $2.50 | $2.00 | $4.00 | $2.00 | |
| 50 | 44201365 | CL C PATCH T2 11 | 26 | SQ YD | $275.00 | $267.56 | $345.00 | $190.00 | $350.00 | $260.00 | |
| 51 | 44201371 | CL C PATCH T4 11 | 338 | SQ YD | $140.00 | $210.69 | $256.00 | $155.00 | $240.00 | $237.25 | |
| 52 | 44201777 | CL D PATCH T2 11 | 10 | SQ YD | $330.00 | $250.19 | $258.00 | $200.00 | $775.00 | $1,100.00 | |
| 53 | 44201783 | CL D PATCH T4 11 | 106 | SQ YD | $125.00 | $245.19 | $120.00 | $190.00 | $330.00 | $274.00 | |
| 54 | 56400100 | FIRE HYDNTS TO BE MVD | 6 | EACH | $6,500.00 | $5,324.52 | $9,450.00 | $5,000.00 | $6,050.00 | $8,732.00 | |
| 55 | 60255500 | MAN ADJUST | 5 | EACH | $425.00 | $808.47 | $550.00 | $600.00 | $1,250.00 | $350.00 | |
| 56 | 60260300 | INLETS ADJ NEW T1F OL | 2 | EACH | $1,100.00 | $1,198.08 | $1,125.00 | $500.00 | $1,550.00 | $350.00 | |
| 57 | 60265700 | VV ADJUST | 6 | EACH | $575.00 | $808.47 | $550.00 | $300.00 | $1,135.00 | $350.00 | |
| 58 | 60300105 | FR & GRATES ADJUST | 3 | EACH | $450.00 | $808.48 | $465.00 | $500.00 | $1,135.00 | $350.00 | |
| 59 | 60600605 | CONC CURB TB | 754 | FOOT | $38.00 | $39.71 | $34.50 | $45.00 | $42.00 | $1.00 | |
| 60 | 60603800 | COMB CC&G TB6.12 | 274 | FOOT | $44.00 | $56.99 | $37.00 | $39.00 | $45.00 | $139.75 | |
| 61 | 60604400 | COMB CC&G TB6.18 | 50 | FOOT | $58.00 | $63.96 | $60.50 | $42.00 | $57.00 | $144.15 | |
| 62 | 60605000 | COMB CC&G TY B-6.24 | 537 | FOOT | $52.00 | $67.10 | $45.00 | $40.00 | $52.00 | $145.80 | |
| 63 | 63000035 | BCK SD PROT OF GRDRL | 90 | FOOT | $25.34 | $26.35 | $55.75 | $45.00 | $29.00 | $25.34 | |
| 64 | 66900200 | NON SPL WASTE DISPOSL | 442 | CU YD | $85.00 | $88.82 | $101.50 | $90.00 | $75.00 | $69.70 | |
| 65 | 66900530 | SOIL DISPOSAL ANALY | 3 | EACH | $850.00 | $884.00 | $850.00 | $1,600.00 | $1,000.00 | $1,500.00 | |
| 66 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $5,200.00 | $5,408.00 | $5,200.00 | $4,000.00 | $1,500.00 | $4,200.00 | |
| 67 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $500.00 | $520.00 | $500.00 | $2,500.00 | $1,000.00 | $500.00 | |
| 68 | 66901006 | REG SUB MON | 15 | CAL DA | $700.00 | $728.00 | $700.00 | $800.00 | $800.00 | $1,500.00 | |
| 69 | 67100100 | MOBILIZATION | 1 | L SUM | $80,640.00 | $91,697.19 | $101,000.00 | $103,000.00 | $102,000.00 | $122,892.80 | |
| 70 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $80,000.00 | $1.04 | $44,750.00 | $49,000.00 | $1.00 | $9,500.00 | |
| 71 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $1.00 | $75,460.23 | $10,460.00 | $100.00 | $28,000.00 | $1.00 | |
| 72 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.04 | $10,460.00 | $100.00 | $1.00 | $1.00 | |
| 73 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1.00 | $1.04 | $2.05 | $1,000.00 | $11,672.50 | $1.00 | |
| 74 | 78009006 | MOD URETH PM LINE 6 | 2,101 | FOOT | $1.90 | $1.98 | $1.90 | $2.00 | $2.50 | $1.90 | |
| 75 | 78009012 | MOD URETH PM LINE 12 | 2,571 | FOOT | $3.30 | $3.43 | $3.30 | $4.00 | $7.50 | $3.30 | |
| 76 | 78009024 | MOD URETH PM LINE 24 | 22 | FOOT | $6.00 | $6.24 | $6.00 | $7.00 | $14.00 | $6.00 | |
| 77 | 78300201 | PVT MKG REM GRINDING | 55 | SQ FT | $14.00 | $14.56 | $14.00 | $20.00 | $2.00 | $14.00 | |
| 78 | 81028200 | UNDRGRD C GALVS 2 | 148 | FOOT | $30.60 | $31.82 | $30.60 | $40.00 | $50.00 | $30.60 | |
| 79 | 81028220 | UNDRGRD C GALVS 3 | 71 | FOOT | $64.20 | $66.77 | $64.32 | $80.00 | $62.00 | $64.20 | |
| 80 | 85000200 | MAIN EX TR SIG INSTAL | 5 | EACH | $4,800.00 | $4,992.00 | $4,800.00 | $6,200.00 | $6,215.00 | $4,800.00 | |
| 81 | 87301215 | ELCBL C SIGNAL 14 2C | 3,092 | FOOT | $2.00 | $2.08 | $2.00 | $3.00 | $3.00 | $2.00 | |
| 82 | 87301225 | ELCBL C SIGNAL 14 3C | 2,505 | FOOT | $2.20 | $2.29 | $2.20 | $3.00 | $3.00 | $2.20 | |
| 83 | 87301245 | ELCBL C SIGNAL 14 5C | 2,130 | FOOT | $2.60 | $2.70 | $2.60 | $3.00 | $3.50 | $2.60 | |
| 84 | 87301255 | ELCBL C SIGNAL 14 7C | 219 | FOOT | $3.00 | $3.12 | $3.00 | $4.00 | $4.00 | $3.00 | |
| 85 | 87301805 | ELCBL C SERV 6 2C | 75 | FOOT | $4.20 | $4.37 | $4.20 | $6.00 | $7.00 | $4.20 | |
| 86 | 87301900 | ELCBL C EGRDC 6 1C | 457 | FOOT | $2.80 | $2.91 | $2.80 | $4.00 | $4.00 | $2.80 | |
| 87 | 87501200 | TS POST 16 | 4 | EACH | $2,514.00 | $2,614.56 | $2,514.00 | $3,000.00 | $2,875.00 | $2,514.00 | |
| 88 | 87702970 | STL COMB MAA&P 48 | 1 | EACH | $31,830.00 | $33,103.20 | $31,830.00 | $36,000.00 | $31,000.00 | $31,830.00 | |
| 89 | 87800100 | CONC FDN TY A | 20 | FOOT | $322.80 | $335.71 | $322.80 | $400.00 | $350.00 | $322.80 | |
| 90 | 87800415 | CONC FDN TY E 36D | 13 | FOOT | $622.50 | $647.40 | $622.50 | $780.00 | $485.00 | $622.50 | |
| 91 | 87900200 | DRILL EX HANDHOLE | 14 | EACH | $617.00 | $641.68 | $617.00 | $790.00 | $770.00 | $617.00 | |
| 92 | 88102717 | PED SH LED 1F BM CDT | 10 | EACH | $574.00 | $596.96 | $574.00 | $670.00 | $830.00 | $574.00 | |
| 93 | 89500100 | RELOC EX SIG HEAD | 10 | EACH | $917.00 | $953.68 | $917.00 | $1,200.00 | $985.00 | $917.00 | |
| 94 | 89500200 | RELOC EX PED SIG HEAD | 5 | EACH | $617.00 | $641.68 | $617.00 | $800.00 | $525.00 | $617.00 | |
| 95 | 89501150 | RELOC EX TS POST | 1 | EACH | $917.00 | $953.68 | $917.00 | $1,200.00 | $740.00 | $917.00 | |
| 96 | 89501400 | REL EM VEH PR SYS D U | 1 | EACH | $536.00 | $557.44 | $536.00 | $700.00 | $770.00 | $536.00 | |
| 97 | 89502200 | MOD EX CONTR | 3 | EACH | $1,782.00 | $1,853.28 | $1,782.00 | $2,300.00 | $1,115.00 | $1,782.00 | |
| 98 | 89502300 | REM ELCBL FR CON | 4,747 | FOOT | $0.6000 | $0.6200 | $0.6000 | $1.00 | $2.00 | $0.6000 | |
| 99 | 89502375 | REMOV EX TS EQUIP | 5 | EACH | $2,400.00 | $2,496.00 | $2,400.00 | $3,100.00 | $3,450.00 | $2,400.00 | |
| 100 | 89502376 | REBUILD EX HANDHOLE | 6 | EACH | $3,493.00 | $3,632.72 | $3,493.00 | $4,400.00 | $2,935.00 | $3,493.00 | |
| 101 | 89502385 | REMOV EX CONC FDN | 7 | EACH | $600.00 | $624.00 | $600.00 | $800.00 | $1,020.00 | $600.00 |