21-00088-00-BR
- Let date
- Friday, March 8, 2024
- Contract
- 61K18 · job page
- District
- District 1
- County
- Cook
- Highway
- Limits
- Superstructure removal and construction of tub girder superstructure with concrete slab dck and concrete substructure repair, approach slab replacement, and sidewalks on Wedgwood Drive over Addison Creek in Westchester.
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Herlihy Mid-Continent Company Low bidder | $1,501,904 | ||
| 2 | Areatha Construction Co., Inc. | $1,588,537 | +5.8% | |
| 3 | MYS, Incorporated | $1,762,005 | +17.3% | |
| 4 | Lorig Construction Company | $1,905,726 | +26.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Herlihy Mid-Con… | #2 Areatha Constru… | #3 MYS, Incorporat… | #4 Lorig Construct… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | XX006834 | E CON TO EX LT SYS | 2 | EACH | $1,688.00 | $1,668.00 | $575.00 | $32,000.00 | |
| 2 | XX009048 | CURB & GUTTER SPL | 115 | FOOT | $77.59 | $116.35 | $50.00 | $85.00 | |
| 3 | XX009569 | PRESS BRK STL TUB GIR | 3,888 | SQ FT | $95.86 | $122.25 | $131.00 | $105.00 | |
| 4 | X0325815 | REMOVE EXISTING CABLE | 150 | FOOT | $3.22 | $3.25 | $2.30 | $5.25 | |
| 5 | X1700034 | FORM LINER TEX SUR SP | 1,290 | SQ FT | $42.00 | $28.60 | $17.92 | $28.00 | |
| 6 | X2010404 | STUMP REMOVAL | 2 | EACH | $250.00 | $250.00 | $287.50 | $250.00 | |
| 7 | X2200020 | FENCE REM & REINSTALL | 128 | FOOT | $97.19 | $112.00 | $111.77 | $82.00 | |
| 8 | X2511630 | EROS CONT BLANKET SPL | 75 | SQ YD | $6.00 | $6.00 | $6.90 | $6.00 | |
| 9 | X4240430 | PC CONC SIDEWALK 5 SP | 150 | SQ FT | $17.50 | $41.30 | $25.00 | $17.00 | |
| 10 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $8,385.00 | $8,385.00 | $15,000.00 | $125,000.00 | |
| 11 | X8130120 | RELOC EX JUNCT BOX | 2 | EACH | $2,504.00 | $2,504.00 | $2,012.50 | $10,800.00 | |
| 12 | X8430100 | REMOV EX CON ATT STR | 110 | FOOT | $20.94 | $20.95 | $5.75 | $17.00 | |
| 13 | Z0004552 | APPROACH SLAB REM | 96 | SQ YD | $32.00 | $53.15 | $85.00 | $75.00 | |
| 14 | Z0012754 | STR REP CON DP = < 5 | 235 | SQ FT | $185.00 | $204.90 | $168.00 | $235.00 | |
| 15 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $28,300.00 | $39,750.00 | $15,000.00 | $20,000.00 | |
| 16 | Z0033024 | MAINT EX LTG SYS | 1 | L SUM | $4,265.00 | $4,265.00 | $11,500.00 | $3,000.00 | |
| 17 | Z0065700 | SLOPE WALL REPAIR | 70 | SQ YD | $442.00 | $347.95 | $350.00 | $490.00 | |
| 18 | 20101350 | TREE PRUN OVER 10 | 1 | EACH | $660.00 | $660.00 | $759.00 | $660.00 | |
| 19 | 20200100 | EARTH EXCAVATION | 220 | CU YD | $65.00 | $59.30 | $95.00 | $50.00 | |
| 20 | 20201200 | REM & DISP UNS MATL | 15 | CU YD | $85.00 | $89.80 | $95.00 | $80.00 | |
| 21 | 21001000 | GEOTECH FAB F/GR STAB | 180 | SQ YD | $2.60 | $4.05 | $5.00 | $2.25 | |
| 22 | 21101615 | TOPSOIL F & P 4 | 120 | SQ YD | $14.00 | $14.00 | $16.10 | $14.00 | |
| 23 | 21301052 | EXPLOR TRENCH 52 | 100 | FOOT | $56.00 | $1.00 | $30.00 | $50.00 | |
| 24 | 25000312 | SEEDING CL 4A | 0.25 | ACRE | $3,600.00 | $3,600.00 | $4,140.00 | $3,600.00 | |
| 25 | 25200110 | SODDING SALT TOLERANT | 85 | SQ YD | $48.00 | $48.00 | $55.20 | $48.00 | |
| 26 | 25200200 | SUPPLE WATERING | 1 | UNIT | $35.00 | $35.00 | $40.25 | $35.00 | |
| 27 | 28000250 | TEMP EROS CONTR SEED | 25 | POUND | $15.00 | $15.00 | $17.25 | $15.00 | |
| 28 | 28000400 | PERIMETER EROS BAR | 200 | FOOT | $3.50 | $3.50 | $4.03 | $3.50 | |
| 29 | 28000510 | INLET FILTERS | 4 | EACH | $275.00 | $275.00 | $316.25 | $275.00 | |
| 30 | 28001100 | TEMP EROS CONTR BLANK | 120 | SQ YD | $2.90 | $2.90 | $3.34 | $2.90 | |
| 31 | 30300001 | AGG SUBGRADE IMPROVE | 8 | CU YD | $107.00 | $87.60 | $80.00 | $190.00 | |
| 32 | 30300112 | AGG SUBGRADE IMPR 12 | 105 | SQ YD | $22.50 | $69.85 | $40.00 | $50.00 | |
| 33 | 35800100 | PREPARATION OF BASE | 415 | SQ YD | $6.00 | $1.00 | $15.00 | $4.50 | |
| 34 | 35800200 | AGG BASE REPAIR | 5 | TON | $202.00 | $101.00 | $85.00 | $125.00 | |
| 35 | 42000080 | PVT CON PCC BR APP SL | 75 | SQ YD | $195.00 | $246.05 | $175.00 | $325.00 | |
| 36 | 42000416 | PCC PVT 9 3/4 JOINTD | 64 | SQ YD | $150.00 | $261.15 | $175.00 | $210.00 | |
| 37 | 42001300 | PROTECTIVE COAT | 140 | SQ YD | $2.50 | $3.75 | $8.00 | $2.00 | |
| 38 | 44000100 | PAVEMENT REM | 120 | SQ YD | $12.50 | $43.30 | $55.00 | $48.00 | |
| 39 | 44000500 | COMB CURB GUTTER REM | 175 | FOOT | $9.00 | $10.80 | $25.00 | $16.00 | |
| 40 | 44000600 | SIDEWALK REM | 407 | SQ FT | $2.00 | $6.60 | $20.00 | $4.00 | |
| 41 | 50101500 | REM EXIST SUP-STR | 1 | EACH | $75,000.00 | $175,000.00 | $225,000.00 | $300,000.00 | |
| 42 | 50102400 | CONC REM | 24.1 | CU YD | $1,350.00 | $1,621.45 | $1,400.00 | $2,100.00 | |
| 43 | 50200100 | STRUCTURE EXCAVATION | 20 | CU YD | $40.00 | $130.50 | $125.00 | $100.00 | |
| 44 | 50300225 | CONC STRUCT | 35.3 | CU YD | $1,564.00 | $2,156.30 | $1,568.00 | $2,100.00 | |
| 45 | 50300255 | CONC SUP-STR | 180.1 | CU YD | $2,100.00 | $1,061.75 | $2,016.00 | $1,250.00 | |
| 46 | 50300260 | BR DECK GROOVING | 340 | SQ YD | $14.00 | $12.25 | $18.00 | $12.00 | |
| 47 | 50300300 | PROTECTIVE COAT | 645 | SQ YD | $2.50 | $2.80 | $4.00 | $2.00 | |
| 48 | 50301350 | CONC SUPSTR APP SLAB | 5.7 | CU YD | $2,250.00 | $1,500.00 | $1,600.00 | $1,975.00 | |
| 49 | 50800205 | REINF BARS, EPOXY CTD | 56,590 | POUND | $1.57 | $1.65 | $2.15 | $1.65 | |
| 50 | 50900105 | ALUM RAILING TY L | 272 | FOOT | $195.29 | $208.00 | $224.58 | $300.00 | |
| 51 | 51500100 | NAME PLATES | 1 | EACH | $550.00 | $863.15 | $672.00 | $650.00 | |
| 52 | 58600101 | GRANULAR BACKFILL STR | 20 | CU YD | $40.00 | $104.40 | $125.00 | $225.00 | |
| 53 | 66900200 | NON SPL WASTE DISPOSL | 85 | CU YD | $81.00 | $129.60 | $125.00 | $100.00 | |
| 54 | 66900530 | SOIL DISPOSAL ANALY | 2 | EACH | $700.00 | $1,540.00 | $805.00 | $1,550.00 | |
| 55 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $3,900.00 | $2,500.00 | $4,485.00 | $2,500.00 | |
| 56 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $1,000.00 | $2,300.00 | $1,150.00 | $2,300.00 | |
| 57 | 66901006 | REG SUB MON | 45 | CAL DA | $690.00 | $887.00 | $100.00 | $900.00 | |
| 58 | 67100100 | MOBILIZATION | 1 | L SUM | $90,000.00 | $95,270.00 | $70,000.00 | $90,000.00 | |
| 59 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $40.00 | $40.00 | $40.25 | $40.00 | |
| 60 | 81702130 | EC C XLP USE 1C 6 | 450 | FOOT | $6.65 | $6.65 | $3.45 | $5.00 | |
| 61 | 83600200 | LIGHT POLE FDN 24D | 8 | FOOT | $425.00 | $425.00 | $690.00 | $1,445.00 | |
| 62 | 84200804 | REM POLE FDN | 1 | EACH | $3,750.00 | $3,750.00 | $460.00 | $1,425.00 | |
| 63 | 84400105 | RELOC EX LT UNIT | 1 | EACH | $2,880.00 | $2,880.00 | $5,175.00 | $7,100.00 | |
| 64 | 89502300 | REM ELCBL FR CON | 350 | FOOT | $3.22 | $3.25 | $4.60 | $1.75 |