23-00120-00-RS
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Gallagher Asphalt Corporation Low bidder | $1,777,633 | ||
| 2 | K-Five Construction Corporation | $1,956,652 | +10.1% | |
| 3 | D. Construction, Inc. | $2,045,851 | +15.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Gallagher Aspha… | #2 K-Five Construc… | #3 D. Construction… |
|---|---|---|---|---|---|---|---|---|
| 1 | K1004595 | PRUN SAFETY/EQUIP CLR | 1 | L SUM | $6,500.00 | $800.00 | $7,150.00 | |
| 2 | X1700021 | BRC PVR REM RENSTL SP | 39 | SQ FT | $30.00 | $20.00 | $22.00 | |
| 3 | X4021000 | TEMP ACCESS- PRIV ENT | 13 | EACH | $50.00 | $448.00 | $55.00 | |
| 4 | X4022000 | TEMP ACCESS- COM ENT | 10 | EACH | $60.00 | $582.00 | $66.00 | |
| 5 | X6030310 | FR & LIDS ADJUST SPL | 63 | EACH | $975.00 | $975.00 | $1,072.50 | |
| 6 | X6066016 | HMA MEDIAN SURF 4 | 87 | SQ FT | $4.50 | $5.00 | $45.00 | |
| 7 | X7800200 | PAINT PVT MARK CURB | 31 | FOOT | $5.00 | $5.00 | $17.60 | |
| 8 | X8860105 | DET LOOP REPL | 1,165 | FOOT | $15.60 | $15.60 | $17.16 | |
| 9 | Z0004530 | HMA DRIVEWAY PAVT 8 | 597 | SQ YD | $66.00 | $85.00 | $55.00 | |
| 10 | Z0017400 | DRAIN UTIL STR ADJ | 75 | EACH | $400.00 | $400.00 | $440.00 | |
| 11 | Z0017700 | DRAIN UTIL STR RECON | 2 | EACH | $1,400.00 | $1,400.00 | $1,540.00 | |
| 12 | Z0030850 | TEMP INFO SIGNING | 125 | SQ FT | $28.00 | $28.00 | $25.00 | |
| 13 | 20200100 | EARTH EXCAVATION | 10 | CU YD | $100.00 | $100.00 | $110.00 | |
| 14 | 20201200 | REM & DISP UNS MATL | 50 | CU YD | $25.00 | $10.00 | $100.00 | |
| 15 | 21101615 | TOPSOIL F & P 4 | 1,521 | SQ YD | $6.00 | $6.00 | $6.60 | |
| 16 | 25200110 | SODDING SALT TOLERANT | 1,521 | SQ YD | $14.00 | $9.00 | $9.90 | |
| 17 | 30300001 | AGG SUBGRADE IMPROVE | 50 | CU YD | $30.00 | $50.00 | $50.00 | |
| 18 | 35101600 | AGG BASE CSE B 4 | 2,055 | SQ YD | $3.50 | $0.0100 | $0.0200 | |
| 19 | 40600290 | BIT MATLS TACK CT | 30,246 | POUND | $0.0100 | $0.0100 | $0.0100 | |
| 20 | 40600370 | LONG JOINT SEALANT | 22,950 | FOOT | $3.05 | $3.00 | $3.00 | |
| 21 | 40600400 | MIX CR JTS FLANGEWYS | 67 | TON | $50.00 | $150.00 | $0.0100 | |
| 22 | 40600982 | HMA SURF REM BUTT JT | 580 | SQ YD | $16.00 | $0.0100 | $0.0100 | |
| 23 | 40603080 | HMA BC IL-19.0 N50 | 5,646 | TON | $71.90 | $75.95 | $75.00 | |
| 24 | 40604060 | HMA SC IL-9.5 D N50 | 5,019 | TON | $78.55 | $84.85 | $79.50 | |
| 25 | 42300400 | PCC DRIVEWAY PAVT 8 | 159 | SQ YD | $112.00 | $112.00 | $123.20 | |
| 26 | 42400200 | PC CONC SIDEWALK 5 | 10,681 | SQ FT | $10.15 | $10.15 | $11.17 | |
| 27 | 42400410 | PC CONC SIDEWALK 8 | 230 | SQ FT | $11.00 | $11.00 | $12.10 | |
| 28 | 42400800 | DETECTABLE WARNINGS | 878 | SQ FT | $25.00 | $24.95 | $27.45 | |
| 29 | 44000165 | HMA SURF REM 4 | 44,809 | SQ YD | $2.90 | $3.70 | $3.50 | |
| 30 | 44000200 | DRIVE PAVEMENT REM | 756 | SQ YD | $21.00 | $35.00 | $19.00 | |
| 31 | 44000300 | CURB REM | 10 | FOOT | $10.00 | $10.00 | $11.00 | |
| 32 | 44000500 | COMB CURB GUTTER REM | 3,705 | FOOT | $10.00 | $10.00 | $11.00 | |
| 33 | 44000600 | SIDEWALK REM | 12,338 | SQ FT | $1.55 | $1.50 | $1.65 | |
| 34 | 44201737 | CL D PATCH T1 8 | 10 | SQ YD | $120.00 | $23.00 | $80.00 | |
| 35 | 44201741 | CL D PATCH T2 8 | 20 | SQ YD | $100.00 | $23.00 | $80.00 | |
| 36 | 44201745 | CL D PATCH T3 8 | 24 | SQ YD | $85.00 | $23.00 | $80.00 | |
| 37 | 44201747 | CL D PATCH T4 8 | 1,265 | SQ YD | $25.00 | $23.00 | $75.00 | |
| 38 | 60266600 | VALVE BOX ADJ | 20 | EACH | $300.00 | $300.00 | $330.00 | |
| 39 | 60406000 | FR & LIDS T1 OL | 1 | EACH | $500.00 | $500.00 | $550.00 | |
| 40 | 60406100 | FR & LIDS T1 CL | 2 | EACH | $550.00 | $550.00 | $605.00 | |
| 41 | 60600605 | CONC CURB TB | 10 | FOOT | $50.00 | $50.00 | $55.00 | |
| 42 | 60603800 | COMB CC&G TB6.12 | 1,507 | FOOT | $33.75 | $33.75 | $37.13 | |
| 43 | 60604400 | COMB CC&G TB6.18 | 37 | FOOT | $38.00 | $38.00 | $41.80 | |
| 44 | 60605000 | COMB CC&G TY B-6.24 | 1,993 | FOOT | $43.00 | $43.00 | $47.30 | |
| 45 | 60608562 | COMB CC&G TM4.12 | 168 | FOOT | $32.00 | $32.00 | $35.20 | |
| 46 | 67100100 | MOBILIZATION | 1 | L SUM | $45,060.00 | $116,295.91 | $115,800.00 | |
| 47 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $13,600.00 | $25,000.00 | $0.0100 | |
| 48 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $500.00 | $77,000.00 | |
| 49 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1.00 | $500.00 | $0.0100 | |
| 50 | 70107025 | CHANGEABLE MESSAGE SN | 50 | CAL DA | $25.00 | $25.00 | $50.00 | |
| 51 | 70300100 | SHORT TERM PAVT MKING | 4,730 | FOOT | $3.00 | $1.00 | $1.00 | |
| 52 | 70300150 | SHRT TRM PAVT MK REM | 1,580 | SQ FT | $0.0100 | $2.00 | $1.00 | |
| 53 | 72000100 | SIGN PANEL T1 | 425 | SQ FT | $32.00 | $32.00 | $27.50 | |
| 54 | 72400100 | REMOV SIN PAN ASSY TA | 3 | EACH | $100.00 | $100.00 | $110.00 | |
| 55 | 72400200 | REMOV SIN PAN ASSY TB | 1 | EACH | $100.00 | $100.00 | $137.50 | |
| 56 | 72800100 | TELES STL SIN SUPPORT | 456 | FOOT | $19.00 | $19.00 | $16.50 | |
| 57 | 78000100 | THPL PVT MK LTR & SYM | 328 | SQ FT | $4.80 | $4.80 | $6.33 | |
| 58 | 78000200 | THPL PVT MK LINE 4 | 15,571 | FOOT | $0.7000 | $0.7000 | $1.05 | |
| 59 | 78000400 | THPL PVT MK LINE 6 | 1,029 | FOOT | $1.20 | $1.20 | $1.60 | |
| 60 | 78000600 | THPL PVT MK LINE 12 | 3,881 | FOOT | $2.40 | $2.40 | $3.25 | |
| 61 | 78000650 | THPL PVT MK LINE 24 | 788 | FOOT | $4.80 | $4.80 | $6.33 | |
| 62 | 78100100 | RAISED REFL PAVT MKR | 585 | EACH | $33.50 | $33.50 | $35.20 | |
| 63 | 78300200 | RAISED REF PVT MK REM | 585 | EACH | $7.00 | $25.00 | $6.00 |